Hebert v. Weil

39 So. 389, 115 La. 424, 1905 La. LEXIS 673
CourtSupreme Court of Louisiana
DecidedApril 10, 1905
DocketNo. 15,142
StatusPublished
Cited by7 cases

This text of 39 So. 389 (Hebert v. Weil) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hebert v. Weil, 39 So. 389, 115 La. 424, 1905 La. LEXIS 673 (La. 1905).

Opinion

BREAUX, C. J.

Plaintiff seeks to recover the sum of $3,300, with 8 per cent, interest from judicial demand, last installment claimed as due under a building contract.

The plaintiff is a contractor and builder. The defendant is the owner, for whom plaintiff bound himself to build houses on his lots in this city. The original amount to be paid for these improvements was $18,300, in six installments. The last installment was to be paid 15 days after the completed and accepted work.

The defendant declined to pay, and alleged for reason in thus declining that plaintiff was indebted to Mm for “demurrage” for not having completed and delivered the houses within the time stipulated.

For this “demurrage” he claims a
credit of........................ $1,035 00
In the second place, he charged that plaintiff had failed to build one of the houses to the height required by
the plan....................... 500 00
And, Surther, that there were small defects in the work for which he
chaiged......................... 200 00
Also for bills and orders of plaintiff paid by defendant and admitted by
defendant at the trial............ 83 46
Attorney’s fees...................... 500 00
$2,318 46

In our decision heretofore handed down we affirmed the judgment of the district court for $3,300, with legal interest from judicial demand, subject to a credit of $1,069.

(1) This credit consists of a sum which the defendant had paid, to which he was, of course, entitled as
a credit......................... $ 971 54
(2) Bills admitted by plaintiff....... 97 46
$1,069 00

The defendant and appellee applied for a rehearing, which was granted, and in consequence the case is before us on rehearing.

We take up for decision the item 1, for “contract demurrage,” $1,035, an item not heretofore allowed, and now in part allowed.

Plaintiff, in argument, through counsel, admitted that there was a delay in completing and delivering the work beyond the time fixed in the contract.

The stipulation in the contract was that plaintiff should complete and deliver the houses on or about the 25th day of September, 1902. The houses were delivered in the November following. It becomes necessary to consider and interpret the clause of the contract whereby plaintiff bound himself to pay the sum of $15 liquidated damages for each day’s delay.

Plaintiff seeks to fasten the cause of delay on the defendant or his agent, and in this con[227]*227nection his further contention is that he owes no damages, “for [his contention is] an owner who is himself the cause of delay cannot recover.” Rev. Civ. Code, art. 2120; Haughery v. Thiberge et al., 24 La. Ann. 442; Mahoney & Co. v. St. Paul’s Church, 47 La. Ann. 1064, 17 South. 484; Ice Machine Co. v. McDonald et al., 48 La. Ann. 446, 19 South. 459.

Manifestly, if it he true, as alleged and as some of the testimony sets forth, that defendant is the one at fault for the delay of which he complains, his plea must fall to the extent at least that he (defen'dant) is at fault.

This brings us to the question: Was defendant at fault? We find an answer readily enough in the fact that there was unquestionably delay caused by the owner, although not to the extent that plaintiff alleges.

In this connection we will first take up for decision the time taken by defendant to put in wires for lighting his houses by electricity. The defendant owner reserved the privilege, if he should so desire while the building would be under construction, to install electric wires for lights, call hells, and apnuneiators; also to put in hard-wood mantels.

We understand that it devolved upon the defendant to be in readiness to begin this work of lighting; and, in the second place, it also devolved upon him not to delay or impede plaintiff in his work of constructing these houses.

Defendant was timely notified to put in the electric wiring, and he, it is true, began immediately. But the preponderance of the testimony shows that subsequently in the work of elettric wiring plaintiff was delayed. The work of putting in laths was thereby stopped. It was Stated in defense that the carpenters might have done other work on the building during the time that lathers chose to stop work.

The neglected opportunity to do other work is not clearly proven, although it may be that, if the workmen had been anxious to work, they would have found something else to do on these buildings. Just the work they could have done is not made evident by the testimony. The positive testimony is that there were delays caused by this electric lighting work. There was no counter testimony introduced to prove that the workman of plaintiff might in the meanwhile have taken up other work. There is abundance of testimony that the immediate work of plaintiff’s workmen was stopped, and could not very well be resumed ' before the lathers had completed their work. There is, in consequence, no ground for damages for the eight days’ delay caused by defendant’s workmen — days taken to put in electric lighting wires.

The 4 days’ delay laid at the door of defendant for failure to timely select the art glass to put in the building is also sustained by sufficient proof, and are deducted from the 56 days before mentioned. He (defendant) was called upon by the glazier, who was subcontractor of plaintiff, and requested to make needful selection in order that the workmen for plaintiff might proceed with the work. For one reason or another defendant dillydallied a week before making up his mind. He is not entitled to these € days of indecision or indifference in selecting his art glass.

This brings us to the consideration of one day’s delay while at work putting up a front step. That asserted delay is not sustained by the testimony. The witness Poillon, called by plaintiff, said that after he had been stopped he was not delayed in the work. He took up other work. The following is part of his testimony:

“Q. You were working on the building?
“A. Oh! yes, sir.
“Q. You were doing something else while you were waiting for these steps to be straightened out?
“A. Yes, sir; that’s all.”

As he was at work elsewhere on the building, it cannot well be charged that the general work of the building was delayed.

The plaintiff asks for a deduction of two [228]*228days in the delay, for time lost, as he says, in matter “of details of arches.” Here, again, the contractor is not sustained by his own testimony, for he testified:

■ “Q. The lather could not work on those two days and he was working at something else?
“A. Yes, sir.
“Q. How long did it take the lather to complete his lathing after his details of the arches were given?
“A. I don’t remember how long it tooh.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brasher v. City of Alexandria
41 So. 2d 819 (Supreme Court of Louisiana, 1949)
Henri Petetin, Inc. v. Board of Levee Com'rs
142 So. 859 (Louisiana Court of Appeal, 1932)
Davidson v. McGrath
5 La. App. 125 (Louisiana Court of Appeal, 1926)
Peterson v. Peralta
3 La. App. 516 (Louisiana Court of Appeal, 1926)
Industrial Homestead Ass'n v. Junker
2 Pelt. 79 (Louisiana Court of Appeal, 1919)
Penn Bridge Co. v. City of New Orleans
222 F. 737 (Fifth Circuit, 1915)
Wallis v. Inhabitants of Wenham
90 N.E. 396 (Massachusetts Supreme Judicial Court, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
39 So. 389, 115 La. 424, 1905 La. LEXIS 673, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hebert-v-weil-la-1905.