Sorenson v. Dager

601 N.W.2d 564, 8 Neb. Ct. App. 729, 1999 Neb. App. LEXIS 282
CourtNebraska Court of Appeals
DecidedOctober 12, 1999
DocketA-98-628
StatusPublished
Cited by31 cases

This text of 601 N.W.2d 564 (Sorenson v. Dager) is published on Counsel Stack Legal Research, covering Nebraska Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sorenson v. Dager, 601 N.W.2d 564, 8 Neb. Ct. App. 729, 1999 Neb. App. LEXIS 282 (Neb. Ct. App. 1999).

Opinion

Carlson, Judge.

INTRODUCTION

Lon Sorenson (Sorenson), doing business as Sorenson Construction, appeals from a January 28,1998, order of the district court for Lancaster County, denying his request to foreclose his construction lien on property owned by James Dager (Dager) and Ginger Sanders Dager, and Norwest Bank Nebraska, N.A. (Norwest). For the reasons set forth below, we reverse, and remand with directions.

BACKGROUND

On April 9, 1996, Sorenson filed a petition for foreclosure of a construction lien under the Nebraska Construction Lien Act, Neb. Rev. Stat. §§ 52-125 to 52-159 (Reissue 1998). In Sorenson’s petition, he alleged that he is an individual doing business as Sorenson Construction and that the Dagers are owners of real property located at 2525 Ridge Road, Lincoln, Nebraska. Sorenson alleged that he contracted with Michael Niemeyer, doing business as Mike’s Custom Homes & Remodels, to furnish materials and services with respect to the *731 Dagers’ property. Sorenson alleged that Niemeyer failed to pay him $22,668.25. Sorenson alleged that he had not pursued a proceeding at law to recover the amount owed.

Sorenson requested that the district court enter a decree of foreclosure directing that the Dagers’ property be sold and the proceeds applied to satisfy his lien. In addition to recovering the $22,668.25, Sorenson requested the reasonable costs of abstracting the property and costs of his action.

On July 19, 1996, Sorenson filed a motion for default judgment against Norwest because Norwest had failed to appear or otherwise plead within 30 days. The trial court subsequently granted Sorenson’s motion for default judgment against Norwest.

On December 9, 1996, the Dagers filed an answer and counterclaim. In the Dagers’ answer, they requested that Sorenson’s petition be dismissed with prejudice. In their counterclaim, the Dagers stated that because Sorenson failed to complete the framing on their house, they were required to have Niemeyer complete the work. The Dagers stated that this cost them an additional $26,246 and that such amount should be set off against the amount requested by Sorenson. The Dagers also alleged that Sorenson and his employees performed framing work which was faulty and unworkmanlike and that such work caused several delays in the construction of their house.

On December 16, 1996, Sorenson filed a reply and answer, which set out several affirmative defenses to the Dagers’ counterclaim and requested that the Dagers’ counterclaim be dismissed with prejudice.

Trial was held on October 9, 1997. The evidence presented at trial shows the following: In 1991 or 1992, Dager contacted Niemeyer, a general contractor, and asked him generally if he was interested in helping Dager build his new house. In late 1994 or early 1995, Dager and Niemeyer entered into more serious discussions. At that time, Dager requested that Niemeyer solicit bids for certain portions of the construction project, including the framing of the house. In late February or early March 1995, Niemeyer contacted Sorenson to do the framing work on the Dagers’ house. The record shows that Sorenson orally provided Niemeyer with a figure of $72,840 for the fram *732 ing and that Niemeyer used the $72,840 figure in a proposed contract submitted to the Dagers. At trial, Sorenson attempted to show that the $72,840 was merely a cost estimate, while the Dagers, through Niemeyer’s testimony, attempted to show that the $72,840 was a firm “bid.”

At trial, on direct examination, Niemeyer testified that he specifically asked Sorenson for a bid on the project, telling Sorenson, “ ‘We need to get a bid on this plan so we can get the house started.’ ” Although, on cross-examination, Niemeyer testified that the figure Sorenson provided might have been an estimate. Niemeyer testified that he had previously worked with Sorenson on a bid basis and that on each occasion, he received a written bid from Sorenson. Niemeyer testified that he did not receive a written bid from Sorenson at any time on the Dagers’ house.

Sorenson testified that he told Niemeyer that he would not do the job on a bid basis, only on an estimate basis. Sorenson testified that Niemeyer agreed to pay him a monthly draw of $15,000 and that he and Niemeyer agreed that when Sorenson and his crew completed framing, Sorenson would submit a final bill to Niemeyer. Sorenson testified that this bill would show in detail the hours his crew worked and the cost of the materials used, and that he and Niemeyer would settle up at this point.

The record shows that Sorenson and his crew started framing the Dagers’ house sometime in August 1995 and that by the time Sorenson and his crew arrived, Niemeyer and his crew had completed a majority of the basement framing.

At trial, Niemeyer testified that he told Sorenson that he would be billing Sorenson for the framing work Niemeyer and his crew had completed on the basement and that this figure would be deducted from the $72,840 figure Sorenson had provided Niemeyer. Sorenson testified that he thought that he was going to be paid on an hourly basis and that nothing Niemeyer and his crew did before he and his crew arrived would affect their pay. Sorenson testified that he assumed that the Dagers would pay Niemeyer and his crew for their framing.

The record shows that Niemeyer paid Sorenson $10,000 in August 1995 (because Sorenson and his crew worked a partial month), $15,000 in September, and $15,000 in October. The *733 record shows that a conflict arose in December when Sorenson requested that Niemeyer pay him $15,000 for the November work.

Niemeyer testified that he told Sorenson prior to December 1995 that they needed to sit down and figure out how many hours Niemeyer and his crew had spent framing. Niemeyer testified that he told Sorenson that this amount needed to be deducted from the $72,840 figure Sorenson gave him and that Sorenson told him that he would take care of it. Niemeyer testified that Sorenson never did so. Niemeyer testified that in addition to the framing he and his crew completed on the basement before Sorenson’s arrival, he and his crew framed for approximately 2 weeks in September.

Niemeyer testified that by his calculations, he and his crew had done approximately $15,338 worth of framing and that after deducting this amount and the payments made to Sorenson in August, September, and October 1995, he owed Sorenson a balance of approximately $17,000. The record shows that Niemeyer did not pay Sorenson $15,000 in December because of Dager’s concern that Sorenson’s draws were starting to exceed the bid price and because there was still a lot of framing to do. Niemeyer testified that instead, he did as Dager instructed and paid Sorenson $5,000.

Similarly, Sorenson testified that after he requested payment from Niemeyer for November 1995, Niemeyer gave him a check for $5,000 and a bill for $15,338. Sorenson testified that he attempted to cash the $5,000 check and that payment on the check had been stopped. Sorenson testified that at that point, he pulled his crew from the job and that Niemeyer failed to pay him any additional amounts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dolton Electric v. Ichtertz
Nebraska Court of Appeals, 2024
Nore Electric v. S & H Holdings
316 Neb. 197 (Nebraska Supreme Court, 2024)
DH-1, LLC v. City of Falls City
305 Neb. 23 (Nebraska Supreme Court, 2020)
Taylor v. Taylor
764 N.W.2d 101 (Nebraska Supreme Court, 2009)
In Re Worldcom, Inc.
382 B.R. 610 (S.D. New York, 2008)
Stark v. Soteria Imaging Services, Inc.
276 F. Supp. 2d 989 (D. Nebraska, 2003)
Omaha Construction Industry Pension Plan v. Children's Hospital
642 N.W.2d 849 (Nebraska Court of Appeals, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
601 N.W.2d 564, 8 Neb. Ct. App. 729, 1999 Neb. App. LEXIS 282, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sorenson-v-dager-nebctapp-1999.