Dolton Electric v. Ichtertz

CourtNebraska Court of Appeals
DecidedAugust 27, 2024
DocketA-23-885
StatusUnpublished

This text of Dolton Electric v. Ichtertz (Dolton Electric v. Ichtertz) is published on Counsel Stack Legal Research, covering Nebraska Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dolton Electric v. Ichtertz, (Neb. Ct. App. 2024).

Opinion

IN THE NEBRASKA COURT OF APPEALS

MEMORANDUM OPINION AND JUDGMENT ON APPEAL (Memorandum Web Opinion)

DOLTON ELECTRIC V. ICHTERTZ

NOTICE: THIS OPINION IS NOT DESIGNATED FOR PERMANENT PUBLICATION AND MAY NOT BE CITED EXCEPT AS PROVIDED BY NEB. CT. R. APP. P. § 2-102(E).

DOLTON ELECTRIC, L.L.C., APPELLEE AND CROSS-APPELLANT, V.

DOLF R. ICHTERTZ AND CAROL J. ICHTERTZ, APPELLANTS AND CROSS-APPELLEES.

Filed August 27, 2024. No. A-23-885.

Appeal from the District Court for Hall County: PATRICK M. LEE, Judge. Affirmed. Jared J. Krejci, of Smith, Johnson, Allen, Connick & Hansen, for appellants. Robert S. Lannin, J. Michael Hannon, and Tyler R. Rademacher, of Baylor, Evnen, Wolfe & Tannehill, L.L.P., for appellee.

MOORE, RIEDMANN, and BISHOP, Judges. MOORE, Judge. I. INTRODUCTION Dolf R. Ichtertz and Carol J. Ichtertz appeal from the order of the district court for Hall County which entered judgment in favor of Dolton Electric, L.L.C., on its claim for unjust enrichment. Dolton Electric has cross-appealed, assigning error to the court’s denial of its contractual claims and failure to award the full amount sought on Dolton Electric’s unjust enrichment claim. We affirm. II. STATEMENT OF FACTS On September 9, 2018, Dolton Electric and Salvador L. Mendoza, d/b/a Premier Plumbing, filed a complaint in the district court against the Ichtertzes, setting forth claims for suit on account stated, breach of contract, and foreclosure of a construction lien in connection with work they performed on a remodeling project at certain real property owned by the Ichtertzes in Grand Island,

-1- Nebraska. Dolton Electric was the only plaintiff identified in a subsequent amended complaint, which added a claim for unjust enrichment. In the amended complaint, Dolton Electric sought judgment of $21,721.88 against the Ichtertzes. Dolton Electric filed a second amended complaint on the morning of trial, alleging that on or about May 23, 2016, Jake’s Construction and the Ichtertzes entered into an oral contract in which Jake’s Construction was to provide construction services for a whole home remodel of the Ichtertzes’ home, and that to complete that construction project, Jake’s Construction engaged the services of Dolton Electric as a subcontractor. Dolton Electric alleged that it was hired to complete electrical wiring for lighting in various portions of the Ichtertzes’ property and for various other electrical projects; that on June 21, it substantially performed all work “under the parties’ remodeling contract,” including work completed by Dolton Electric “at the specific request and control by” the Ichtertzes; and that it performed all work in a workmanlike manner. Dolton Electric alleged that on July 7, an invoice was provided to the Ichtertzes; that on September 13, the Ichtertzes notified Jake’s Construction that they would not pay the invoice, which included Dolton Electric’s invoiced amount; that a construction lien was subsequently filed against the property with respect to the remodeling contract; and that Dolton Electric was later assigned the rights of Jake’s Construction under the lien. Finally, Dolton Electric alleged that it had fully performed the contract and that the Ichtertzes had failed to perform their obligations by failing to pay for labor and materials provided under the contract. In the second amended complaint, Dolton withdrew the construction lien foreclosure claim, amended its prayer for damages to $24,144.38, and included a request for pre-judgment interest in the suit on account stated claim. Trial was held before the district court on August 3, 2023. The court received exhibits offered by the parties and heard testimony from Aaron Dolton (Aaron), the owner of Dolton Electric; the Ichtertzes; and Jim Hoag, an electrician who worked on the remodeling project prior to Dolton Electric. The Ichtertzes have owned the property in question since December 1999, and they resided there at the time of trial. Between about 2002 and 2004, the Ichtertzes undertook significant renovation of the property. During the renovation, they stayed at a house they owned next door. The Ichtertzes directly hired various contractors to work on remodeling the property, including someone who did insulation and drywall work, and electrician Jim Hoag. Sometime between 2011 and 2013, the Ichtertzes engaged Jeremy Jakubowski, the owner of Jake’s Construction, “to do the bathrooms and sequential stuff” at the property. Jakubowski and his father had previously “put a brick wall in” at the property and had done work on other property owned by the Ichtertzes. Once Jakubowski began work on the bathrooms on the property, the scope of the remodeling project expanded to include other areas of the house. Dolf viewed Jake’s Construction as a general contractor, noting that Jakubowski “had the permits and stuff and he was bringing in the subcontractors,” but Dolf did not recall having “anything beyond that formally,” like a written contract with Jake’s Construction. Jake’s Construction remained on the project until late summer 2016. For electrical work on the remodeling project, the Ichtertzes initially hired Hoag, who had done other work for them in the past. Although Hoag completed “[q]uite a bit” of electrical work at the Ichtertzes’ house, at some point he left the project and Dolton Electric took over the electrical work. The witnesses presented conflicting testimony about the transition from Hoag to Dolton

-2- Electric. When asked about how Dolton Electric became involved in the project in 2016, Dolf testified that they “were trying to get the project done” and were told by Jakubowski that Hoag was too busy to complete the project. Carol testified that Jakubowski told her “Hoag wasn’t available.” According to Aaron, the Ichtertzes “requested a new electrician that had good ideas, better ideas, new modern ideas, than the electrician they had that was wiring the house at the time.” Hoag’s testimony about the transition is less clear. Hoag testified that he “never really stopped” his work prior to the transition, but that at some point he saw Aaron at the house and “got the impression” Aaron wanted to finish the project, which he “didn’t have a problem with . . . because [he] was kind of busy anyway.” Jakubowski, who had been a high school classmate of Aaron’s, introduced Aaron to the Ichtertzes. At the time, Aaron was based in Lincoln, Nebraska, did not have a driver’s license, and had to have his apprentice drive him. Dolf testified that he explained to Jakubowski that he was not going to pay for fuel or travel since there were local service providers Jakubowski could hire. Carol also testified that she told Jakubowski they would not pay for travel. After the introduction by Jakubowski, Aaron met with the Ichtertzes and “went over some ideas that [he] had that [he] would do if [he] was the electrician on the job.” According to Aaron, the Ichtertzes “agreed” and said, “you’ve got the job,” and “[t]here was a hand shake.” When Aaron left, his understanding was that he had been hired by the Ichtertzes to complete the electrical duties on the project. Aaron stated that Jakubowski was “just the guy doing the main construction work,” “not the one to say, hey, you have the job,” and testified that he “had to be hired by [the Ichtertzes].” Aaron testified that before starting work on the project, he also called Hoag “to make sure that [he] was not stepping on [Hoag’s] toes or overstepping [his] boundaries,” to see if Hoag was “okay with [Dolton Electric] taking it over,” and to let Hoag know he did not “want to take a job from him.” Aaron testified that Hoag told him, “yes, the job is yours, go for it.” Hoag did not remember receiving such a phone call. There was no written contract between Dolton Electric and the Ichtertzes (or between Dolton Electric and Jake’s Construction).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lindsay Manufacturing Co. v. Universal Surety Co.
519 N.W.2d 530 (Nebraska Supreme Court, 1994)
Andrews Electric Company v. Farm Automation, Inc.
198 N.W.2d 463 (Nebraska Supreme Court, 1972)
Sorenson v. Dager
601 N.W.2d 564 (Nebraska Court of Appeals, 1999)
RM Campbell Indus. v. Midwest Renewable Energy
886 N.W.2d 240 (Nebraska Supreme Court, 2016)
Armstrong v. Clarkson College
297 Neb. 595 (Nebraska Supreme Court, 2017)
Crossman & Hosford v. Harbison
25 Neb. Ct. App. 849 (Nebraska Court of Appeals, 2018)
Bloedorn Lumber Co. of N. Platte, Corp. v. Nielson
300 Neb. 722 (Nebraska Supreme Court, 2018)
Bloedorn Lumber Co. v. Nielson
300 Neb. 722 (Nebraska Supreme Court, 2018)
DH-1, LLC v. City of Falls City
305 Neb. 23 (Nebraska Supreme Court, 2020)
Benjamin v. Bierman
305 Neb. 879 (Nebraska Supreme Court, 2020)
Wizinsky v. State
308 Neb. 778 (Nebraska Supreme Court, 2021)
Moore v. Nebraska Acct. & Disclosure Comm.
310 Neb. 302 (Nebraska Supreme Court, 2021)
Humphrey v. Smith
974 N.W.2d 293 (Nebraska Supreme Court, 2022)
Zook v. Zook
978 N.W.2d 156 (Nebraska Supreme Court, 2022)
132 Ventures v. Active Spine Physical Therapy
313 Neb. 45 (Nebraska Supreme Court, 2022)
Slama v. Slama
987 N.W.2d 257 (Nebraska Supreme Court, 2023)
Uhrich & Brown Ltd. Part. v. Middle Republican NRD
998 N.W.2d 41 (Nebraska Supreme Court, 2023)
SID No. 596 v. THG Development
315 Neb. 926 (Nebraska Supreme Court, 2024)
Nebraska Journalism Trust v. Dept. of Envt. & Energy
316 Neb. 174 (Nebraska Supreme Court, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
Dolton Electric v. Ichtertz, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dolton-electric-v-ichtertz-nebctapp-2024.