Wiebe Construction Co. v. School District of Millard

255 N.W.2d 413, 198 Neb. 730, 1977 Neb. LEXIS 995
CourtNebraska Supreme Court
DecidedJune 29, 1977
Docket41034
StatusPublished
Cited by32 cases

This text of 255 N.W.2d 413 (Wiebe Construction Co. v. School District of Millard) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wiebe Construction Co. v. School District of Millard, 255 N.W.2d 413, 198 Neb. 730, 1977 Neb. LEXIS 995 (Neb. 1977).

Opinion

Clinton, J.

This is an action by Wiebe Construction Company against the School District of Millard, arising out of a contract entered into by the parties on July 22, 1969, under the terms of which Wiebe agreed to construct for the district a project identified as the Millard high school stadium at a cost price of $556,365. In accordance with provisions for changes in the contract contained therein, the contract was modified by the parties by change orders Nos. 1, 2, 3, and 4, calling for additional work and payments in the amount of $2,172.18, $2,067, and $8,553. The original contract required completion of the work within “350 consecutive calendar days” after “ ‘Notice to Proceed.’ ” The contract also provided that the contractor pay liquidated damages in the sum of $100 per day for each day of delay in performance.

*732 Wiebe’s petition contained three causes of action as follows: (1) $56,915.72 for balance unpaid on the contract price; (2) $42,042 for increased costs by reason of delay caused when problems not anticipated by the parties arose and the district and its engineers delayed in making decisions as to necessary specification changes; and (3) $1,361.21 for extra work performed in reconstruction of a sidewalk.

The district filed an answer and a counterclaim. In its answer the district alleged that Wiebe failed to complete the work properly. It denied that unanticipated conditions were encountered and alleged that in any event they should have been anticipated by the contractor. In its counterclaim the district made factual allegations, and prayed for liquidated damages at $100 per day for 224 days delay in completion of the project and for damages for certain defects in performance, including, among others, the claim that planks for certain stadium seats were not in accordance with contract specifications. Its total prayer for damages was in the sum of $62,112.65. In its reply Wiebe alleged, among other things, that the delay in construction was caused by indecision of the district’s engineers and agent as to whether specification changes were required and what these changes would be.

The trial of the case began before a jury and after 5 days before the jury the parties waived a jury trial, presenting the remainder of the evidence and submitting the case to the trial judge.

The trial court entered a judgment in part as follows: ”... the court finds generally in favor of the plaintiff and that there is due to the plaintiff from the defendant on the causes of action set forth in plaintiff’s petition the sum of $44,880.68.” The court also allowed interest at 6 percent from October 1, 1971, until April 30, 1976, the date of judgment, in the amount of $12,342.18. The court dismissed with prejudice the counterclaim of the district.

*733 The district appealed to this court, here making two assignments of error: (1) The trial court erred in awarding prejudgment interest. (2) The trial court erred in not awarding liquidated damages for delay in performance. In a cross-appeal Wiebe asserted that it was entitled to the full amount of the balance on the contract, to wit, $56,915.72, instead of the $44,880.68 awarded by the court, as well as prejudgment interest on the full balance.

We will first discuss the claim of the district that it was entitled to liquidated damages for delay in performance. The entire project consisted of a football field, stadium, appurtenances, and a running track. The delay in performance arose only in connection with the running track portion of the contract. The evidence would permit the trial court to find the following. After construction was commenced a part of the site was found to be underlain with ground water and to be in a very spongy condition. When this matter was called to the attention of the engineers in November of 1969, it appeared that the condition would require a change in contract specifications and not merely more difficult work on the part of the contractor. As a consequence of this situation the engineers, in a letter dated December 18, 1969, in response to a letter from Wiebe, stated: “It would seem to us that a more reasonable approach to resolving this matter would be to wait until spring of 1970 to determine the change in thé work.” In a letter dated June 1, 1970, the engineers wrote to Wiebe: “We will provide you with additional details on the extra work to be performed for stabilization of the running track subgrade in the very near future.” A letter from the engineers to Wiebe dated June 15, 1970, contained the following item: “6. The track stabilization detail will be made available, for construction purposes, upon the completion of all items listed above and no work should be performed on the track curb, subgrade base, etc. until these items *734 have been corrected.” As one consequence of the water condition, change order No. 4, dated September 1, 1970, and executed by the parties a few days later, was entered into. It called for an extra in the form of a drainage system which was in fact constructed. The system was not, however, completely effective. After that there were extended discussions between the parties as to what, if any, further specification changes were required. The engineers hired a soil expert who made recommendations. Under date of September 3, 1970, a fifth change order, which was a revision of several previously proposed change orders, was offered by the district’s engineers. This change order made some additional specification changes in the preparation of the subgrade of the track and also provided for an 120-day additional time extension on the contract period in addition to a 28-day extension which had been granted by one of the earlier change orders. The proposed changes in change order No. 5 were not agreed to by Wiebe because of, among other things, a claim that it could not, on the basis of the proposed specification changes, make any reasonable estimate of quantities of certain materials involved.

It is now necessary to note portions of the four change orders which were in fact adopted as these portions pertain to the ‘‘contract period.” In change order No. 1 the contract period was designated as August 18, 1969, to August 3, 1970 (350 days). The second change order provided for the same contract period. The third change order stated the contract period as 378 days and contained no substantive contract changes otherwise. Change order No. 4, dated September 1, 1970, in addition to the drainage system change, provided: ‘‘Contract Period To be determined.” Following change order No. 4 there were no further determinations as to what would be the contract period, but on September 15 or 16, 1970, Wiebe was instructed to proceed under the *735 original track specifications. On October 28, 1970, the engineers performed a test of soil conditions and it was found the ground was too wet to proceed at that time. Wiebe, however, indicated that he would proceed nonetheless if the district would accept the risk of frost damage to the track. No agreement was reached at that point. The track was completed on October 25, 1971.

The foregoing evidence would be sufficient to support a finding that the district had waived the provision for time of performance, or that the parties had modified the time for performance of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Continental Indemnity Company v. IPFS of New York
7 F.4th 713 (Eighth Circuit, 2021)
U.S. Pipeline v. Northern Natural Gas Co.
303 Neb. 444 (Nebraska Supreme Court, 2019)
Troy v. RFD-TV The Theater, LLC
498 S.W.3d 550 (Court of Appeals of Tennessee, 2016)
World Classic Productions, Inc. v. RFD-TV The Theater, LLC
498 S.W.3d 874 (Court of Appeals of Tennessee, 2016)
Empire Gas Corp. v. UPG, Inc.
781 S.W.2d 148 (Missouri Court of Appeals, 1989)
Bruning Seeding Co. v. McArdle Grading Co.
439 N.W.2d 789 (Nebraska Supreme Court, 1989)
Lueder Construction Co. v. Lincoln Electric System
424 N.W.2d 126 (Nebraska Supreme Court, 1988)
D. K. Meyer Corp. v. Bevco, Inc.
292 N.W.2d 773 (Nebraska Supreme Court, 1980)
Nebraska Public Power District v. Borg-Warner Corp.
621 F.2d 282 (Eighth Circuit, 1980)
King v. Sky Harbor Air Service, Inc.
281 N.W.2d 209 (Nebraska Supreme Court, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
255 N.W.2d 413, 198 Neb. 730, 1977 Neb. LEXIS 995, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wiebe-construction-co-v-school-district-of-millard-neb-1977.