Jobst v. Hayden Bros.

121 N.W. 957, 84 Neb. 735, 1909 Neb. LEXIS 251
CourtNebraska Supreme Court
DecidedJune 11, 1909
DocketNo. 15,612
StatusPublished
Cited by12 cases

This text of 121 N.W. 957 (Jobst v. Hayden Bros.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jobst v. Hayden Bros., 121 N.W. 957, 84 Neb. 735, 1909 Neb. LEXIS 251 (Neb. 1909).

Opinion

Calkins, C.

This was an action by the plaintiff to foreclose a mechanic’s lien upon a building which he had erected under a written contract with the defendant Hayden Brothers, a corporation, hereinafter called the owner. A portion of his claim was for the remainder of the contract price, to which were added for extras sundry items. The owner contested a portion of these claims for extras, and demanded a large sum for defects in construction and damages for delay in the completion of the building. The dis[737]*737trict court allowed part of plaintiff’s claim for extras, and deducted from the plaintiff’s contract price for defects in construction, $100 for the freezing of the west wall, and $500 on account of defective floor topping. It found that the owner agreed to and did'release the plaintiff from any and all claims for damages on account of delay in completing the building, and rendered judgment against it for the sum of $9,520.38.

1. It appears that the plaintiff first entered into a contract with the owner for the construction of a building, which was designed with re-enforced concrete columns, on the 28th day of March, 1905; that the city inspector, not being at that time acquainted with this method of construction, refused to approve the plans, and the design was changed so as to call for steel columns in place of the other; and that on April 12 an additional contract was made providing for the latter construction and for the payment of the increased expense that the same entailed. Between the date of the execution of these two contracts, a contract was entered into between the plaintiff, on the one part, and the defendants Lehmer and Collins, on the other, which recited that the latter had the exclusive agency for a certain system of re-enforced concrete construction, and provided that certain specified parts of whatever work of that class should be contracted for by the plaintiff should be executed .by the said Lehmer and Collins.

After the making of the' contract between the plaintiff and the owner, the plaintiff entered into a supplemental contract with Lehmer and Collins in reference to the construction of the Hayden building, under which the plaintiff agreed to execute certain specified parts of such construction, and the said Lehmer and Collins agreed to execute certain other parts, each for a fixed price. The plaintiff filed a mechanic’s lien for the entire amount claimed to be due upon the contract, and Lehmer and Collins filed a lien for the amount claimed to be due them, [738]*738on the theory that they were to be regarded as subcontractors. The court found that the plaintiff and Lehmer and Collins were a partnership, but permitted the plaintiff to prosecute this action for the use of such partnership, and in entering its decree made the same for the benefit of the plaintiff and the said Lehmer and Collins. There is no contest between Jobst and Lehmer and Collins, but the owner questions the right of Jobst to bring the suit in his own name. Whether the agreement referred - to constituted Lehmer and Collins partners with Jobst, or simply made them subcontractors, we do not deem it necesssary to determine. If such agreement did constitute a partnership, then the action should have been in the name of all the members of the firm. Under this assumption there was a defect of parties plaintiff, which constitutes the fourth ground of demurrer under section 94 of the code. Section 96 of the code provides that, if no objection be taken either by demurrer or answer, the defendant shall be deemed to have waived the same. The facts concerning the interest of these parties were fully disclosed upon the face of the petition, and the owner therefore waived the same by a failure to demur.

2. Further, section 145 of the code requires that no judgment shall be reversed on account of any error Avhich does not affect the substantial rights of the adverse party. In this case all the parties were before the court, and the owner is as fully protected against any claims that might be made by Lehmer and Collins as it would have been had. they been made parties plaintiff instead of defendants. It is not pointed out how the oAvner is prejudiced by this alleged error of the court, and, in the absence of such prejudice, the judgment should not be reversed, even assuming the position of the OAvner as to the proper parties to be correct.

3. The owner complains that the alloAvance of $100 for the defect in the west wall and'$500 for defects in the topping of the floor was insufficient, and Ave are asked to re-examine the question of fact passed upon by the lower [739]*739court. After a careful reading of a most voluminous record, we are unable to say that the court below should have arrived at a-different conclusion than was reached. There was evidence which would have justified a conclusion that the work was very poor in quality, and, opposed to this, testimony that the work fulfilled the conditions of the specifications of the contract. Under these circumstances the finding of the district court will not be set aside.

4. The contract contained the provision: “No alteration shall be made in the work done or described by the drawings and specifications except upon a written order from the architect; and Avlien so made the Avalué of the work added or omitted shall be computed by the architect, and the amount so ascertained shall he added to or deducted from the contract price.” The court included in its decree six items for which it is contended the architect had not made a Avritten order, and it is insisted as a matter of laAV that, under the above quoted proAdsion, they cannot be allowed. Only two of these items are argued in the brief. It is admitted that, on account of the caving in of the earthen embankment during the winter, it was found expedient to extend- the basement and subbasement some eight feet farther into the street than was originally intended. This involved going that distance beyond the curb, which was the boundary according to the original plans. It necessitated additional brick work and the use of heavier steel to support the weight of the roadway above. It is not contended that the work was not performed with the knowledge and under the direction of the architect, and that it did not impose an extra burden and additional expense upon the contractor. The other item was for a change in the form of foundation in the northern part of the west wall made necessary, or at least expedient, by conditions which we will notice more fully ■hereafter. It is enough to say that it was found impracticable to proceed Avith the work in this part of the construction according to the original specifications. There [740]*740was a sketch or plan for the new work, which the testimony shows was approved by the architect; but this document had apparently been lost at the time of the trial. There is no question made as to the merit of these claims, but it is insisted that the above quoted clause in the contract prohibits their allowance. We do not. think this clause susceptible of the construction contended for. It does not provide that the contractor shall forfeit his right to compensation for extras performed by him at the request of the owner or the architect without the written direction stipulated for. The evidence abundantly establishes that the extras so complained of were performed at the direction and upon the request of the owner and architect, and the clause in the contract quoted does not prevent their allowance.

5.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southwest Engineering Co. v. Reorganized School District R-9
434 S.W.2d 743 (Missouri Court of Appeals, 1968)
City of Scottsbluff v. Western Public Service Co.
254 N.W. 712 (Nebraska Supreme Court, 1934)
Sesto v. City of Omaha
238 N.W. 357 (Nebraska Supreme Court, 1931)
Sartoris v. Utah Const. Co.
21 F.2d 1 (Ninth Circuit, 1927)
North American Ginseng Co. v. Gilbertson
206 N.W. 610 (Supreme Court of Iowa, 1925)
Merritt v. Johnston
192 N.W. 734 (Nebraska Supreme Court, 1923)
Stone v. Stine
178 N.W. 838 (Nebraska Supreme Court, 1920)
Cady v. Travelers Insurance
142 N.W. 107 (Nebraska Supreme Court, 1913)
McGowan v. Gate City Malt Co.
130 N.W. 965 (Nebraska Supreme Court, 1911)
Jobst v. Hayden Bros.
129 N.W. 992 (Nebraska Supreme Court, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
121 N.W. 957, 84 Neb. 735, 1909 Neb. LEXIS 251, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jobst-v-hayden-bros-neb-1909.