World Classic Productions, Inc. v. RFD-TV The Theater, LLC

498 S.W.3d 874, 2016 Tenn. App. LEXIS 197
CourtCourt of Appeals of Tennessee
DecidedMarch 17, 2016
DocketM2015-00638-COA-R3-CV
StatusPublished

This text of 498 S.W.3d 874 (World Classic Productions, Inc. v. RFD-TV The Theater, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
World Classic Productions, Inc. v. RFD-TV The Theater, LLC, 498 S.W.3d 874, 2016 Tenn. App. LEXIS 197 (Tenn. Ct. App. 2016).

Opinion

OPINION

BRANDON O. GIBSON, J.,

delivered the opinion- of the court, in which

FRANK G. CLEMENT, JR., P.J., M.S., and W. NEAL McBRAYER, J., joined.

This appeal arises out of a breach of contract action. The plaintiff is a corporate entity that represents a musical group. The defendant is a venue owner that cancelled the show in which the musical group performed. After a bench trial, the trial court found in favor of the plaintiff and ordered the defendant venue owner to pay $195,741.86 in damages for breach of contract and $166,353.77 in prejudgment interest. The defendant appeals, arguing that the award of prejudgment interest was erroneous according to Nebraska law, which the parties chose to govern their contract. For the following reasons, we reverse and remand for further proceedings.

I. Facts & Procedural History

World Classic Productions, Inc. (“WCP”) is a Tennessee corporation that represents.a musical entertainment group known as “The Sons of Tennessee.” The musical group - performs primarily on horseback. Defendant RFD-TV The Theater, LLC (the “Theater”) owns and operates a musical venue in Branson, Missouri. On January 11, 2007, the Theater entered into an entertainment services agreement (the “Contract”) with WCP. Pursuant to *876 the Contract, The Sons of Tennessee would provide “[m]usical performances on stage and on horseback for the 2007 season” at the Theater, with a starting date of March 19, 2007, and an ending date of December 30, 2007. The Contract provided that the shows would last no more than 45 minutes, ■ and The Sons of Tennessee would perform no more than ten shows per week. However,- the specific show dates and times were “[t]o be determined and mutually agreed upon by both parties.” The Sons of Tennessee would provide entertainment “for shows scheduled during the time period outlined above.” The Contract further provided:

While the original intent is for [WCP] to provide services through December 30, 2007, in accordance with the provisions set forth in this agreement, [the Theater] has the option to terminate the agreement on November 1, 2007, to facilitate a separate Christmas Show, if desired.

Regarding payment, the Contract provided that the Theater would pay WCP for the services provided “a guarantee of Four Hundred Forty Four Thousand Dollars ($444,000.00) for the period of April 1, 2007 -through October • 28, 2007 (30 weeks).” Specifically, the Theater would pay WCP $14,800 “on each Friday during the agreement.” The Theater agreed to make an advance payment to WCP of $59,200 at the signing of the Contract for services provided -the last four weeks of the engagement.

' In the Contract, the Theater agreed to provide a climate- controlled staging area and horse facility - connected to its main theater for protection against the elements.- The Contract acknowledged that permanent horse facilities might not be completed in- time for the start of the engagement, but the Theater agreed to proceed with due diligence to provide the necessary facilities and to provide and pay for any temporary facilities that were needed to facilitate the performances. The Theater specifically acknowledged in the Contract that performing on horseback with musical instruments is a specialized act and that the group’s equipment could be susceptible to damage from inclement weather elements and certain facility conditions. Accordingly, the Contract gave The Sons of Tennessee “the right to cancel a performance or performances without penalty, if in their sole judgment, proceeding with a performance would jeopardize, harm or damage equipment, animals or personnel.” The Contract provided that it would be governed by and construed in accordance with the laws of the State of Nebraska, which was the location of the corporate headquarters of the Theater.

The Sons of Tennessee began performing at the Theater as agreed, but the Theater never constructed the horse facilities required by the Contract. As a result, WCP incurred expenses related to the care of the horses and sought reimbursement from the Theater. However, the Theater refused to reimburse WCP for the expenses.

On July 1, 2007, the president of the Theater called a meeting with all staff and crew and announced that the show was cancelled. The Theater discontinued its weekly payments to WCP. On July 10, 2007, WCP sent a letter to the Theater notifying it that The Sons of Tennessee was ready, willing, and able to perform pursuant to the Contract. WCP claimed that the Theater had breached the Contract by terminating' the show. As a result, WCP demanded its weekly fee of $14,800 for 26 weeks, spanning from July 1 through December 30, 2007, for a total of $384,800. WCP also demanded payment of $9,316.82 in expenses it incurred due to the Theater’s failure to construct the horse facilities. WCP acknowledged the $59,200 *877 advance payment it had received and deducted that sum from the total amount of damages it was claiming. In sum, WCP advised the Theater that the final amount owed was $334,916.82. The Theater did not make the payment requested in WCP’s letter and claimed it had no obligation to make further payments under the Contract after it cancelled the show and performances ceased.

On October 5, 2007, WCP filed this lawsuit in Davidson County Circuit Court. The complaint named as defendants the Theater and other separate but related entities. It sought recovery based on breach of contract and/or promissory es-toppel. , The complaint alleged that the term of the Contract was from March 19, 2007, until December 30, 2007, and therefore, the Theater breached the Contract by cancelling the show on July 1, 2007, and discontinuing payments to WCP. WCP alleged that The Sons of Tennessee was ready, willing, and able to perform under the Contract but was not allowed to do so. WCP calculated its base damages ' for breach of contract in the amount of $325,600. Specifically, it calculated $14,800 for each of the weeks between July 1 and December 30, 2007 (equaling $384,800), minus the $59,200 deposit already paid. WCP claimed that it had made all necessary efforts to mitigate its damages. WCP also sought to recover $9,316.82 for expenses related to the temporary horse facilities due to the Theater’s failure to construct the facilities required by the Contract. The total of these two sums was $334,916.82, the same amount demanded in WCP’s previous letter to the Theater. WCP also sought an award of prejudgment interest.

The case remained pending for several years. The trial court held a bench trial from January 26 to January 29, 2015. On March 4, 2015, the trial court entered a final order entering a judgment in favor of WCP. The trial court found that The Sons of Tennessee performed every time it was requested to perform, for a total of approximately 111 shows. The court found that The Sons of Tennessee justifiably performed without their horses for approximately 9 shows due to inclement weather and another 9 or 10 shows due to the presence of larger bands on stage for guest stars. The trial court concluded that WCP did not breach the Contract and that the Theater cancelled the show due to no fault of WCP. It found that the Theater materially breached the Contract by failing to construct the horse facilities, failing to reimburse WCP for its additional expenses, cancelling the show, and discontinuing its payments to WCP.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lee Medical, Inc. v. Paula Beecher
312 S.W.3d 515 (Tennessee Supreme Court, 2010)
Win Myint and wife Patti KI. Myint v. Allstate Insurance Company
970 S.W.2d 920 (Tennessee Supreme Court, 1998)
Standard Fire Insurance Co. v. Chester-O'Donley & Associates, Inc.
972 S.W.2d 1 (Court of Appeals of Tennessee, 1998)
First Data Resources, Inc. v. Omaha Steaks International, Inc.
307 N.W.2d 790 (Nebraska Supreme Court, 1981)
Otis v. Cambridge Mutual Fire Insurance Co.
850 S.W.2d 439 (Tennessee Supreme Court, 1993)
Charles Hampton's A-1 Signs, Inc. v. American States Insurance Co.
225 S.W.3d 482 (Court of Appeals of Tennessee, 2006)
Gottsch Feeding Corp. v. Red Cloud Cattle Co.
429 N.W.2d 328 (Nebraska Supreme Court, 1988)
Classen v. BECTON, DICKINSON AND CO.
334 N.W.2d 644 (Nebraska Supreme Court, 1983)
Wiebe Construction Co. v. School District of Millard
255 N.W.2d 413 (Nebraska Supreme Court, 1977)
A.G.A. Inc. v. First National Bank
474 N.W.2d 655 (Nebraska Supreme Court, 1991)
Slusarski v. American Confinement Systems, Inc.
357 N.W.2d 450 (Nebraska Supreme Court, 1984)
Land Paving Co. v. D. A. Construction Co.
338 N.W.2d 779 (Nebraska Supreme Court, 1983)
Spencer Ex Rel. Spencer v. A-1 Crane Service, Inc.
880 S.W.2d 938 (Tennessee Supreme Court, 1994)
Rampy v. ICI Acrylics, Inc.
898 S.W.2d 196 (Court of Appeals of Tennessee, 1994)
State ex rel. Smith v. Early
934 S.W.2d 655 (Court of Appeals of Tennessee, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
498 S.W.3d 874, 2016 Tenn. App. LEXIS 197, Counsel Stack Legal Research, https://law.counselstack.com/opinion/world-classic-productions-inc-v-rfd-tv-the-theater-llc-tennctapp-2016.