U.S. Pipeline v. Northern Natural Gas Co.

303 Neb. 444
CourtNebraska Supreme Court
DecidedJune 28, 2019
DocketS-18-679
StatusPublished

This text of 303 Neb. 444 (U.S. Pipeline v. Northern Natural Gas Co.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
U.S. Pipeline v. Northern Natural Gas Co., 303 Neb. 444 (Neb. 2019).

Opinion

Nebraska Supreme Court Online Library www.nebraska.gov/apps-courts-epub/ 09/20/2019 08:06 AM CDT

- 444 - Nebraska Supreme Court A dvance Sheets 303 Nebraska R eports U.S. PIPELINE v. NORTHERN NATURAL GAS CO. Cite as 303 Neb. 444

U.S. Pipeline, Inc., appellee, v. Northern Natural Gas Company, appellant. ___ N.W.2d ___

Filed June 28, 2019. No. S-18-679.

1. Trial: Witnesses: Evidence: Appeal and Error. In a bench trial of an action at law, the trial court is the sole judge of the credibility of the witnesses and the weight to be given their testimony; an appellate court will not reevaluate the credibility of witnesses or reweigh testimony but will review the evidence for clear error. 2. Judgments: Appeal and Error. The trial court’s factual findings in a bench trial of an action at law have the effect of a jury verdict and will not be set aside unless clearly erroneous. 3. ____: ____. In reviewing a judgment awarded in a bench trial of a law action, an appellate court considers the evidence in the light most favor- able to the successful party and resolves evidentiary conflicts in favor of the successful party, who is entitled to every reasonable inference deducible from the evidence. 4. Judgments: Directed Verdict: Appeal and Error. In reviewing rul- ings on motions for directed verdict and judgments notwithstanding the verdict, an appellate court gives the nonmoving party the benefit of all evidence and reasonable inferences in his or her favor, and the question is whether a party is entitled to judgment as a matter of law. 5. Contracts: Judgments: Appeal and Error. The meaning of a contract is a question of law, in connection with which an appellate court has an obligation to reach its conclusions independently of the determinations made by the court below. 6. Damages: Appeal and Error. The amount of damages to be awarded is a determination solely for the fact finder, and its action in this respect will not be disturbed on appeal if it is supported by evidence and bears a reasonable relationship to elements of damages proved. 7. Contracts: Damages: Appeal and Error. The issue of whether dam- ages are consequential under a contract is a question of law that an - 445 - Nebraska Supreme Court A dvance Sheets 303 Nebraska R eports U.S. PIPELINE v. NORTHERN NATURAL GAS CO. Cite as 303 Neb. 444

appellate court reviews de novo, but the factual determinations underly- ing such a characterization are reviewed for clear error. 8. Expert Witnesses: Appeal and Error. The standard for reviewing the admissibility of expert testimony is abuse of discretion. 9. Contracts: Waiver: Damages. Generally, a contractual waiver or exclu- sion of consequential damages will be upheld unless the provision is unconscionable. 10. Contracts: Damages. Consequential damages, as opposed to direct damages, do not arise directly according to the usual course of things from a breach of contract itself. 11. ____: ____. Direct damages refer to those which the party lost from the contract itself—in other words, the benefit of the bargain—while conse- quential damages refer to economic harm beyond the immediate scope of the contract. 12. Trial: Evidence: Appeal and Error. Unless an objection to offered evidence is sufficiently specific to enlighten the trial court and enable it to pass upon the sufficiency of such objection and to observe the alleged harmful bearing of the evidence from the standpoint of the objector, no question can be presented therefrom on appeal. 13. Appeal and Error. An issue not properly presented and passed upon by the trial court may not be raised on appeal. 14. ____. In order to be considered by an appellate court, an alleged error must be both specifically assigned and specifically argued in the brief of the party asserting the error. 15. Waiver: Appeal and Error. Errors not assigned in an appellant’s initial brief are waived and may not be asserted for the first time in a reply brief. 16. Trial: Directed Verdict: Appeal and Error. In an appeal of a trial court’s refusal to enter a directed verdict, the appellate court should consider solely those grounds urged by the appellant to the trial court in support of its directed verdict motion. 17. ____: ____: ____. If a party fails to set forth certain arguments as grounds in a motion and renewed motion for directed verdict, such argu- ments will not be properly preserved for appeal. 18. Contracts: Waiver. The determination of whether a contractual provi- sion has been waived is a factual determination. 19. Contracts: Waiver: Damages. A contractual provision for liquidated damages for delay in performance may be waived. 20. Waiver: Estoppel. In order to establish a waiver of a legal right, there must be clear, unequivocal, and decisive action of a party showing such purpose, or acts amounting to estoppel on his or her part. - 446 - Nebraska Supreme Court A dvance Sheets 303 Nebraska R eports U.S. PIPELINE v. NORTHERN NATURAL GAS CO. Cite as 303 Neb. 444

21. Contracts: Waiver: Proof. A written contract may be waived in whole or in part, either directly or inferentially, and the waiver may be proved by express declarations manifesting the intent not to claim the advan- tage, or by so neglecting and failing to act as to induce the belief that it was the intention to waive. 22. Contracts: Waiver. Even a provision in a written contract that specifies that a waiver of the conditions and terms of the agreement must be in writing may be waived by acts or conduct.

Appeal from the District Court for Douglas County: Timothy P. Burns, Judge. Affirmed.

Gregory C. Scaglione, J. Daniel Weidner, Minja Herian, Michele E. Young, and Cassandra M. Langstaff, of Koley Jessen, P.C., L.L.O., for appellant.

Shawn D. Renner and Richard P. Jeffries, of Cline, Williams, Wright, Johnson & Oldfather, L.L.P., and Barrett H. Reasoner, Ayesha Najam, and Ross M. MacDonald, of Gibbs & Bruns, L.L.P., for appellee.

Heavican, C.J., Cassel, Stacy, Funke, and Freudenberg, JJ.

Freudenberg, J. I. NATURE OF CASE In 2014, a natural gas company solicited bids for a pipeline replacement and relocation project in northern Michigan. The natural gas company accepted a bid from a pipeline company, and the parties entered into a detailed construction contract. The contract provided that the project would be substantially completed by September 2014. However, because of extra work orders by the natural gas company and for various other reasons, the project was not substantially completed by that date. Based on a liquidated damages provision in the contract, the natural gas company withheld the maximum amount of liquidated damages allowable under the contract for the delay in the project’s completion. The natural gas company also refused to pay certain costs requested by the pipeline company - 447 - Nebraska Supreme Court A dvance Sheets 303 Nebraska R eports U.S. PIPELINE v. NORTHERN NATURAL GAS CO. Cite as 303 Neb. 444

related to the extra work orders. At the center of the lawsuit is whether the natural gas company should pay for the costs associated with the extra work and be allowed to withhold liq- uidated damages. II. FACTS 1. Pleadings In January 2016, U.S. Pipeline, Inc., a corporation engaged in the business of constructing oil and gas pipelines and related energy infrastructure facilities, filed a complaint in the dis- trict court for Douglas County against Northern Natural Gas Company (Northern), a corporation headquartered in Omaha, Nebraska, and engaged in the business of providing natural gas transportation and storage services. U.S. Pipeline sought com- pensation under a pipeline replacement and relocation project contract for costs incurred to perform work that was outside of the original contract price (Extra Work). U.S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Penncro Associates, Inc. v. Sprint Spectrum, L.P.
499 F.3d 1151 (Tenth Circuit, 2007)
Richmond Medical Supply Co. v. Clifton
369 S.E.2d 407 (Supreme Court of Virginia, 1988)
Pearce v. Elic Corp.
329 N.W.2d 74 (Nebraska Supreme Court, 1982)
Chestnut Hill Development Corp. v. Otis Elevator Co.
739 F. Supp. 692 (D. Massachusetts, 1990)
Davenport Ltd. v. 75th & Dodge I
780 N.W.2d 416 (Nebraska Supreme Court, 2010)
Reichert v. Rubloff Hammond, L.L.C.
645 N.W.2d 519 (Nebraska Supreme Court, 2002)
State v. Boham
447 N.W.2d 485 (Nebraska Supreme Court, 1989)
Crowley v. McCoy
449 N.W.2d 221 (Nebraska Supreme Court, 1989)
Adams v. American Cyanamid Co.
498 N.W.2d 577 (Nebraska Court of Appeals, 1992)
El Fredo Pizza, Inc. v. Roto-Flex Oven Co.
261 N.W.2d 358 (Nebraska Supreme Court, 1978)
Wiebe Construction Co. v. School District of Millard
255 N.W.2d 413 (Nebraska Supreme Court, 1977)
Hooper v. FREEDOM FINANCIAL GROUP, INC.
784 N.W.2d 437 (Nebraska Supreme Court, 2010)
Mondelli v. Kendel Homes Corp.
631 N.W.2d 846 (Nebraska Supreme Court, 2001)
McDonald v. Miller
518 N.W.2d 80 (Nebraska Supreme Court, 1994)
Creighton University v. General Electric Co.
636 F. Supp. 2d 940 (D. Nebraska, 2009)
State v. Hill
288 Neb. 767 (Nebraska Supreme Court, 2014)
McCoolidge v. Oyvetsky
874 N.W.2d 892 (Nebraska Supreme Court, 2016)
SOLIDFX, LLC v. Jeppesen Sanderson, Inc.
841 F.3d 827 (Tenth Circuit, 2016)
State v. Swindle
300 Neb. 734 (Nebraska Supreme Court, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
303 Neb. 444, Counsel Stack Legal Research, https://law.counselstack.com/opinion/us-pipeline-v-northern-natural-gas-co-neb-2019.