Shreves v. D. R. Anderson Constructors, Inc.

293 N.W.2d 106, 206 Neb. 433, 1980 Neb. LEXIS 870
CourtNebraska Supreme Court
DecidedJune 10, 1980
Docket42842
StatusPublished
Cited by8 cases

This text of 293 N.W.2d 106 (Shreves v. D. R. Anderson Constructors, Inc.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shreves v. D. R. Anderson Constructors, Inc., 293 N.W.2d 106, 206 Neb. 433, 1980 Neb. LEXIS 870 (Neb. 1980).

Opinion

McCown, J.

This is an action by the bankruptcy representative of a subcontractor against a contractor to recover money allegedly due under a written subcontract. The jury returned a verdict for the plaintiff in the sum of $15,079.11. The District Court sustained defendant’s motion for a new trial and vacated the jury verdict. The plaintiff has appealed.

The plaintiff is the trustee in bankruptcy of John J. Salonis Masonry, Inc., a Nebraska corporation. On July 24, 1974, Salonis entered into a written subcontract with the defendant, D. R. Anderson Constructors, Inc., the general contractor, to perform the work specified in the contract in accordance with the plans and specifications for the construction of a school building in Omaha, Nebraska. The subcontract price was $183,900. Two subsequent deletions were made from the subcontract requirements by written change orders which reduced the total contract amount to $182,357.

Section 4 of the written contract provides:

Changes. The contractor may at any time by written order of Contractor’s authorized representative, and without notice to the Subcontractor’s sureties, make changes in, additions to and omissions from the work to be performed and materials to be furnished under this Subcontract, and the Subcontractor shall promptly proceed with the performance of this Subcontract as so changed. Any increase or decrease in the Subcontract price resulting from such changes shall be agreed upon in writing by the parties hereto. Any claim for adjustment of the subcontract price under this Section must be made in writing within ten days from the date such changes are ordered. The Subcontract *435 price shall be equitably adjusted on account of any such changes, subject to any applicable provisions of the contract between the Contractor and the Owner.

Plaintiff’s petition alleged that Salonis fully performed all the work specified in the subcontract. The petition also alleged that Salonis had performed additional masonry work for the defendant.

Plaintiff alleged that the defendant orally requested Salonis to do certain additional work because of defective work of the Ray Martin Company, another subcontractor, and promised that Salonis would be paid for the additional work requested. It was alleged that the fair value of the additional Martin work was $8,356.

The petition also alleged that the defendant requested that Salonis performed additional work of cutting approximately 1,500 blocks and promised to compensate Salonis for its labor. The fair value of the labor was alleged to be $1,500.

The petition also alleged that the defendant requested that Salonis perform additional work of in replacing and patching in connection with electrical and other masonry contract work and promised that Salonis would be compensated for the labor and materials furnished, and the fair value of that work was $2,875.

The petition alleged that defendant had paid Salonis the total sum of $179,489.89 for the work under the contract and prayed judgment against the defendant for the sum of $4,410.11 due for the work specified in the subcontract, and for the sum of $12,731 due for the additional labor and material furnished in connection with the additional work referred to in the petition.

The defendant’s answer denied that Salonis had properly completed the specified work under the contract. The answer also generally denied all the allegations of additional work except for the Martin *436 work. The defendant admitted that it had requested Salonis to perform additional masonry work resulting from the defective work of the Ray Martin Company and had promised that Salonis would be paid for the proper labor and material expended on the Martin work. The defendant affirmatively alleged that Salonis performed certain work upon the Martin project but that, in spite of numerous requests by the defendant to Salonis to furnish an itemized list of material and labor expended in the performance of the additional Martin work, Salonis had failed to provide the defendant with any data upon which the reasonable value of said work and materials could be ascertained.

The evidence of Salonis at trial was that the defendant’s representatives verbally requested him to perform the three items of additional masonry work, told him to keep track of his time and materials, and promised that he would be paid for the work. Salonis testified that he computed the cost for the Martin portion of the work which, including overhead and a 10-percent profit, totaled $8,356, and that he orally reported that amount to the defendant’s project supervisor. Salonis admitted that he had never submitted written claims for any part of the extra work and materials and conceded that he had not submitted time cards nor material invoices for the Martin work, nor responded to the requests for that information, except to tell the defendant that he had already given him all the information he had as he did not keep explicit records of equipment and materials used.

The defendant’s evidence supported the allegations of its answer and indicated that the defendant had not requested the additional work except for the Martin portion of it, and that the other additional work was in connection with the principal contract.

The case was pleaded and tried by both parties as a single cause of action on the basic written sub *437 contract. Although the facts were pleaded and the evidence tended to establish that some oral modifications of the written contract might have been made, neither party specifically pleaded modification of the written contract nor waiver of any of its provisions, nor did the plaintiff plead or set out any separate cause of action for quantum meruit.

At the conclusion of the plaintiff’s evidence, the plaintiff moved to amend its petition to allege that the defendant’s conduct in requesting additional work and agreeing to pay for it waived the requirement of written change orders and the requirement that claims for adjustment of the subcontract price must be made in writing within 10 days from the date such changes were ordered. The plaintiff’s motion to amend also included a request to amend the petition by setting out a separate alternative count on the basis of quantum meruit for the additional work. The defendant objected on the ground that there was no evidence to support a modification or waiver of the written contract and that it was too late. The court concluded that the proposed amendments injected additional issues into the case and denied the motion.

The defendant proceeded with the introduction of its evidence and, at the close of all the evidence, the proposed jury instructions were presented to counsel for both parties before submission of the cause. Instruction No. 6 instructed the jury that the plaintiff could satisfy its burden of proof by proving performance and compliance with the terms and conditions of the written subcontract or, in the alternative, that the parties to the contract could avoid the provisions of the written contract by such words, acts, or conduct from which the jury might find that the parties waived, modified, rescinded, abrogated, or abandoned the provisions of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cass County Bank v. Dana Partnership
750 N.W.2d 701 (Nebraska Supreme Court, 2008)
Holmes v. Crossroads Joint Venture
629 N.W.2d 511 (Nebraska Supreme Court, 2001)
Wheat Belt Public Power District v. Batterman
452 N.W.2d 49 (Nebraska Supreme Court, 1990)
Eastline Corp. v. Marion Apartments, Ltd.
524 So. 2d 582 (Mississippi Supreme Court, 1988)
Barker v. Wrehe
351 N.W.2d 412 (Nebraska Supreme Court, 1984)
Hegarty v. Campbell Soup Co.
335 N.W.2d 758 (Nebraska Supreme Court, 1983)
Schroll v. Fulton
328 N.W.2d 780 (Nebraska Supreme Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
293 N.W.2d 106, 206 Neb. 433, 1980 Neb. LEXIS 870, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shreves-v-d-r-anderson-constructors-inc-neb-1980.