Groner v. Cavender

133 So. 825, 16 La. App. 565, 1931 La. App. LEXIS 105
CourtLouisiana Court of Appeal
DecidedFebruary 26, 1931
DocketNo. 3790
StatusPublished
Cited by7 cases

This text of 133 So. 825 (Groner v. Cavender) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Groner v. Cavender, 133 So. 825, 16 La. App. 565, 1931 La. App. LEXIS 105 (La. Ct. App. 1931).

Opinions

McGREGOR, J.

The plaintiff brings this suit in the form of a concursus proceeding under the provisions of Act No. 139 of 1922. There was a written contract between Morris Groner, plaintiff, and R. J. Cavender, defendant, dated May 18, 1926, wherein the defendant contracted to remodel certain premises for the plaintiff at 444 Stoner avenue in the city of Shreveport, for the contract price of $4,679.56. This contract was based on written plans and specifications, both of which were very loosely drawn. In the specifications there ' is indicated the following stipulations:

“* * * Should alterations be suggest- ' ed or deviations from plans or specifications arise same shall be agreed to by all parties concerned and either credits or additional charges ‘as the case may be’ ¡ entered • or attached to these specifica- ' tions.” . ;

Upon the interpretation of this clause and the law applicable to such cases de- ; pend in a large measure the issues in- ; volved in this' case. In his petition the • plaintiff alleged that he had paid to the 'defendant the sum of $4,600 on the contract price; that the work had been com- ■ pleted, and that he had executed an acceptance of the work and caused it .to be recorded in the mortgage record in the form and manner provided by law; that there was a balance of $79.56 due the defendant contractor on the contract price; and that there was an additional sum of $155.65 due him for extra work and material performed upon and furnished on the said job which was not included in the written contract, thus making a total of $235.21 due by the plaintiff to the defendant on account of the said job of remodeling the said premises. Plaintiff further alleged that there had been recorded a large number of liens on the said job amounting to the sum of $2,117.29 said to be due to the several lienors for materials ■ furnished to the defendant and used by him in the said remodeling job. It is still further alleged that the defendant himself had filed a lien on the job for the sum of $892,12 for labor and material alleged to have been performed and furnished by him as extras over and beyond 'that called for and provided for in the written contract. 'Plaintiff took $50 of the $235.21 adñiitted to be due by him, and used it to file this suit, and deposited the balance, or $185.21, in the court in accordance with the statute. It is further alleged that the defendant R. J. 'Cavender and the Indemnity 'Insurance Company of North America,'as surety, executed and delivered a bond in the principal- sum of _$4,679.56, and that this bond, together with the 'contract, had been duly filed and recorded in the mortgage records of Caddo parish as required by law. The said surety company was made a party defendant in the case. The defendants answered, admitting the contract and the liens filed, but alleged that the balance due the contractor by the plaintiff, was the sum of $892.12, including the sum of $235.21 admitted by the plaintiff in his petition and deposited by [567]*567him in the court. The sum of $656.21 is therefore claimed by the defendant as plaintiff in reconventional demand for extra labor and material performed and furnished on the said remodeling job.

There was judgment in the lower court in favor of the plaintiff against the defendant contractor and all the lienholders and canceling and erasing all of the liens filed against the plaintiff’s property on account of said contract and bond, and particularly the special lien filed by the defendant contractor for the extra labor and material claimed to have been furnished by him. There was also judgment in favor of plaintiff in solido against the defendant contractor and the Indemnity Insurance Company of North America and the fund deposited by the plaintiff for the sum of $250 attorneys’ fees for the concursus proceedings and for all costs of the suit. There was also judgment in favor of the several lienholders against the contractor and the surety company for the respective sums shown to have been due them on the trial of the case. The reconventional demand of the defendant contractor was rejected, and judgment for $2,355.29 was granted in favor of the Indemnity Insurance Company of North America against the defendant contractor. The contractor and the surety company have appealed from that part of the judgment rejecting the contractor’s reconventional demand and canceling the lien filed and recorded by him.

As stated, the contractor’s reconventional demand is for the sum of $892.12. A part of this is admitted by the plaintiff in his petition—$79.56 balance due ’ on 'the contract price and $155.65 for extra labor and material furnished on the job, so that the amount in dispute is the sum of $656.21.

Because of- the clause in the specification reading: “* *■ * Should alterations be suggested or deviations from plans • or specifications- arise same shall be agreed to by all parties concerned and either credits or additional charges ‘as the case may be’ entered or attached to these specifications,” the plaintiff contends that none of the amounts which are claimed by the contractor should be allowed, as none of the extras in the form of labor and material were agreed upon in advance by the parties in writing, and that none of them were indicated and provided for in the plans and specifications. To support their position,- counsel for plaintiff cite article 2276 of the Revised Civil Code, but.this article must be read 'in connection with article 2275, and, when this ' is done, we find that the two articles deal primarily with the transfer of immovables, so that that article does not' govern the case at bar. Articles 2763 and 2764 evidently govern here. Those articles specially provide that, even though a contract is reduced to writing by the owner and the contractor, and the building is being -erected in accordance with the written plans and specifications, the contractor can claim pay for extra labor and material if he can prove that the extra labor and material were performed and furnished in compliance with the “wishes of the owner,” and “in a ease where the alteration or increase is so great, that it can not be supposed to have been made without the knowledge of the owner, and also where the alteration or increase was necessary and has not been foreseen.” - Under those two' articles of the Code, it would seem to be clear that, if the defendant contractor can prove that the various items claimed by him in his reconventional demand complied “with the wishes” of the plaintiff, or that they were so great or patent “that it cannot -be supposed to have been made without the [568]*568knowledge of the owner,” he should recover. In the case of Wellman v. Smith, et al., 114 La. 228, 38 So. 151, 152, the Supreme Court considered this question, and in the course of its opinion said:

“The -contract provided that no change in the plan, and extra work in that connection, would be paid for unless the work was done in accordance with written order.
“The owner cites Maas v. Succession of Hernandez, 48 La. Ann. 264, 19 So. 269, and Monarch & Kaiser v. Board, 49 La. Ann. 991, 22 So. 259, in support that $200 for extra work should not be allowed.
“In the cases cited, the testimony did not prove that the owner knew anything about the extra work. It follows that he had not assented to- it. Here the work was done. The owner was frequently about the ■building, and saw the improvements as they were made. It is not shown that the least objection was ever made, nor that they have not received full consideration.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pelican Elec. Contractors v. Neumeyer
419 So. 2d 1 (Louisiana Court of Appeal, 1982)
Smith v. Scott
345 So. 2d 981 (Louisiana Court of Appeal, 1977)
Master Maintenance Engineering, Inc. v. McManus
292 So. 2d 284 (Louisiana Court of Appeal, 1974)
Pamper Corporation v. Town of Marksville
208 So. 2d 715 (Louisiana Court of Appeal, 1968)
Roff v. Southern Construction Corporation
163 So. 2d 112 (Louisiana Court of Appeal, 1964)
Gross v. Breaux
144 So. 2d 763 (Louisiana Court of Appeal, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
133 So. 825, 16 La. App. 565, 1931 La. App. LEXIS 105, Counsel Stack Legal Research, https://law.counselstack.com/opinion/groner-v-cavender-lactapp-1931.