Peters v. Halligan

152 N.W.2d 103, 182 Neb. 51, 1967 Neb. LEXIS 443
CourtNebraska Supreme Court
DecidedJuly 7, 1967
Docket36492
StatusPublished
Cited by45 cases

This text of 152 N.W.2d 103 (Peters v. Halligan) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Peters v. Halligan, 152 N.W.2d 103, 182 Neb. 51, 1967 Neb. LEXIS 443 (Neb. 1967).

Opinions

White, C. J.

The defendants Halligan appeal from a judgment of the district court foreclosing a mechanic’s lien for labor and materials in the sum of $1,576.82 furnished in the construction of a basement on defendants’ property.

In his petition plaintiff alleges that he was employed to construct and furnish the material for a basement on the defendants’ premises and that the fair and reasonable value of the labor and material charges was in the sum of $1,576.82. Defendants, in an answer and cross-petition, allege that the plaintiff did perform work and labor on their premises under an oral contract; that the plaintiff entered into an oral contract with the defendants to construct a basement and a frame addition to the trailer home of the defendants for the agreed sum of $2,850; that thereafter the plaintiff did construct the basement; that it was defectively constructed by reason of the failure of the plaintiff to properly seal and [53]*53waterproof the floor; that after construction of the basement plaintiff refused to construct the, frame addition to defendants’ trailer as provided under the oral contract; that the defendants were required to employ another contractor to construct the, trailer house addition; and that by reason of the defective construction work in the basement and the additional cost of constructing the trailer house addition they were damaged in the sum of $1,968.20.

Outside, the question of defective workmanship in the construction of the basement, the basic question involved in this case is whether the parties entered into a contract for an agreed price for the, construction of a basement and the trailer house addition. In approaching this problem, we bear in mind th'e basic rule that a fundamental and indispensable basis of any enforceablei agreement is that there be a meeting of the minds of the parties as to the essential terms and conditions of the proposed contract. Voss v. Linn, 171 Neb. 32, 105 N. W. 2d 383; Griggs v. Oak, 164 Neb. 296, 82 N. W. 2d 410. The evidence in this case is in irreconcilable conflict consisting of the testimony of Peters and the, defendant Clinton J. Halligan. A few days prior to August 25, 1965, the Halligans contacted Peters in Ogallala, Nebraska, about the building of an addition on their trailer house which, at that time, was located on their parent’s property but which they planned to move to their property south of Brule, Nebraska. Peters told them that he was building a house at that time; that he did not know whether he had time to do the job; and that he had never done anything like that before. In response to the Halligans’ request, Peters went out to the trailer house to discuss the matter with them. At this time they talked about moving one wall of the trailer out to form the outside wall of the new addition and filling in the ends and the ceiling. They discussed the sub-floor and the flooring, the stairwell location in the basement, the moving and possible installation of cup[54]*54boards, and various other details as to the addition. At this time, the Halligans stated they wanted a basement under the trailer house that was to be, constructed on their property south of Brule on which the trailer was to be moved, and there was discussion of the details of the basement construction. Peters testified that the main thing that the Halligans were interested in was to get the basement done so they could get the trailer moved to their property south of Brule. After this conversation the parties visited the Halligan place south of Brule to inspect the construction site. The basement under the trailer house was to be 20 fe,et by 48 feet and the basement under the new addition was to be 12 feet by 22 feet. Peters’ attention was called to a spring located close to the proposed site of the basement and to a wet spot at the site of the excavation. Peters told Halligan that in order to prevent any water problem he was going to put in a polyethylene seal.

Peters testified he told the Halligans, with reference to the construction of the addition, that he did not know actually when he could do it; that he could not give them any possible date; that at all times in his conversation with them he stressed there was no way he could give an exact figure because he did not know exactly what they had in mind; that he did not know what he might run into; that he had never done anything like that before; and that the cost of an ordinary basement was at least $1,000 for the blocks and laying.

It appears from the plaintiff’s evidence that he did not do any plumbing or electrical work and, in the preliminary negotiations, there was no discussion as to the electrical work or the plumbing other than hooking up a temporary toilet drain in the trailer prior to the time of the construction of the addition. The testimony is that the, defendants were securing an F.H.A. loan to finance the basement and the addition. Peters testified that in giving the Halligans a figure of $1,800 on the addition and a figure of $1,000 on the basement these [55]*55were only estimates and the defendants “would have to allow accordingly.” The evidence shows that there were no written plans or specifications for the building of the addition or the basement and none were ever introduced into evidence in this case. Peters testified that there were some, rough specifications in writing submitted to the F.H.A. for the loan but again the substance of his testimony is that this was a mere estimate and he could not give an exact figure because, he did not know exactly what they wanted and because he did not know what he might run into in building the addition.

Defendant Halligan’s testimony varies considerably from the plaintiff’s testimony. He testified that when Peters came out to discuss the addition they discussed “what ideas we had as far as the addition to the kitchen.” He says they discussed the size of the addition, the, construction and size of the basement, the floor covering, the details of the walls, the building of the walls out 12 fee,t from the trailer, the exterior to be aluminum covered, the interior to be of wood paneling, the ceiling, the placement of the stairway, the building of cabinets and their location, the installation of insulation and aluminum windows, the moving of the, sink, and the electrical outlets around the top of the counters. They made a trip to the basement site where they discussed the details of the, construction and Halligan advised Peters about the spring and asked him about a water problem in the basement. He says that the plaintiff was taking notes in a small notebook during this period of time and after these conversations Peters left and returned and told defendant Halligan that it would cost $1,850 to build the kitchen. He had previously given him a figure of $1,000 on the basement. Halligan told him that he needed these, figures for the F.H.A. in order to get a loan. He does not testify that they had a specific conversation or agreement that this would be the contract price. That inference must be drawn from the following testimony on the párt of Halligan: “When [56]*56he told us the figures that he had, we told him that was agreeable with us, and asked him when he could start construction, * *

We observe that no explanation appears as to why the defendant Halligan’s wife did not testify in this case and corroborate his testimony. We observe further that Peters’ repeated and precise testimony that the figures he furnished the Halligans were only estimates and the reasons he gave therefor stand undenied in the, record by Halligan.

The basement was finished about October 25, 1965.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Becher v. Hunt Irrigation
Nebraska Court of Appeals, 2019
Bloedorn Lumber Co. v. Nielson
300 Neb. 722 (Nebraska Supreme Court, 2018)
Bloedorn Lumber Co. of N. Platte, Corp. v. Nielson
300 Neb. 722 (Nebraska Supreme Court, 2018)
Gibbons Ranches v. Bailey
289 Neb. 949 (Nebraska Supreme Court, 2015)
Stitch Ranch v. Double B.J. Farms
Nebraska Court of Appeals, 2013
Henggeler v. Brumbaugh & Quandahl, P.C.
894 F. Supp. 2d 1180 (D. Nebraska, 2012)
Sorenson v. Dager
601 N.W.2d 564 (Nebraska Court of Appeals, 1999)
Young v. Tate
442 N.W.2d 865 (Nebraska Supreme Court, 1989)
Meek v. Gratzfeld
389 N.W.2d 300 (Nebraska Supreme Court, 1986)
CHICAGO LUMBER CO. OF OMAHA v. Horner
317 N.W.2d 87 (Nebraska Supreme Court, 1982)
HOUSTEIN TRUCKING v. Sandhills Beef, Inc.
308 N.W.2d 331 (Nebraska Supreme Court, 1981)
Omaha National Bank v. Continental Western Corporation
274 N.W.2d 867 (Nebraska Supreme Court, 1979)
Mickelson & Mickelson Hay Contractors v. Christensen
246 N.W.2d 655 (Nebraska Supreme Court, 1976)
MICKELSON & MICKELSON, ETC. v. Christensen
246 N.W.2d 655 (Nebraska Supreme Court, 1976)
Paxton & Vierling Steel Co. v. Barmore
187 N.W.2d 590 (Nebraska Supreme Court, 1971)
Hooper v. City of Lincoln
163 N.W.2d 117 (Nebraska Supreme Court, 1968)
Peters v. Halligan
152 N.W.2d 103 (Nebraska Supreme Court, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
152 N.W.2d 103, 182 Neb. 51, 1967 Neb. LEXIS 443, Counsel Stack Legal Research, https://law.counselstack.com/opinion/peters-v-halligan-neb-1967.