Troy v. RFD-TV The Theater, LLC

498 S.W.3d 550, 2016 Tenn. App. LEXIS 200
CourtCourt of Appeals of Tennessee
DecidedMarch 18, 2016
StatusPublished
Cited by23 cases

This text of 498 S.W.3d 550 (Troy v. RFD-TV The Theater, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Troy v. RFD-TV The Theater, LLC, 498 S.W.3d 550, 2016 Tenn. App. LEXIS 200 (Tenn. Ct. App. 2016).

Opinion

OPINION

Brandon O. Gibson, J.,

delivered the opinion of the court, in which

Frank G. Clement, Jr., P.J., M.S. and W. Neal McBrayer, J., joined.

This appeal arises out of a breach of contract action filed by a musical performer after the defendant venue owner can-celled the show in which the plaintiff performed. The trial court found in favor of the plaintiff performer and ordered the [553]*553defendant to pay $70,744 in damages for breach of contract, $59,864.18 in prejudgment interest, and $90,000 in attorney’s fees. The defendant appeals, arguing that the awards of prejudgment interest and attorney’s fees were erroneous according to Nebraska law, which the parties chose to govern their contract. For the following reasons, we reverse and remand for further proceedings.

I. Facts & Procedural History

Plaintiff Troy L. Boswell is a musical performer and a resident of Goodlettsville, Tennessee. He is professionally known as “Leroy Troy.” Defendant RFD-TV The Theater, LLC (the “Theater”) owns and operates a musical venue in Branson, Missouri. On February 5, 2007, the Theater entered into an entertainment services agreement (the “Contract”) with Boswell. Pursuant to the Contract, the Theater agreed to purchase from Boswell “[m]usical performances for the 2007 season,” with a starting date of March 1, 2007, and an ending date of October 31, 2007. The Contract listed 21 dates during that period when Boswell would be unavailable, due to previous bookings, and the parties agreéd that a pro-rata amount of $715 per day would be deducted from Boswell’s weekly fee for those absences. The Contract provided that Boswell’s shows would last no more than 45 minutes, and he would perform no more than ten shows per week. However, the specific show dates and times were “[t]o be determined and mutually agreed upon by both parties.”

The Contract provided that from March 1 until the opening date of the venue, the Theater would pay Boswell $2,500 per week for rehearsals. Once the venue opened to the public, the Theater would pay Boswell $5,000 per week for the services provided. The Theater agreed to pay a $5,000 deposit to Boswell upon execution of the agreement, which would be applied to the payment for the final week of the contract term. The Contract also contained the following provisions:

BREACH OF CONTRACT. In the event of any action, suit or proceeding arising from or based on this agreement brought by either party hereto against the other, the prevailing party shall be entitled to recover from the other its reasonable attorney’s fees in connection therewith in addition to the costs of that action, suit or proceeding.
GOVERNING LAW. This Agreemént shall be governed by and construed in accordance with the laws of the State of Nebraska.1

The parties agree that the Theater paid Boswell the $5,000 deposit as an advance payment for his final week of performances, and it also paid him $2,500 per week for rehearsals from March 1 until March 29, 2007, when the Theater opened to the public. Thereafter, Boswell performed a total of 60 shows at the Theater from its public opening on March 29 through June 28, 2007. The Theater paid Boswell $5,000 per week during that time. However, on July 1, 2007, the president of the Theater called a meeting with all staff and crew and announced that the show was can-celled.

On July 9, 2007, Boswell’s attorney sent a letter to the Theater advising it that Boswell was ready, willing, and able to perform pursuant to the parties’ Contract. The letter suggested that the Theater was “in material breach” of the Contract by terminating Boswell’s weekly payments of $5,000 and indicating that it would no longer honor the Contract. The letter stated [554]*554that Boswell was making every effort to mitigate his damages, but due to such late notice, he had not been successful -in his efforts., Boswell claimed that he was entitled to $5,000 for the previous week’s missed payment and “approximately $80,000 in additional compensation.” He requested that the Theater contact his attorney “to work out payment of damages,” but the Theater never responded to the letter or made payment to Boswell as requested in the letter.

On October 11, 2007, Boswell filed this lawsuit in Davidson County Circuit Court. He named as defendants the Theater and other separate but related entities. The complaint sought recovery based on breach of contract and/or promissory es-toppel. The complaint alleged that the term of the Contract was from March 1, 2007, until October 31, 2007, and therefore, the Theater breached the Contract by can-celling the show on July 1, 2007, and discontinuing payments to Boswell. Boswell alleged that he was ready, willing, and able to perform under the Contract but was not allowed to do so. He sought damages for breach of contract in the amount of $82,140. Specifically, he sought $5,000 for each of the remaining weeks of the contract (equaling $90,000), minus the $5,000 deposit already paid, minus the pro rata fee of $715 for four days he would have missed during the remainder of the contract term, totaling $2,860. He also sought an award of prejudgment interest and an award of attorney’s fees as provided in the parties’ Contract.

The case remained pending for several years.2 Throughout the proceedings, the parties agreed that Nebraska law applied to the substantive issues in the case, while Tennessee law governed procedural issues. The parties stipulated that the Theater had already paid Boswell a total of $77,500 pursuant to the Contract. However, the Theater asserted that it had no further obligation to pay Boswell after it cancelled the show on July 1, 2007, because the Contract provided that show dates and times were “[t]o be determined and mutually agreed upon by both parties.” The Theater claimed that this constituted an unenforceable “agreement to agree.”

The trial court held a bench trial from November 17 to November 19, 2014. On March 4, 2015, the court entered a final order entering a judgment in favor' of Boswell. The trial court found the contract enforceable, valid, and unambiguous. The court concluded that the Contract was for a specific term—from March 1 through October 31, 2007. The court concluded that Boswell was obligated to be available to perform during that time, with specific dates and times to be determined on an ongoing basis, and it found that his payment was not conditioned on the number of his performances. The court found that the Theater materially breached the Contract by cancelling the show on July 1, 2007, due to no fault of Boswell, and by failing to pay him the weekly sum due under the Contract.’

■ The trial court looked to the Contract to calculate Boswell’s damages. It found that he was entitled to be paid $2,500 per week for the four-week period between March 1 and the opening of the Theater on March 30, 2007, for a total of $10,000, in addition to $5,000 per week for the remaining thir[555]*555ty-one weeks of the Contract term, for a total of $155,000. In sum, he was to be paid $165,000 during the term of the Contract. As noted above, the Theater paid Boswell $77,500 prior to cancellation of the show. The trial court found that the Theater .was entitled to deduct from the amount owed the pro rata allowance for the 21 dates specified in the Contract for previously booked performances, at the rate of $715 per day, for a total deduction of $15,015.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
E.D. Tennessee, 2026
John F. Curran v. Only Motorsports, LLC
Court of Appeals of Tennessee, 2025
Poplar Avenue 1856 Center, LLC v. Nexus Exxon, Inc.
Court of Appeals of Tennessee, 2025
Mark DeLong v. Brian Paul General Partner, LLC
Court of Appeals of Tennessee, 2021
W. Douglas Harris v. Gary McMichael
Court of Appeals of Tennessee, 2021
O'Shields v. Columbia Automotive, LLC
Court of Appeals of South Carolina, 2021
1600 Barberry Lane 8 v. Cottonwood Residential
2021 UT 15 (Utah Supreme Court, 2021)
In Re Conservatorship of Annette H. Cross
Court of Appeals of Tennessee, 2020

Cite This Page — Counsel Stack

Bluebook (online)
498 S.W.3d 550, 2016 Tenn. App. LEXIS 200, Counsel Stack Legal Research, https://law.counselstack.com/opinion/troy-v-rfd-tv-the-theater-llc-tennctapp-2016.