D. H. Overmyer Co. v. Harbison

453 S.W.2d 368, 1970 Tex. App. LEXIS 2481
CourtCourt of Appeals of Texas
DecidedApril 1, 1970
Docket6070
StatusPublished
Cited by4 cases

This text of 453 S.W.2d 368 (D. H. Overmyer Co. v. Harbison) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D. H. Overmyer Co. v. Harbison, 453 S.W.2d 368, 1970 Tex. App. LEXIS 2481 (Tex. Ct. App. 1970).

Opinion

OPINION

WARD, Justice.

Appellee, a sub-contractor, brought this suit to recover, primarily, upon a release bond executed pursuant to Article 5472c., Vernon’s Texas Civil Statutes, by D. H. Overmyer Warehouse Company (now D. H. Overmyer Company, Inc.), as principal, and Liberty Mutual Insurance Company, as surety, for the release of the appellee’s mechanic’s and materialman’s lien against certain real estate in El Paso upon which had been erected two warehouses. Upon trial to the court without a jury, judgment was entered in favor of the appellee against these two appellants for the sum of $5,-965.80, together with attorney’s fee in the amount of $2,250.00. We affirm the judgment of the trial court.

Appellee entered into five written contracts with Nixon Construction Company (a wholly-owned subsidiary of Green and White Construction Company) as the general contractor, to do certain work on premises owned by Overmyer, the contracts being approved by the owner. The one contract in question before us is dated November 23, 1965 and is for labor in excavation and laying a concrete slab in one of the warehouses. The contract is for $11,000.00 and the work was accepted by the owner on June 11, 1966. On this contract there is due and owing to the appellee the sum of $2,684.00. On the other four contracts, the correct performances of *370 which are not questioned, there are due additional sums, to make the total of $5,965.-80 owing the appellee if he should prevail. Appellee filed his mechanic’s and material-man’s lien in September, 1966 on the property in question, in accordance with Article 5453; and thereafter, on May 29, 1967, Ov-ermyer, as principal, and the insurance company as surety, executed their bond to release the property pursuant to Article 5472, in the amount of $11,950.00 in favor of the appellee, conditioned that these appellants would pay the appellee the amount of his lien and all costs in the event the same was proved to be a lien on the property. The trial court allowed a judgment such as was approved by this court in Nixon Construction Company and D. H. Over-myer Co., Inc. v. Rosales, 437 S.W.2d 52 (1969, wr.ref. n. r. e.). No findings of fact and conclusions of law were filed by the trial court and none were requested, but the court in its judgment, did find that the work performed by appellee was performed and completed in a good and workmanlike manner; that the appellee’s lien was fixed and established in accordance with law; that the release bond in favor of the appellee was executed in compliance with Article 5472c.; that appellee timely filed suit upon the bond; that appellee’s lien in the amount of $5,965.80 had been proved and that a reasonable attorney’s fee amounted to $2,250.00.

The appellants’ points consist of “no evidence” and “insufficient evidence” points relating to the fact that the appellee never obtained the owner’s consent to any changes in the plans and specifications which occurred during the construction. The written contracts contain the following provision:

“Any changes, alterations or deviations from the final plans and specifications must be approved in writing by the owner, general contractor, and engineer before that part of the work is started.”

According to the appellee, as developed by his own attorney, during the laying of the concrete floor, only half of the control joints or construction joints were placed, rather than as were called for in the original plans and specifications in the flooring. Apparently the plans were changed during construction, and at no time were these changes ever approved in writing by the owner. However, there is no testimony before us as to the number of control joints called for by the original plans, nor any testimony as to the number actually placed in the floor. It is the appellants’ reasoning that recovery under the statutory release bond is allowed only upon the establishment of a valid lien by the sub-contractor, which lien is valid only if there was a substantial compliance with the subcontract terms, and there can be no substantial compliance with the subcontract terms as the concrete work was not in accordance with the plans and specifications, which were changed without the owner’s written consent.

It is the general rule that a stipulation, in a private building or construction contract, that changes, alterations or deviations must be ordered in writing, is valid and binding upon the parties and, therefore, so long as such a provision remains in effect, no recovery can be had for the alterations done without a written order in compliance therewith. As stated in Magee v. I. & G. N. Wood & Coal Co., 269 S.W.2d 498, 505 (Tex.Civ.App., San Antonio 1954, wr.ref. n. r. e.) :

“A man contracting for a modest cottage can not be made to pay for a mansion, because a judicial tribunal thinks it suitable for him, nor should a man be required to accept inferior and different materials and workmanship when he has contracted otherwise.”

See Uhlhorn v. Reid, 398 S.W.2d 169 (Tex.Civ.App., San Antonio 1965, wr.ref., n. r. e.); Chambless v. J. J. Fritch, General Contractor, Inc., 336 S.W.2d 200 (Tex.Civ.App., Dallas 1960, wr.ref., n. r. e.), and the extensive annotation, 2 A.L.R.3rd 620, 631.

*371 Three reasons are apparent why the general rule does not apply to our present case. In the first place, we are unable to see where the deviation or alteration was within the meaning of the contract under consideration. This contract was only that this sub-contractor would furnish all the labor, equipment and supervision necessary to complete the cement flooring; and except for furnishing tie wire, all material in the construction was to be furnished by the general contractor. The plans and specifications are not a part of the record, and we have no description before us as to the type of control or construction joints in this floor. If this were some device such as the rod or dowel type, then under this contract the general contractor would have been obligated to furnish them. If the general contractor changed the plans and specifications to eliminate half of the control joints or construction joints, this did not obligate the sub-contractor to furnish them. This would then relate to matters outside the scope of the sub-contract and involves a dispute only between the owner and the general contractor, who is also now owned by the owner-appellant.

In the second place, there has been an effective expressed waiver as was defined in Nixon Construction Co. and D. H. Overmyer Warehouse Co. v. Downs, 441 S.W.2d 284 (Tex.Civ.App., Houston 1969, n. w. h.):

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
453 S.W.2d 368, 1970 Tex. App. LEXIS 2481, Counsel Stack Legal Research, https://law.counselstack.com/opinion/d-h-overmyer-co-v-harbison-texapp-1970.