Roff v. Southern Construction Corporation

163 So. 2d 112
CourtLouisiana Court of Appeal
DecidedApril 21, 1964
Docket1081
StatusPublished
Cited by5 cases

This text of 163 So. 2d 112 (Roff v. Southern Construction Corporation) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roff v. Southern Construction Corporation, 163 So. 2d 112 (La. Ct. App. 1964).

Opinion

163 So.2d 112 (1964)

Willard E. ROFF and Johnny W. Rouse, d/b/a R. & R. Brick and Stone Construction Company, Plaintiff and Appellee,
v.
SOUTHERN CONSTRUCTION CORPORATION, Trinity Universal Insurance Company and the Housing Authority for the City of Lake Charles, Louisiana, Defendants and Appellants.

No. 1081.

Court of Appeal of Louisiana, Third Circuit.

April 21, 1964.

*113 Patin & Patin, by John A. Patin, Lake Charles, Davidson, Meaux, Onebane & Donohoe, by John Torian, Lafayette, for defendants-appellants.

L. Carroll Fogleman and George W. Liskow, Lake Charles, for plaintiff-appellee.

Before TATE, CULPEPPER and HOOD, JJ.

HOOD, Judge.

This is a suit by a subcontractor, R. & R. Brick and Stone Construction Company, a partnership composed of Willard E. Roff and Johnny W. Rouse, for amounts alleged to be due plaintiff in connection with the construction of a portion of a housing project in the City of Lake Charles. The suit was instituted against Southern Construction Corporation, the general contractor; Trinity Universal Insurance Company, the surety on the general contractor's building contract bond; and against the Housing Authority for the City of Lake Charles, the owner. Plaintiff demands judgment for the sum of $5,516.59, being the balance alleged to be due on the subcontract and for extra work performed, for $36.75 as the expense of preparing and filing the lien, and for the additional sum of $3,500.00, as damages alleged to have been sustained by plaintiff for injury to its reputation, loss of business, etc. A claim or lien in the sum of $5,516.00 was recorded by plaintiff as authorized by LSA-R.S. 38:2242. After the recordation of this claim, the general contractor bonded the claim or lien under the provisions of LSA-R.S. 9:4841 or LSA-R.S. 9:4941, with defendant Trinity as the surety on that bond.

On motion of the Housing Authority for the City of Lake Charles, a summary judgment was rendered dismissing the suit as to that defendant. No appeal has been taken from that judgment.

Each of the remaining defendants filed an answer and a reconventional demand, alleging that plaintiff had been overpaid the sum of $33.57, and reconvening for judgment against plaintiff for that amount. Defendant Trinity Universal Insurance Company also filed a third party action against Southern Construction Corporation, Charles R. Grein and George L. Grein, alleging that said third party defendants had obligated themselves to indemnify Trinity against any loss which it may sustain under bonds executed by Southern as principal and Trinity as surety, and demanding judgment in favor of Trinity and against said third party defendants for any amounts which it might be condemned to pay plaintiff.

After trial on the merits, judgment was rendered in favor of plaintiff and against Southern and Trinity, in solido, for the *114 principal sum of $3,600.54, and judgment further was rendered in favor of Trinity and against the third party defendants, Southern, Charles R. Grein and George L. Grein, for the same amount. Southern, Trinity, Charles R. Grein and George L. Grein have appealed. Plaintiff has answered the appeal praying that the amount of the award be increased.

The evidence shows that on October 6, 1960, plaintiff entered into a subcontract with the general contractor, Southern, under the terms of which plaintiff agreed to lay, clean and caulk bricks in connection with the construction of a number of houses for the owner, Housing Authority for the City of Lake Charles. The subcontract provides that as consideration for this work plaintiff is to be paid "$55.00 per thousand for the laying of bricks." Thirty-five houses were completed under the general contract. Although plaintiff laid the bricks for these houses, it failed to caulk and wash the bricks as required by the subcontract, and it was necessary for Southern to have that work done by someone else. Plaintiff and defendants disagree as to the number of bricks which were laid by the former, and as to the "back charges" to which Southern is entitled because of the expense which it incurred in caulking and washing the bricks. Plaintiff also claims that it is entitled to recover from defendants additional amounts for a number of items of "additional or extra work" performed at the instance and request of Southern, all of which claims are denied by defendants. And, finally, plaintiff contends that it is entitled to recover damages for injury to its reputation and for loss of business and inconvenience. Each of the disputed items will be considered separately.

Plaintiff contends that the total indebtedness of Southern to plaintiff under the provisions of the subcontract amounted to $18,378.27, this figure being arrived at by determining the number of bricks actually laid and then computing the amount due at $55.00 per thousand. Defendants contend that Southern's indebtedness under the subcontract was only $17,982.36. The difference is due to a dispute as to the number of bricks which were used in one group of houses. Plaintiff maintains that 9,973 bricks were used on each of 18 houses which were constructed, designated as "B type houses," while defendants contend that only 9,573 bricks were used on each of those houses. The trial judge concluded that the larger number of bricks was used, and we think the evidence supports his conclusions to that effect. We concur in the finding of the trial court, therefore, that the total indebtedness of Southern to plaintiff under the terms of the subcontract, based on the number of bricks laid, was $18,378.27.

Plaintiff originally alleged that it has been paid in cash by Southern the sum of $15,007.74 to be applied on the subcontract, but during the trial and with permission of the court, plaintiff amended its pleadings to show that only $14,822.56 had been paid. Defendants contend that Southern paid $15,088.56 to be applied on the subcontract, the dispute between the parties being based largely upon whether one payment made by Southern to plaintiff should be credited on the indebtedness due on this subcontract or on another account. The trial judge concluded, correctly we think, that only $14,822.56 has been paid to plaintiff by Southern to apply on this subcontract.

Plaintiff concedes that it failed to caulk and to wash the bricks, as it was required to do under the subcontract, and that Southern incurred expenses in having that work done. It alleges that Southern is entitled to a "back charge" or credit of $503.00 for caulking and a back charge of $600.00 for washing the bricks, making a total of $1,103.00 which plaintiff admitted in its original petition that it owed the general contractor for these items. During the trial plaintiff moved to amend its petition to allege that the credit for caulking should be reduced from $503.00 to $375.00. The trial *115 judge found, however, that Southern was entitled to a credit of $503.00 for caulking, and we agree with that finding. The court further allowed a back charge of $800.00 for washing the bricks, which plaintiff maintains is excessive and defendants argue is inadequate. Defendants contend that Southern incurred expenses in the amount of $1,598.25 for washing the bricks, and that it incurred additional expenses of $1,092.00 for repainting some of the woodwork on the houses, which they allege became necessary because of plaintiff's failure to timely wash the brickwork.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

B & G Crane Service, Inc. v. Lamastus
323 So. 2d 515 (Louisiana Court of Appeal, 1975)
McGowan-Rigsby Sup., Inc. v. CHARLES CARTER & CO. INC.
268 So. 2d 716 (Louisiana Court of Appeal, 1972)
Welch-Eckman Construction Co. v. Vancouver Plywood Co.
213 So. 2d 134 (Louisiana Court of Appeal, 1968)
Pamper Corporation v. Town of Marksville
208 So. 2d 715 (Louisiana Court of Appeal, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
163 So. 2d 112, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roff-v-southern-construction-corporation-lactapp-1964.