Millsap v. Ball

46 N.W. 1125, 30 Neb. 728, 1890 Neb. LEXIS 159
CourtNebraska Supreme Court
DecidedNovember 11, 1890
StatusPublished
Cited by10 cases

This text of 46 N.W. 1125 (Millsap v. Ball) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Millsap v. Ball, 46 N.W. 1125, 30 Neb. 728, 1890 Neb. LEXIS 159 (Neb. 1890).

Opinion

Norval, J.

The record shows that on the 26th day of September, 1887, lots 6 and 7, block 5, Omaha View, were owned by Boggs & Hill, and on that day they sold the lots to the defendant A. F. Groves, for the sum of $2,600. The sum of $115 was paid in cash and time was given for the balance. Boggs & Hill delivered to Groves the following receipt and memorandum of the terms of sale:

“September 26, 1887.

“Received of A. F. Groves one hundred and fifteen ($115) dollars to apply on lots six and seven, block five, Omaha View, price of lots to be $2,600. Contract to be given for same when the foundations for buildings on said lots are commenced. Payable as follows: In five equal payments, on or before, at 8 per cent. Blouses to cost at least $600 to $700 each.

Boggs & Hiix.”

At the time of the sale'the lots were vacant and unimproved. Groves went into possession and contracted with the defendant Ball to erect four cottages on the lots. The buildings were constructed and the plaintiff Millsap and several of the subcontractors, who are defendants, filed their liens for materials furnished and labor performed for the construction of the buildings. This action was brought by A. Millsap against John Ball, the contractor, Boggs & Hill, the vendors, A. F. Groves, the vendee, and the several lien-holders, to foreclose his lien. Each lien-holder [731]*731filed a cross-petition setting up his lien upon the premises and buildings.

The defendants Boggs & Hill deny in their answer the claims of the mechanics and material-men, and admit that they made the agreement in writing with the defendant Groves (copied above) by which they agreed to sell to him the lots in controversy, and that the defendant Groves agreed to pay them therefor the sum of $2,600 in the manner following, to-wit: Cash, $116, and the balance in five equal payments.

The answer further states that it was agreed that, upon ■ the payment in full of' said sums of money, and certain taxes and interest, Boggs & Hill were to make to Groves a warranty deed for said premises; that Groves went into possession under said contract, and paid the cash payment of $115, and that said contract is in full force. Boggs & Hill claim a vendor’s lien on the lots and the buildings thereon superior to the liens of the mechanics and material-men.

The defendant Groves, for answer, denies that either of the parties to the action has any valid lien or interest in said property. He further sets up that he contracted with Ball to furnish all labor and materials, and erect four houses on the lots for the sum of $700; that about January 4, 1888, after partly completing the buildings, Ball abandoned, refused, and neglected to carry out the terms of the contract, and that neither Ball nor any one of the subcontractors have carried out the agreement; that the defendant Gi’oves, on the 15th day-of May, 1888, completed said buildings so far as practicable, considering the unworkmanlike manner in which the work was performed, and the inferiority of the materials furnished by Ball, and that all the mechanics’ liens were prematurely filed before the completion of the buildings. There 'are other allegations in the answer of Groves to which it is not necessary to refer.

[732]*732The court found that there was due from Groves to Boggs & Hill $2,485 as balance of purchase money, together with 8 per cent interest thereon from September 26, 1887. The court also found the amount due the various lien holders. A decree of foreclosure was rendered, which gave Boggs & Hill a paramount lien for the purchase money, and the premises were ordered sold and the proceeds applied, after the payment of costs, first, to the payment of the claim of Boggs & Hill, and the balance fro rata among the mechanic lien holders. The defendant Groves and the mechanic lien-holders appeal.

The main question raised in this case is identically the same as we have just considered at the present term, in the case of Bohn Mfg. Co. et al. v. Kountze, ante, p. 719. We held in that case that where a vendee of real estate under a contract of sale which contained a stipulation that the purchaser shall construct a building upon the premises, erects a building thereon, the laborer and material-man are entitled to a lien against the premises paramount to the lien of the vendor. The memorandum of agreement in the case we are now considering contemplated that the purchaser, Groves, would erect houses on the lots to cost at least $600 to $700 each. The buildings were constructed, but the labor performed and materials furnished have not not been paid for. Boggs & Hill, having authorized the purchaser to make the improvements on the property, to which they held the legal title, we hold, for the reasons given in the Kountze case,'that they postponed their lien for the unpaid purchase money to that of the mechanic and material-man.

We will now pass to the consideration of the points raised by the appellant Groves. It appears that after Ball abandoned the contract for the construction of the buildings, H. A. Sohreckingast, in pursuance of a. contract with Groves, furnished the balance of the hardware and the labor necessary to complete the buildings, amounting to [733]*733$75.75. The last item was furnished on the 9th day of May, 1888. Within sixty days thereafter Schreckingast filed his answer and cross-petition herein, and upon the trial the defendant Groves objected to the Schreckingast lien being introduced in evidence, because his suit was prematurely brought. The court thereupon permitted this answer and cross-petition to be withdrawn from the files and to be refiled. This ruling is assigned for error.

Under section 2 of the mechanic’s lien law, a subcontractor, to obtain a lien, must make out and file with the register of deeds of the county where the building is erected, a sworn statement of the amount due him from the contractor, within sixty days from the performing of the labor or the furnishing of the materials. The section also provides that “No owner shall be liable to any action by the contractor until the expiration of the said sixty days.” It is obvious that a contractor cannot lawfully bring an action against the owner of the building within sixty days after performing the last labor or furnishing the last item of material. To bring the case within the provisions of the statute, Schreckingast withdrew his answer and ■ cross-petition and refiled the • same. At that time the sixty days’ limit had elapsed, and he was entitled to maintain his action. Of course, on the refiling of the pleading, Groves would have been entitled to a continuance of the hearing upon the cross-bill had he demanded it. Failing to request a postponement, there was no error committed in proceeding with the trial.

After the lienors had introduced their testimony in support of their respective claims, the defendant Groves offered to prove that the contract entered into between Ball and himself had never been complied with by Ball, and that the buildings were not erected according to the terms of the contract. Groves’s counsel stated to the court that his purpose in offering this testimony was to show that the liens were prematurely filed and that they could not file [734]*734and enforce their liens until the buildings were completed and the contract complied with. The court ruled out the testimony.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peters v. Halligan
152 N.W.2d 103 (Nebraska Supreme Court, 1967)
Home Savings & Loan Ass'n v. Sullivan
1929 OK 17 (Supreme Court of Oklahoma, 1929)
Fossett v. Rock Island Lumber & Manufacturing Co.
92 P. 833 (Supreme Court of Kansas, 1907)
Guiou v. Ryckman
110 N.W. 759 (Nebraska Supreme Court, 1906)
Hampton v. Christensen
84 P. 200 (California Supreme Court, 1906)
Cummings v. Emslie
68 N.W. 621 (Nebraska Supreme Court, 1896)
Chappell v. Smith
59 N.W. 110 (Nebraska Supreme Court, 1894)
Hoagland v. Lowe
58 N.W. 197 (Nebraska Supreme Court, 1894)
Sheehy v. Fulton
57 N.W. 395 (Nebraska Supreme Court, 1894)

Cite This Page — Counsel Stack

Bluebook (online)
46 N.W. 1125, 30 Neb. 728, 1890 Neb. LEXIS 159, Counsel Stack Legal Research, https://law.counselstack.com/opinion/millsap-v-ball-neb-1890.