*285 PEDEN, Justice.

Suit by subcontractor E. J. Downs for losses occasioned by cancellation of two contracts to pave parking areas. Nixon Construction Co. as general contractor and D. H. Overmyer Warehouse Co. as owner of the premises were Defendants, and they have perfected this appeal from an adverse judgment based on a jury verdict.

E. J. Downs, the appellee, entered into two contracts on March IS, 1966 with Nixon, each contract requiring him to provide a ten-inch base and asphalt topping on certain parking areas adjoining a warehouse being built for Overmyer, who approved the contracts. The first contract covered job number 426.08 and the second covered job number 426.09. The contracts contained identical provisions, one of which was: “11. The General Contractor shall give the Subcontractor reasonable time to settle any labor disputes, but if the Subcontractor has a work stoppage for a period of over 3 days, for any reason, the General Contractor shall have the right to have said work performed by others at the expense of the Subcontractor.”

Work under job 426.08 was completed and Downs received payment for all of the amount for which he billed Nixon under the contract except $1,605.81 retained by Nixon and Overmyer in accordance with the contract’s provisions. After several delays, which Downs testified were caused by heavy rains, work on job 426.09 was terminated on May 27, 1966 when Downs received a telegram signed by Nixon’s regional manager; the parties have also stipulated that it was sent by “Nixon- Construction Co. and/or Overmyer Warehouse Co.” It stated: “Dear sir, due to soil conditions and weather it has been determined that concrete paving in lieu of asphalt is necessary to support anticipated loads contemplated for warehouse operations. Therefore this will serve as notice to cease all future paving operations.”

In response to special issues, the jury found 1) that Downs was at all times ready, willing and able to perform in accordance with the terms and conditions of the contracts, 2) that Nixon and Overmyer by their conduct waived the three-day work stoppage provisions of the contracts, 3) that the work performed by Downs and his employees stopped for over three days during the period after he began work under one of the contracts in question and prior to May 27, 1966; the jury did not find 4) that Downs failed to have- men and equipment on the job performing the work on job 426.09 in a workmanlike manner according to standard procedures so as to complete the job by the time as directed by a representative of Nixon. The jury did find 5) that $1,605.81 was still due and owing to Downs by Nixon and Overmyer under- the contracts before those defendants terminated them, and 6) that Downs would have derived $17,225.00 in profits from his performance of the contracts had they not been terminated by Nixon and Overmyer.

Appellants’ first three points of error are “no evidence”, “insufficient evidence” and “against the great weight of the evidence” assignments with respect to the jury’s answer to Special Issue Number 2. Appellants make the same assignments of error as to the jury’s answers to Special Issues 1, 5 and .6.

Appellants’ first three points, which concern the jury’s finding that they waived the three-day work stoppage provision of the contract, are overruled. We hold that the provision, which we have noticed as item 11 of the contract, was not available to Nixon and Overmyer as a defense under the facts of this case. Item 11 permitted Nixon to have “said work” performed by others at the expense of the subcontractor, but it did not authorize Nixon and Over-myer to cancel Downs’ contract and go to a different type of construction (as they did) without compensating Downs for his loss of anticipated profits. If Nixon had invoked item 11 and required Downs to pay for having another subcontractor complete the asphalt paving, the substitute subcontractor’s price for the job might have been so low as to increase Downs’ profit.

*286 Even if Special Issue Number 2 were an ultimate issue in this case, however, we would hold that the evidence supports the jury’s answer to it. Downs testified that after the last work stoppage (which he said was caused by rain), Nixon’s superintendent directed Downs’ men and equipment in work on job 426.09 for at least three full days before May 27, the day the telegram which halted paving operations was sent and received.

“A waiver takes place where one dispenses with the performance of something which he has a right to exact, and occurs where one in possession of any right, whether conferred by law or by contract, with full knowledge of the material facts, does or forbears to do something, the doing of which or the failure or forbearance to do which is inconsistent with the right or his intention to rely upon it. 92 C.J.S. p. 1061. Waiver, of course, is a matter or question of intention.” Ford v. Culbertson, 158 Tex. 124, 308 S.W.2d 855, at 865 (1958).

“A waiver, involving as it does the. idea of intention, may be express or implied. Waiver may be shown by such conduct as will warrant the inference of the relinquishment of a known right. But waiver by implication will be applied only to prevent fraud or inequitable consequences. To establish an implied waiver of a legal right, there must be a clear, unequivocal, and decisive act of the party showing such a purpose or acts amounting to an estoppel on his part. In the absence of an express renunciation a waiver will not be presumed , or implied contrary to the intention of the party whose rights would be injuriously affected thereby, unless by his conduct the opposite party has been misled to his prejudice into the honest belief that such waiver was intended or consented to.” 60 Tex.Jur.2d 191-192, Waiver, § 9.

It is also noted that the telegram made no reference to the three-day work stoppage provision of the contracts, but stated that the reason for ceasing paving operations was that soil and weather conditions had caused defendants (appellants) to decide to pave with concrete instead of asphalt.

Mr. Nixon, who had been connected with Nixon Construction Co. when this controversy arose, testified that the telegram was sent to terminate the contract because Downs had not been on the job on the days specified in the contract. We conclude that Nixon’s testimony was not of such force that the jury’s answer to the second special issue was against the great weight and preponderance of the evidence even if it be considered an ultimate issue.

Appellants’ points relative to the first special issue are also overruled. Appellants assert in support of these points that the parties mutually rescinded the contract, but we find no evidence of rescission on the part of Downs. Also, he testified that when he received the telegram of May 27 he was ready, willing and able to perform under the terms of the contract.

We hold that the evidence supports the jury’s finding in response to the fifth special issue, that Nixon and Overmyer owed Downs $1,605.81 when he received the telegram on May 27. It is undisputed that such amount had been retained by the appellants on job 426.08 pursuant to the contract’s provision that the “General Contractor and the Owner shall retain 10% of the amount due on each payment until final payment becomes due” plus another re-tainage of 5%.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Elena Markovsky v. Kirby Tower, L. P.
Court of Appeals of Texas, 2011
Conoco, Inc. v. Amarillo National Bank
950 S.W.2d 790 (Court of Appeals of Texas, 1997)
Robinson v. Robinson
961 S.W.2d 292 (Court of Appeals of Texas, 1997)
Webster v. Lipsey
787 S.W.2d 631 (Court of Appeals of Texas, 1990)
Federal Deposit Insurance Corp. v. Attayi
745 S.W.2d 939 (Court of Appeals of Texas, 1988)
Cox v. Bancoklahoma Agri-Service Corp.
641 S.W.2d 400 (Court of Appeals of Texas, 1982)
Fisher v. First National Bank of Memphis
584 S.W.2d 515 (Court of Appeals of Texas, 1979)
D. H. Overmyer Co. v. Harbison
453 S.W.2d 368 (Court of Appeals of Texas, 1970)
South Builders, Inc. v. Brown
449 S.W.2d 542 (Court of Appeals of Texas, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
441 S.W.2d 284, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nixon-construction-co-v-downs-texapp-1969.