U.S. Pipeline v. Northern Natural Gas Co.

303 Neb. 444, 930 N.W.2d 460
Nebraska Supreme Court·Decided June 28, 2019·No. S-18-679.·Published·Cited by 138 cases

Opinion

Freudenberg, J.

*464 I. NATURE OF CASE

In 2014, a natural gas company solicited bids for a pipeline replacement and relocation project in northern Michigan. The natural gas company accepted a bid from a pipeline company, and the parties entered into a detailed construction contract. The contract provided that the project would be substantially completed by September 2014. However, because of extra work orders by the natural gas company and for various other reasons, the project was not substantially completed by that date. Based on a liquidated damages provision in the contract, the natural gas company withheld the maximum amount of liquidated damages allowable under the contract for the delay in the project's completion. The natural gas company also refused to pay certain costs requested by the pipeline company **447 related to the extra work orders. At the center of the lawsuit is whether the natural gas company should pay for the costs associated with the extra *465 work and be allowed to withhold liquidated damages.

II. FACTS

1. PLEADINGS

In January 2016, U.S. Pipeline, Inc., a corporation engaged in the business of constructing oil and gas pipelines and related energy infrastructure facilities, filed a complaint in the district court for Douglas County against Northern Natural Gas Company (Northern), a corporation headquartered in Omaha, Nebraska, and engaged in the business of providing natural gas transportation and storage services. U.S. Pipeline sought compensation under a pipeline replacement and relocation project contract for costs incurred to perform work that was outside of the original contract price (Extra Work). U.S. Pipeline sought relief under a breach of contract theory, as well as alternative theories, including claims for misrepresentation and fraudulent concealment.

In response to U.S. Pipeline's amended complaint, Northern's answer and counter-complaint denied that it owed U.S. Pipeline any compensation for the Extra Work and resources U.S. Pipeline did not anticipate and denied any liability to U.S. Pipeline for U.S. Pipeline's low bid. Northern's counter-complaint further alleged that pursuant to the contract, U.S. Pipeline materially missed the substantial completion date and overbilled Northern for the work it performed. Based on this and a liquidated damages provision within the parties' contract, Northern sought a declaratory judgment upholding Northern's decision to withhold payment of $351,000 from U.S. Pipeline as liquidated damages. Northern also sought a declaration from the district court upholding Northern's withholding of $320,000 in payment from U.S. Pipeline as a credit for U.S. Pipeline's change in the construction plan that resulted in a cost savings.

**448 2. SUMMARY JUDGMENT

Prior to trial, the court granted Northern partial summary judgment on the issue of whether U.S. Pipeline is entitled to indirect or consequential damages. The district court found that U.S. Pipeline admitted that it is not seeking damages for "indirect or consequential damages." The district court overruled Northern's motion for summary judgment on the remaining issues.

3. MOTIONS FOR DIRECTED VERDICT

A bench trial was held pursuant to a jury waiver contained in the parties' contract. At the close of U.S. Pipeline's case, Northern moved for a directed verdict, asserting that (1) U.S. Pipeline's damages were barred by the consequential damages waiver and (2) there was no genuine issue of fact on U.S. Pipeline's misrepresentation/fraudulent concealment claims regarding "geotechnical information." The court denied the motion. Northern later renewed the motion at the close of all the evidence, adding no further new grounds, and the court again denied the motion.

4. BENCH TRIAL

The following evidence was adduced during the parties' 2-week bench trial.

(a) Bidding and Northern's Original Project Plans

In 2013, Northern decided to replace or relocate approximately 29,450 feet, or 5.58 miles, of its Marquette main line (Marquette Replacement) and approximately 8,000 feet, or 1.52 miles, of its Ishpeming branch line (Ishpeming Relocation) (collectively the Project), both located in the Upper Peninsula of Michigan.

Northern designers prepared drawings for the Project. Northern's construction drawings called for the installation of new underground piping using open-cut installation *466 and horizontal directional drilling (HDD) techniques. Generally, **449 underground pipeline is installed through either an open-cut process or HDD. For an open-cut installation, a trench is excavated and the pipe is placed in the bottom of the trench and covered. An HDD, in contrast, is a steerable, trenchless method of installing underground pipe in an arc along a prescribed bore path by using a surface-launched drilling rig. HDD drilling is more complicated and expensive to install.

Specifically, Northern's construction drawings called for six HDD's-four locations along the Marquette Replacement (including the "Highway 476/Ely Creek" crossing) and two HDD's on the Ishpeming Relocation (including the "Cliffs Road" crossing). In addition, each set of Northern's drawings specified an arc radius of 525 feet on the 12-inch-diameter pipeline and 600 feet on the 6-inch-diameter pipeline. A governmental permit was granted for these specifications. The design arc radius or design radius of curvature is the radius of directional changes along the drill path. The arc radius is determined by several factors, including the desired distance between entry and exit points, the desired drill depth, direction changes for the drill path, and how much the drill stem and installed pipe can bend without being damaged.

In March 2014, Northern opened the bid process for the Marquette Replacement and Ishpeming Relocation. Northern issued notice of a mandatory onsite, pre-bid meeting and route inspection to be held on May 13 and 14, 2014. One of the purposes for the route inspection was to walk the pipeline route to provide bidders a better understanding of the site conditions, project layout, and access issues. Three prospective bidders and their subcontractors, along with Northern representatives, attended the pre-bid meeting and route inspection.

U.S. Pipeline sent Kris Osborn to represent U.S. Pipeline at the meeting and route inspection. Osborn drove to the pipeline on May 13, 2014, but he did not walk the route like other bidders. The meeting and route inspection continued on May 14, but Osborn did not attend. U.S. Pipeline's representative who created its bid for the Project confirmed that he was informed **450 that Osborn did not walk the pipeline route with the other bidders and Northern's representatives.

Free access — add to your briefcase to read the full text and ask questions with AI

U.S. Pipeline v. Northern Natural Gas Co., 303 Neb. 444, 930 N.W.2d 460 (Neb. 2019).

303 Neb. 444 (U.S. Pipeline v. Northern Natural Gas Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Campbell v. Bel Fury Investments
Nebraska Court of Appeals, 2026
Bentley v. Sandhills Aviation
Nebraska Court of Appeals, 2026
Magett v. CHI Health Immanuel Med. Ctr.
Nebraska Court of Appeals, 2025
State v. Dae
Nebraska Court of Appeals, 2025
Zapata v. Cederburg
Nebraska Court of Appeals, 2025
Kumke v. Palu
Nebraska Court of Appeals, 2024
State v. Bredemeier
Nebraska Court of Appeals, 2024
State v. Allen
314 Neb. 663 (Nebraska Supreme Court, 2023)
Slama v. Slama
987 N.W.2d 257 (Nebraska Supreme Court, 2023)
Lewis v. Goslin
Nebraska Court of Appeals, 2023
State v. Allen
Nebraska Court of Appeals, 2023
In re Interest of Draygon W.
31 Neb. Ct. App. 400 (Nebraska Court of Appeals, 2022)
Kingery Constr. Co. v. 6135 O St. Car Wash
979 N.W.2d 762 (Nebraska Supreme Court, 2022)
Trotter, Inc. v. Jacquot
Nebraska Court of Appeals, 2022
Herrera v. Herrera
Nebraska Court of Appeals, 2022
State v. Davis
Nebraska Court of Appeals, 2022
de Vries v. L & L Custom Builders
968 N.W.2d 64 (Nebraska Supreme Court, 2021)
Rodgers v. Rodgers
Nebraska Court of Appeals, 2021