McMillan v. Malloy

10 Neb. 228
CourtNebraska Supreme Court
DecidedJanuary 15, 1880
StatusPublished
Cited by8 cases

This text of 10 Neb. 228 (McMillan v. Malloy) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McMillan v. Malloy, 10 Neb. 228 (Neb. 1880).

Opinion

Maxwell, Oh. J.

Malloy sued McMillan in the county court of Saunders county, and recovered the sum of $4.70 and costs. McMillan appealed to the district court, where judgment was rendered against him for the sum of $30 and costs. He brings the cause into this court by petition in error. The petition of the plaintiff in the court below alleges — -first, that there is a balance due him from the defendant of the sum of $4.62, for threshing grain in 1876 ; second, that there is due him from the defendant the sum of $40.08, for threshing wheat in 1878.

To this petition the defendant filed an answer in which he denied the facts stated in the .first count of the petition; second, alleged that the threshing done in the year 1878 was performed under a contract between [230]*230the plaintiff and defendant, that the plaintiff should thresh all the defendant’s grain for that year at forty cents per acre, and that plaintiff threshed about one-third of said, grain and refused to complete his contract, whereby the defendant was damaged in the sum of $100; third, as a third defense the defendant alleged that the knuckles and joints of tumbling-rods of the threshing machine were not safely boxed and secured, as required by law.

It is evident from the record that the jury rejected the item of $4.62, balance claimed to be due for threshing in 1876. It appears from the testimony that in the month of September, 1878, the plaintiff entered into a contract with the defendant to thresh his grain raised that year for the sum of forty cents per acre; and that in pursuance of said contract the plaintiff threshed wheat for the defendant for three days, and had to quit work because the defendajxlj was unable to obtain a sufficient number of hands to keep the 'machine in operation. The plaintiff threshed about 78£ bushels of wheat, being about one-third of the defendant’s grain, and which, at forty cents per acre, would amount to the sum of $17. There is some testimony tending to show that the plaintiff was to return and complete the job, although upon that point there is some conflict. The plaintiff, ignoring his contract, seeks to recover the value per bushel for threshing the wheat in question. The court instructed the jury that, “ if you find from the evidence that the contract for the threshing in 1878 was broken by the plaintiff, that ■ fact will not prevent him from recovering for what he actually' did, and you will allow him what it was reasonably worth, as shown by the evidence. But you will then proceed to ascertain how much, if any, damages the defendant (McMillan) sustained by reason- of Malloy’s failure to comply with the agreement. As[231]*231certain to whom the greater amount is due; deduct the less amount from the greater, and return your verdict for the balance.” To which instruction the defendant excepted, and now assigns the giving of the same for error.

The plaintiff in error insists that a recovery upon a quantum meruit cannot be had upon part performance of an entire contract of this sort, where there is no w’aiver nor voluntaiy acceptance’ by the defendant. We are aware that there are a large number of cases, most of them tried in courts having no equity powers, holding that no recovery can be had in such case. These decisions are placed upon the ground that the contract is entire, and that no recovery can be had on the contract until the plaintiff has performed his part of the same. And where a contract is entire and indivisible, and payment is to be made only after full performance, no action can be maintained on part performance. But when the contract is susceptible of division, and its entirety has been destroyed by part performance, from which the other party has derived a benefit, the law raises an implied promise to pay to the extent of the benefit received; and an action may be maintained thereon after the time has expired for the completion of the contract.

In the leading case of Oxendale v. Wetherell, 9 Barn & C., 386, an action was brought to recover the price of 130 bushels of wheat sold and delivered by the plañir tiff to the defendant at 8 shillings per bushel. The defendant proved that he made an absolute contract for 250 bushels, and contended that as the plaintiff had not fully performed, he could not recover. It was held that the plaintiff, having retained the 130 bushels, after the time for completing the contract had expired, was bound to pa}? for the same.

In Bowker v. Hoyt, 18 Pick., 555, the plaintiff sold [232]*232the defendant 1,000 bushels of corn, but delivered only 400 bushels. The court held in substance that the acceptance of a part of the corn was a severance of the entirety of the contract, and the defendant was bound to pay for the corn so delivered; but that he might reduce the plaintiff’s claim by showing any damages he had sustained by the plaintiff’s failure to fulfill his contract. 2 Smith’s L. C. (6 Ed.), 33. 2 Parsons on Contracts (5 Ed.), 523-4.

In Britton v. Turner, 6 N. H., 481, the plaintiff brought an action for work and labor performed by the plaintiff for the defendant from March 9, 1831, to December 27 of the same year. The defendant offered to prove that the work was done under a contract for one year for the sum of $100, and that the plaintiff left his service without his consent and without good cause. Parker, C. J., in delivering the opinion of the court, after referring to certain cases where a recovery could be had, said: “ Those cases are not to be distinguished in principle from the present, unless it be in the circumstance that where the party has contracted to furnish the materials, and do certain labor, as to build a house in a specified manner, if it is not done according to the contract, the party for whom it is built may refuse to receive it — elect to take no benefit from what has been performed — and therefore, if he does receive, he shall be bound to pay the value; whereas, in a contract for labor -merely, from day to day, the party is receiving the benefit of the contract under an expectation that it will be fulfilled, and cannot, upon the breach of it, have an election to refuse to receive what has been done, and thus discharge himself from payment.

But we think this difference in the nature of the contracts does not justify the application of a different rule in regard to them. The party who contracts for [233]*233labor merely, for ,a certain period, does so with full knowledge that he must, from the nature of the case, be accepting part performance from day to day, if the other party commences the performance,' and with knowledge also that the other party may eventually fail of completing the entire term. If, under such circumstances, he actually receives a benefit from the labor performed over and above the damage occasioned by the failure to complete, there is as much reason ■why he should pay the reasonable worth of what has thus been done for his benefit as there is when he enters and occupies the house which has been built for him, but not according to the stipulations of the contract, and which he perhaps enters, not because he is satisfied with what has been done, but because circumstances compel him to accept it as it is. It is said that in those cases, where the plaintiff has been permitted to recover, there was an acceptance of what had been done.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peters v. Halligan
152 N.W.2d 103 (Nebraska Supreme Court, 1967)
Rickertsen v. Carskadon
100 N.W.2d 852 (Nebraska Supreme Court, 1960)
Jones v. Thomas
184 N.W. 151 (Nebraska Supreme Court, 1921)
Gilkie & Anson Co. v. Dawson Town & Gas Co.
64 N.W. 978 (Nebraska Supreme Court, 1895)
West v. Van Pelt
51 N.W. 313 (Nebraska Supreme Court, 1892)
Sieber v. Weiden
17 Neb. 582 (Nebraska Supreme Court, 1885)
Sawyer v. Brown
17 Neb. 171 (Nebraska Supreme Court, 1885)

Cite This Page — Counsel Stack

Bluebook (online)
10 Neb. 228, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcmillan-v-malloy-neb-1880.