McGowan v. Gate City Malt Co.

130 N.W. 965, 89 Neb. 10, 1911 Neb. LEXIS 137
CourtNebraska Supreme Court
DecidedApril 8, 1911
DocketNo. 16,373
StatusPublished
Cited by10 cases

This text of 130 N.W. 965 (McGowan v. Gate City Malt Co.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McGowan v. Gate City Malt Co., 130 N.W. 965, 89 Neb. 10, 1911 Neb. LEXIS 137 (Neb. 1911).

Opinion

Reese, C. J.

This is an action- by plaintiffs, as subcontractors, against James Stewart & Company, as principal contractors, and the Gate City Malt Company, the owner, by which a judgment is sought against James Stewart & Company, contractors, and the foreclosure of a mechanic’s lien on lot 6, in block 16, and lots 1, 2 and 3, in block 18, in the city of South Omaha, as against the owner of said property.

The pleadings are of great length and cannot be set out in detail here. It must be sufficient to say that it is alleged in the petition that- the defendants James Stewart & Company ■ entered into a contract with defendant Gate City Malt Company to furnish' the material and construct buildings on the lots described above- in the city of South Omaha, and subsequently, by a contract [12]*12with plaintiffs, sublet a portion thereof to them and by which plaintiffs were to furnish the material and dp the brick and concrete work for the prices and upon the terms set out in said contract, all of which was done and performed by plaintiffs, amounting to the total sum of $31,923.49; that defendants, had paid to plaintiffs thereon the sum of $25,524.70, and no more, and that there remained due and unpaid thereon the sum of $6,398.79, for which judgment was demanded as against James Stewart & Company, and for the foreclosure of the mechanic’s lien as against the Gate City Malt Company. The contract with the items of account are set out in the petition as exhibits, but they need not be here stated.

The answer of defendants James Stewart & Company is of considerable length. By it the contract with plaintiffs is admitted, and, in substance, it is admitted that plaintiffs furnished material and labor thereunder, but by way of counterclaim it is alleged that plaintiffs so failed to comply with the contract as to result in serious loss and damage to defendants. Among the items presented by defendants are: Balance due on brick furnished to plaintiffs, $113.25; demurrage on cars plaintiffs failed to unload, $238; making connections of water pipes, $65. It is alleged that by the terms of the contract 80 per cent, in value of the labor and material furnished by plaintiffs was to be paid as the work progressed; the remaining 20 per cent, was to be withheld until the work was finished and accepted; that the 20 per cent, is included in plaintiffs’ petition, but that the work has never been accepted; that there is nothing due plaintiffs until such acceptance, and therefore the suit is prematurely brought and cannot be maintained; that owing to the many violations of the provisions of the contract, both in the manner of doing the work and the failure to complete the structure within the time limited by the contract, plaintiffs having thereby failed in its performance, no action can be maintained thereon. The answer of the Gate City Malt Company is practically a general denial of .the averments [13]*13of the petition and of any indebtedness to plaintiffs, it having no contractual relations with them. Plaintiffs’ reply to this answer is a general denial.

Plaintiffs’ reply to the answer of James Stewart & Company is to the effect that they had brick of their own purchase, sufficient to meet all demands as the work progressed, and the purchase of brick by defendants was therefore unnecessary, but to accommodate defendants plaintiffs had used them and allowed defendants the same price for which they had purchased brick for themselves; that defendants had purchased their brick at 50 cents a thousand more than plaintiffs had purchased their own brick, but that they had accepted defendants’ brick at the same price for which they had purchased, to wit, $7 a thousand; that the demurrage charge was occasioned by the unnecessary purchase and shipment of brick in such large quantities by defendants that they could not be unloaded from the cars, the demurrage being caused by the unnecessary act of defendants, and plaintiffs were not liable therefor. It is alleged that the piping for water was done for defendants’ own use and benefit, and not for or at the request of plaintiffs; that immediately upon the completion of the buildings the Gate City Malt Company, defendant, had taken possession thereof and has since occupied the same; that defendants are estopped to object to plaintiffs’ work because all of said work was done under defendants’ immediate supervision and direction. The cause was tried to the court, the result being a general finding in favor of plaintiffs. The amount found due, including interest, was. $7,282.87, and an order of sale was directed to.issue for the sale of the property in case of nonpayment. Defendants James Stewart & Company appeal.

Each party has furnished elaborate, able and extended briefs, and the cause was quite exhaustively argued at the bar of this court. The bill of exceptions is of great length, and consists largely of details which it is impossible for us to follow without extending this opinion [14]*14to an unnecessary and unreasonable length. Reversing, to some extent, the order of the presentation of the subjects by defendants in their brief, we notice the contention that plaintiffs’ action cannot be maintained upon the contract until there is a performance of its conditions by them. This contention is, in a general way, correct. That one cannot maintain an action on a contract without a prior substantial compliance on his part is the well-settled law, but this principle must have a. reasonable application. If there is a substantial performance the action thereon may be maintained, but without prejudice to any set-off or counterclaim which may be presented by the defendant in the action. This is a reasonable and just rule, and is the well-settled law of 'this state. Hahn v. Bonacum, 76 Neb. 837, and cases there cited; Nebraska Plumbing Supply Co. v. Payne, 84 Neb. 390; GroveWharton Construction Co. v. Clarke, 86 Neb. 831. There can be no doubt but there was at least a substantial compliance with the plaintiffs’ contract on their part, and therefore the action can be maintained, but subject to damages, if any, which defendants may have suffered.

Defendants further contend that the decree of the district court should be reversed “because the contract between the parties provided that the final payment of 20 per cent, (of the contract price) should be made only after the approval and acceptance of the work by the supervising architect.” The contract provides' that the payments for the work are “to be made on or about the 20th of each month at the rate of 80 per cent, of the value of material delivered and in place during the preceding month, ás determined by the contractor or the architect; and the remaining 20 per cent, within 30 days after the completion and acceptance of this work.” It may be noted that the contract does not specify by whom the acceptance of the work is to be made, whether by the architect, the owner, or the contractor. We are inclined to the belief that as between the contractor and the subcontractor (and they are the only parties to this appeal) [15]*15the completion of the work and its surrender to the contractor would be a sufficient compliance with this provision, but subject to any damage he might sustain by failure to comply with details. However, we do not base our decision exclusively upon this. The clause is incomplete, and a compliance with the contract is all that can be required under it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

D. K. Meyer Corp. v. Bevco, Inc.
292 N.W.2d 773 (Nebraska Supreme Court, 1980)
Obray v. Mitchell
567 P.2d 1284 (Idaho Supreme Court, 1977)
Griffin v. Geneva Industries, Inc.
228 N.W.2d 880 (Nebraska Supreme Court, 1975)
Peters v. Halligan
152 N.W.2d 103 (Nebraska Supreme Court, 1967)
Rickertsen v. Carskadon
108 N.W.2d 392 (Nebraska Supreme Court, 1961)
Parsons Construction Co. v. Gifford
262 N.W. 508 (Nebraska Supreme Court, 1935)
Groner v. Cavender
133 So. 825 (Louisiana Court of Appeal, 1931)
Fossier v. Knight Motors Co.
127 So. 87 (Louisiana Court of Appeal, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
130 N.W. 965, 89 Neb. 10, 1911 Neb. LEXIS 137, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcgowan-v-gate-city-malt-co-neb-1911.