D. K. Meyer Corp. v. Bevco, Inc.

292 N.W.2d 773, 206 Neb. 318, 1980 Neb. LEXIS 860
CourtNebraska Supreme Court
DecidedMay 28, 1980
Docket42731
StatusPublished
Cited by8 cases

This text of 292 N.W.2d 773 (D. K. Meyer Corp. v. Bevco, Inc.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D. K. Meyer Corp. v. Bevco, Inc., 292 N.W.2d 773, 206 Neb. 318, 1980 Neb. LEXIS 860 (Neb. 1980).

Opinion

Brodkey, J.

This matter involves an appeal by Bevco, Inc., and a cross-appeal by D. K. Meyer Corporation from an order of the District Court for Douglas County, Nebraska, affirming a judgment rendered by the Omaha municipal court in favor of Meyer for money due it from Bevco on a construction project. We affirm as modified.

It appears from the record that the Church of the Holy Spirit in Plattsmouth, Nebraska, engaged an architectural firm to draft plans and specifications for the purpose of constructing the Holy Spirit Parish Center. Bids were subsequently let, with Bevco *320 being awarded the general contract. Bevco, in turn, let subcontracts for portions of the work to various parties under the contract. A roof support structure was to be fabricated by two different subcontractors and Meyer was awarded the subcontract for the complete erection of the roof support structure, consisting of the structural steel, steel space grid, open web joists, metal decking, and miscellaneous and ornamental metals. The total amount to be paid Meyer for its work under the contract was $10,550. The actual building was erected according to the plans and specifications. Likewise, the roof support structure was fabricated according to the specifications and plans. However, when Meyer attempted to place the roof support structure in place, it did not fit on the building as was required by the plans and specifications.

Measurements of the building were again taken and it was determined that the structure was dimensionally correct. In fact, the steel space grid support structure was of a standardized dimension, but did not fit into the building as planned by the architect. All parties to the construction project agreed that modifications were necessary for the completion of the project, which modifications were performed by Meyer, without objections by Bevco. While it is not clear from the record which party specifically authorized the modifications, it is, however, apparent from the evidence adduced at trial that the parties, including Meyer and Bevco, inferentially agreed to the modifications. Meyer incurred additional expenses in performing the modifications in a total amount of $3,891.40. This action arose from the refusal of Bevco to pay the additional costs incurred by Meyer as a result of the modifications performed by it.

On the basis of the foregoing evidence, the municipal court found for Meyer in the amount of $3,891.40 and costs in the amount of $44. The Dis *321 trict Court affirmed this judgment and Bevco has appealed to this court, assigning two errors.

Bevco contends that error was committed by the lower court because the work was performed by Meyer without its first receiving a written change order pursuant to the contract entered into by Bevco and Meyer. Said contract was a “Standard SubContract Agreement,” which provided in relevant part: “[T]hat no extra work shall be allowed or

changes made by the Sub-Contractor, or paid for by the Contractor unless and until authorized by the Contractor or his superintendent in writing before the work and/or changes are begun.” It is undisputed that a written change order for the modifications performed was never given to Meyer. However, we conclude that the failure to obtain a written change order does not bar Meyer’s recovery herein. In Griffin v. Geneva Industries, Inc., 193 Neb. 694, 696-97, 228 N.W.2d 880, 882 (1975), we stated:

It is well-established that the parties to a contract may avoid such a provision where their words, acts, or conduct amount to a waiver, modification, rescission, abrogation, or abandonment of the provision, or the party claiming the benefit of the provision is es-topped to rely on it. Annotation, 2 A. L. R. 3d 620.
The evidence is clear that the defendant knew about the additional work performed by the plaintiff and its conduct indicated approval and authorization for the work to proceed. Under these circumstances the defendant cannot now contend that the plaintiff is not entitled to compensation because he failed to obtain prior approval of a quotation for the additional work. Where the parties ignore such a provision in the contract it will not furnish a defense to a claim for compensation for the additional work *322 performed. McGowan v. City Malt Co., 89 Neb. 10, 130 N.W. 965.

See, also, Annot., 2 A.L.R.3d 620 (1965); and Annot., 66 A.L.R. 649 (1930).

The record sustains the conclusion that the parties herein ignored the provision of the contract requiring a written change order prior to the modification of the project. “The interpretation given a contract by the parties themselves while engaged in the performance of the contract is one of the best indications of the true intent of the parties and, ordinarily, that construction of the contract should be enforced." Richards v. Bycroft, 197 Neb. 478, 481, 249 N.W.2d 743, 745 (1977).

The job supervisor from Meyer testified that the work performed in the modifications was not originally contemplated in the contract. The project manager from Bevco testified that the modifications caused Meyer to incur costs not originally contemplated in the contract for erection of the steel space grid. Moreover, correspondence between Bevco and the architectural firm which designed the building indicates knowledge and acceptance of the extra costs incurred by Meyer and a request by Bevco to the architect that a change order be issued to Bevco for the costs of said modifications. In fact, in its request for a change order, Bevco demanded a- 7 percent markup for itself on the costs of modification, but the request- for the change order was denied. Whether or not the owner chose to modify its contract with Bevco in regard to any written change orders • is immaterial on the question of whether Bevco’s actions amounted to a modification of its own contract with Meyer. We believe that Bevco’s actions clearly demonstrated a modification of the contract and recognized that Meyer was due money for the extra costs incurred as a result of the modifications. We,' therefore, reject Bevco’s assignment of error to the contrary.

*323 Bevco also contends that error occurred because the contract further conditioned Meyer’s payment on receipt of payment by Bevco from the owner. The contract provided, in relevant part: “That the Contractor shall not be liable for, nor bound in any respect to the Sub-Contractor for the payment to him of his monthly or final estimates of any moneys in excess of the amount which the Contractor receives from the Owner for the Sub-Contractor’s work.” The record is clear that Bevco has paid Meyer for all the work called for by the subcontract, but that Meyer has not been paid for the additional or extra labor and work incurred in the corrections and modifications referred to above.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Capitol Steel Fabricators, Inc. v. Mega Constr. Co.
58 Cal. App. 4th 1049 (California Court of Appeal, 1997)
Koch v. Construction Technology, Inc.
924 S.W.2d 68 (Tennessee Supreme Court, 1996)
Cianci Constr. Co. v. Griffin Constr. Co., No. 27 77 93 (Feb. 4, 1991)
1991 Conn. Super. Ct. 1461 (Connecticut Superior Court, 1991)
Lauritzen v. Davis
335 N.W.2d 520 (Nebraska Supreme Court, 1983)
Shreves v. D. R. Anderson Constructors, Inc.
293 N.W.2d 106 (Nebraska Supreme Court, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
292 N.W.2d 773, 206 Neb. 318, 1980 Neb. LEXIS 860, Counsel Stack Legal Research, https://law.counselstack.com/opinion/d-k-meyer-corp-v-bevco-inc-neb-1980.