Creighton University v. General Electric Co.

636 F. Supp. 2d 940, 2009 U.S. Dist. LEXIS 64515, 2009 WL 2096015
CourtDistrict Court, D. Nebraska
DecidedJuly 14, 2009
Docket8:08CV460
StatusPublished
Cited by19 cases

This text of 636 F. Supp. 2d 940 (Creighton University v. General Electric Co.) is published on Counsel Stack Legal Research, covering District Court, D. Nebraska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Creighton University v. General Electric Co., 636 F. Supp. 2d 940, 2009 U.S. Dist. LEXIS 64515, 2009 WL 2096015 (D. Neb. 2009).

Opinion

MEMORANDUM AND ORDER *

RICHARD G. KOPF, District Judge.

In a memorandum and order entered on March 18, 2009 (filing no. SI), the court determined, among other things, that: (1) the plaintiff, Creighton University, had not pleaded, and therefore could not argue, that a damages disclaimer in its contract with the defendant, General Electric Company, 1 is unconscionable; (2) this contract clause prevents Creighton from seeking to recover consequential damages for (a) loss of an anticipated $4.7 million increase in revenue, and (b) loss of income from uncollected billings in the amount of $2.4 million; and (3) the disclaimer also prevents Creighton from seeking to recover incidental damages for collection costs.

On May 29, 2009, 2 Creighton filed a motion for leave to file an amended complaint (1) to reclassify the $2.4 million in lost income as direct damages; (2) to allege in the alternative that the damages disclaimer is unconscionable; (3) as an alternative measure of damages, to seek to recover between $1.4 and $3 million for the difference between the value of the system as warranted and its actual value; (4) to allege that additional representations were made regarding system performance; (5) to add a new claim for breach of an oral agreement for reimbursement of a portion of the collection costs; and (6) to itemize out-of-pocket costs. GE opposes all aspects of the motion. I will grant Creighton leave to amend its complaint in some respects, and will direct it to file a modified version of the proposed amended complaint. 3

(1) Loss of Income

As discussed in my previous memorandum, the $2.4 million in net billings that Creighton allegedly was unable to collect because of programming deficiencies and delayed implementation of some parts of the system must be categorized as an item of consequential damages. “Consequential damages, as opposed to direct damages, do not arise directly according to the usual course of things from the breach itself; rather, they occur as a consequence of *943 special circumstances known or reasonably supposed to have been contemplated by the parties when the contract was made.” Adams v. American Cyanamid Co., 1 Neb. App. 337, 498 N.W.2d 577, 588 (1992) (farmers’ claim against herbicide manufacturer for crop loss concerned consequential damages rather than direct damages). Paragraph 27 of the parties’ agreement provides that GE shall not be liable “for any consequential, special, incidental, punitive or indirect damages (including without limitation loss of profit, revenue, business opportunity or business advantage),.... ” (Filing no. 1-2 (Exhibit Á to complaint), p. 18.)

In an attempt to avoid this contractual provision, Creighton would allege that “[t]hese damages were naturally expected to follow from breach of the Agreement because the net billings would have been collected had the System been able to process claims in a timely manner so that claims could be submitted to payors within deadlines established by payors for the submission of claims.... The $2.4 million in uncollected claims are direct damages that Creighton suffered as a result of GE’s breach of contract and negligent misrepresentations.” (Filing no. 46-2 (proposed amended complaint), pp. 5-6, ¶¶ 11, 12.) 4 Labeling the $2.4 million in uncollected claims “direct damages” does not make them so. In fact, the allegation that the claims were uncollectible because they were not submitted within deadlines established by payors shows that the loss of income was attributable to special circumstances.

Creighton’s proposed amendments regarding the alleged $2.4 million loss will not be permitted because they do not avoid the contract’s exclusion of consequential damages. “Futility is a valid basis for denying leave to amend.” United States ex rel. Roop v. Hypoguard USA, Inc., 559 F.3d 818, 822 (8th Cir.2009).

(2) Unconscionability

“Pleading in the alternative in the event that the $2.4 million in uncollected claims are deemed to be consequential damages,” Creighton next alleges that “the damages disclaimer in paragraph 27 of the Agreement is unconscionable because it would prevent Creighton from recovering damages directly resulting from the failure of the System to process claims in a timely manner so that claims could be submitted to payors within deadlines established by payors for the submission of claims.” (Filing no. 46-2, p. 6, ¶ 12.) GE objects that no facts are alleged to establish that the damages disclaimer is procedurally or substantively unconscionable, and argues that the contract was negotiated by parties of equal bargaining power.

The unconscionability of a contract provision presents a question of law. See Melcher v. Boesch Motor Co., 188 Neb. 522, 198 N.W.2d 57 (1972). When considering whether an agreement is unconscionable, [the Nebraska Supreme Court] has stated that the term “unconscionable” means manifestly unfair or inequitable. See Weber v. Weber, 200 Neb. 659, 265 N.W.2d 436 (1978).
A contract is not substantively unconscionable unless the terms are grossly unfair under the circumstances that existed when the parties entered into the contract. Adams v. American Cyanamid Co., 1 Neb.App. 337, 498 N.W.2d 577 *944 (1992). In a commercial setting, however, substantive unconscionability alone is usually insufficient to void a contract or clause. See id., citing 1 E. Allan Farnsworth, Farnsworth on Contracts § 4.28 (2d ed. 1990). A court must also consider whether the contract formation was procedurally unconscionable. See id. 5

Myers v. Nebraska Inv. Council, 272 Neb. 669, 724 N.W.2d 776, 799 (2006).

While Creighton adequately alleges that the damages disclaimer clause is substantively unconscionable insofar as it bars recovery of consequential damages for loss of income resulting from delays in claim processing, 6 there are no facts alleged in the proposed amended complaint which would support a finding of procedural unconscionability. In fact, Creighton alleges that it sought proposals from other vendors, and the contract itself recites that “the terms and conditions of this Agreement have been the subject of active and complete negotiations[J” (Filing no. 46-2, p.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

U.S. Pipeline v. Northern Natural Gas Co.
303 Neb. 444 (Nebraska Supreme Court, 2019)
Hawkins Construction Co. v. Peterson Contractors, Inc.
970 F. Supp. 2d 945 (D. Nebraska, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
636 F. Supp. 2d 940, 2009 U.S. Dist. LEXIS 64515, 2009 WL 2096015, Counsel Stack Legal Research, https://law.counselstack.com/opinion/creighton-university-v-general-electric-co-ned-2009.