Peterson v. Peralta

3 La. App. 516, 1926 La. App. LEXIS 32
CourtLouisiana Court of Appeal
DecidedJanuary 18, 1926
DocketNo. 9164
StatusPublished
Cited by21 cases

This text of 3 La. App. 516 (Peterson v. Peralta) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Peterson v. Peralta, 3 La. App. 516, 1926 La. App. LEXIS 32 (La. Ct. App. 1926).

Opinion

CLAIBORNE, J.

This is a suit by a building contractor against the owner for $1,298.50 under a contract and for extras.

The plaintiff alleged that on May 22, 1922, he made a contract with the defendant for the construction of a building for the price of $5,810; that he completed the building in accordance with the contract; that there remains due to him on said contract the sum of $1,162.00; that in addition to the -contract the plaintiff did extra work under instruction of the owner and under his supervision amounting to $136.50, making a total of $1,298.50, which the defendant refuses to pay.

The defendant, in an extended answer divided into sixteen paragraphs, admits the contract and his refusal to pay the two amounts claimed, but denies all the other allegations of the petition.

Further answering, he alleges:

. 1st. That at the time he accepted the building he had not had the opportunity to examine the premises; that the plaintiff kept the keys of the building and refused to allow the defendant to inspect it until he had signed an acceptance;

2nd. That upon inspecting said build-' ing he ascertained there were numerous defects, which he enumerated in two letters addressed by him to the plaintiff;

3rd. That in accordance with the building contract J. B. Humphreys, building expert, inspected the building and reported that the building was not erected in accordance with the contract;

4th. That the building contract contained the stipulation that the fifth payment shall be due thirty days after the said building is completed and accepted, provided that in each case of said payments a certificate shall be obtained from said expert;

[517]*5175th. That the building contract contained the further stipulation that no new work of any description shall be considered as extra unless the consent' of the owner is first obtained in writing;

6th. . That owing to the failure of the plaintiff to employ proper materials and workmanship and to erect the building in accordance with the plans, the defendant has been damaged in the sum of $2,000.00;

7th. That it is stipulated in said contract that the contractor shall be liable for all costs and attorney’s fees incurred in any legal proceeding made necessary by the failure of the contractor to comply with his contract, which fees were fixed at five per cent on the amount of the bond of $2,905, or $145.25.

Defendant therefore prays for judgment rejecting plaintiff’s demand, and for judgment in his favor against the plaintiff for $2,145 and all costs of suit.

There was judgment in favor of plaintiff as prayed for and defendant has appealed.

The contract under consideration was dated May 22, 1922; the building was accepted August 17, 1922; the case was tried in the District Court in March, 1923.

The presumption is that the plaintiff has complied with his contract.

He swears to it as a witness and he is corroborated by Hoduet and Scott, foremen for plaintiff.

The burden of proof is upon the defendant to show that he has not done so.

We shall examine each of defendant’s objections in their order.

1st. That the defendant had not had the opportunity of inspecting the building because the plaintiff kept the keys and refused to deliver them to the defendant until he had accepted the building.

Concerning this complaint the plaintiff testifies:

Q. Was Mr. Peralta around the work very often when the building was going on?
A. He was there every morning and always got home at two o’clock ■ in the afternoon, except when he took a trip for one week or ten days.
Q. He operated a grocery store in that block while the building was being erected?
A. Next door.

Wm. Scott says:

.Q “How often was Mr. Peralta around the building when it was being constructed?
A. “While I was there he was there every day; he runs a grocery store right beside the building.”

H. H. Hendricks says:

Q. How often was Mr. Peralta around the house while it was going up?
A. Quite often; 1 could not say exactly, but he was there every day while I was there.

The defendant does not deny this testimony.

2nd. Numerous defects enumerated in two letters.

Both letters are dated October 9, 1922, nearly two months after the defendant had accepted the building and occupied it, August 16, 1922.

The complaints mentioned in the first - letter are:

1st. That a canvas on the porch was essential and therefore not an extra. It was not mentioned in the specifications and therefore was not considered essential by the architect who prepared them. It was ordered afterwards and is therefore an extra. 2nd. The plans call for six-foot awning over the hanging part of the roof on the sidewalk. “You had it nine [518]*518foot in point.” The defect in the awning is not pointed out. Morgan D. E. Hite, architect, expert for defendant, estimates $100 as the cost of putting it in proper shape; but he does not say why. 3rd. The plaintiff led the defendant to believe he would not charge for the bookcase, but he did not tell him so.

The bookcase cost the plaintiff $70.

4th. No damp proof slate course on foundation. One witness swears there was. 5th. No creosote on sills. Two witnesses swear that they were creosoted. 6th. Door in toilet should be lattice instead of panel. No testimony to that effect. 7th. Rear porch, water settles on same, leaks in front rooms; leaks over bath room; all windows leak from sills. Conflicting and insufficient evidence in support of any of these charges. No evidence that any repairs were made by the owner to remedy the alteged leaks. 8th. Cylinder lock on Orleans street entrance put on upside down. Scott, a carpenter, foreman, answers that charge as follows: “That is absolutely untrue.” There is no contradiction of his testimony. 9th. All sashes work hard. No evidence. 10th. Step on Orleans street entrance not up to plans. No evidence.

In the second letter of the same date the defendant writes to plaintiff:

“On September 18th you requested me to make them (the defects) in writing; so therefore I will mention them all while I am at it.” Then follows:

1st. Roof round instead of square on Orleans street. The defendant saw the change and acquiesced in it.

2nd. Staircase. The evidence is that the stairs were made wider at defendant’s request to permit the installation of a toilet beneath.

3rd. All windows leak. The plaintiff and his workmen deny this. The defect is not satisfactorily proven; nor is it shown that defendant ever repaired the windows, after his occupation of the house.

4th. Lavatory not what specifications called for under stairs. No evidence on that point.

5th. No clean out box for sewerage. The evidence is that it was attended to.

6th. Sash cord in window broke. No evidence in support.

7th. Two locks out of commission. No evidence.

8th. Gas jet leaks. No evidence.

9th.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Campbell Construction Co. v. Barnhill Bros., Inc.
245 So. 2d 776 (Louisiana Court of Appeal, 1970)
U-Finish Homes, Inc. v. Lanzl
202 So. 2d 339 (Louisiana Court of Appeal, 1967)
Roff v. Southern Construction Corporation
163 So. 2d 112 (Louisiana Court of Appeal, 1964)
Meaux v. Southern Construction Corporation
159 So. 2d 156 (Louisiana Court of Appeal, 1963)
Guillot v. Moore
131 So. 2d 533 (Louisiana Court of Appeal, 1961)
Ducore v. Gross
110 So. 2d 752 (Louisiana Court of Appeal, 1959)
Jones v. Tusa
100 So. 2d 799 (Louisiana Court of Appeal, 1958)
Spicuzza v. Ranzino
73 So. 2d 208 (Louisiana Court of Appeal, 1954)
Beeson v. Oden
58 So. 2d 221 (Louisiana Court of Appeal, 1952)
Banks v. Reed
52 So. 2d 554 (Louisiana Court of Appeal, 1951)
Brandin Slate Co. v. Bannister
30 So. 2d 877 (Louisiana Court of Appeal, 1947)
Sarver v. Barksdale
24 So. 2d 649 (Louisiana Court of Appeal, 1946)
Mangin v. Jorgens
24 So. 2d 384 (Louisiana Court of Appeal, 1946)
Lillis v. Anderson
21 So. 2d 389 (Louisiana Court of Appeal, 1945)
Merrill v. Harang
198 So. 386 (Louisiana Court of Appeal, 1940)
Cary v. Brown
196 So. 579 (Louisiana Court of Appeal, 1940)
Slack v. Standard Chevrolet Corporation
197 So. 200 (Louisiana Court of Appeal, 1940)
Reimann Const. Co. v. Upton
178 So. 528 (Louisiana Court of Appeal, 1938)
Henri Petetin, Inc. v. Board of Levee Com'rs
142 So. 859 (Louisiana Court of Appeal, 1932)
Garrett v. Verlander
120 So. 492 (Louisiana Court of Appeal, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
3 La. App. 516, 1926 La. App. LEXIS 32, Counsel Stack Legal Research, https://law.counselstack.com/opinion/peterson-v-peralta-lactapp-1926.