Penn Bridge Co. v. City of New Orleans

222 F. 737, 138 C.C.A. 191, 1915 U.S. App. LEXIS 1477
CourtCourt of Appeals for the Fifth Circuit
DecidedApril 26, 1915
DocketNo. 2728
StatusPublished
Cited by22 cases

This text of 222 F. 737 (Penn Bridge Co. v. City of New Orleans) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Penn Bridge Co. v. City of New Orleans, 222 F. 737, 138 C.C.A. 191, 1915 U.S. App. LEXIS 1477 (5th Cir. 1915).

Opinions

WALKER, Circuit Judge.

Omitting mention of details not necessary to be considered in reviewing the ruling of the trial court which is assigned as error, the petition alleged, and there was evidence tending to prove, the following facts:

The plaintiff in error contracted with the defendant in error the city of New Orleans to build for it a bridge of the bascule or lift type, strictly in accordance with plans and specifications furnished to the city by bridge architects employed by it alone. After the plaintiff in error had, in pursuance of the terms of the contract and under the supervision of the city engineer, carried the work to a point nearing the completion thereof, the bridge collapsed and fell while it was being lowered from a vertical to a horizontal position upon the request and order of the official of the city who had the supervision for it of the construction work. This collapse of the bridge was not due to any fault or omission of the plaintiff in error, its agents, servants, or employés, nor to any defective material used therein, nor to any nonobservance by it of any requirement'of the contract, but was due altogether to the plans and specifications, which, as above stated, the contract required the builder strictly to observe and follow, being fundamentally defective and insufficient. That contract contained the following provisions:

“14. Damage to Bridge. — The contractor shall he responsible for all damages the bridge might suffer from fire, storm, or whatsoever cause during erection or after completion until accepted by the city engineer and the commissioner of public works. * * *
“20. Maintenance. — The contractor guarantees, at his expense, to maintain to the satisfaction of the commissioner of public works, in good condition, for a period of one (1) year from the day it is accepted by the city engineer, all of the work executed under- the contract.”

During the progress of the work, before the collapse of the bridge, payments had been made thereon as provided for in the contract; but the proportion of the work contracted for which had then been done was considerably greater than- that which the amount that had [739]*739been paid thereon bore to the contract price. After the collapse of the bridge the city procured new and revised plans and specifications for its erection, and it was completed under a new contract entered into between the city and the plaintiff in error, which provided for the. payment of a specified sum for the work called for by that contract. It was expressly stipulated in that contract that the making of it was “without prejudice, waiver, or admission of liability by or 011 behalf of any party hereto, either to each other or to third persons, each denying that it is liable either to the other, or to third persons, for the collapse of said bridge, or for any damage, injury, loss, or liability flowing therefrom.” There was evidence tending to prove, that an unpaid balance was due under this second contract.

[1] At the close of the evidence the counsel for the defendants moved the court orally to instruct the jury to find a verdict for the defendants. Thereupon the presiding judge made some remarks to the jury as to his views of the rules of law applicable to the case, which he concluded with this statement:

‘'However, there is due the plaintiff an amount of §2,551.93 for matters arising after the failure of the bridge, and I will direct a verdict for that amount.”
Immediately following its recital of this statement, the bill of exceptions states:
“And thereupon, and before the said jury retired, immediately after said charge, counsel for the plaintiff then and there, in the presence of the jury, excepted and reserved this its bill of exceptions, which was then and there noted.”

The counsel for the defendants in error suggest that the exception which was reserved was insufficient to present for review any action ol’ the trial court, in that it failed to direct the attention of the court to any particular ruling sought to be made the subject of objection. There is no merit in this suggestion. Manifestly the exception reserved was directed, not to what the court said in explanation of the ruling it was about to make, but to the action of the court in so disposing of the motion submitted as to deny the plaintiff’s right to recover anything for work done under the original contract. The exception sufficiently directed the attention of the court to the ruling made on the motion for a directed verdict, and it duly presents that ruling for review. E. H. Rollins & Sons v. Board of Commissioners, 80 Fed. 692, 26 C. C. A. 91.

[2] The effect of the court’s ruling was to deny the plaintiff in the case any right to recover for work done under the original contract, though its failure to' complete the work called for by that contract was due, not to any fault on its part, but to a collapse of the bridge because the plans and specifications for it, to which the plaintiff had to conform, were fundamentally wrong, and though neither the agreed price for building the bridge nor so much of that price as was proportionate with the part of the work which had been done at the time of the collapse had been paid. This amounted to holding that any loss resulting from the collapse of a structure while in course of erection must fall on the party who undertook the work of construe[740]*740tion, though the collapse was due, not at all to his fault or omission, ■but wholly to the fatal insufficiency of plans and specifications for which he was in no way responsible and from which he was not permitted to deviate. The remarks made by the presiding judge in explanation of the ruling he was about to make show that he regarded the provision contained in article 2758 of the Civil Code of Louisiana as determinative of the question presented for decision. That provision is as follows:

“Art. 2758. Accidental Destruction Before Delivery. — When the undertaker furnishes the materials for the work, if the work be destroyed, in whatever manner it may happen, previous to its being delivered to the owner, the loss shall be sustained by the undertaker, unless the proprietor be in default for not receiving it, though duly notified to do so.”

This article provides when the loss resulting from the destruction of a work before it has been completed and delivered is to fall on the undertaker or builder. ' Another article of the same Code (article 2762) provides when the loss due to a building falling to ruin after its completion and delivery is to fall upon the builder. It is to be noted that neither of these provisions contains language which makes it plain that it was a part of the legislative purpose to subject the builder to the loss occasioned by a destruction of the work, due to a cause for which he was not responsible and of which the owner alone had control. In the framing of each of these articles use was made of provisions on the same subjects contained in the Code Napoléon (articles 1788, 1792). They were redrafted and somewhat changed in phraseology before being incorporated in the Louisiana Civil Code.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zerbe v. State
583 P.2d 845 (Alaska Supreme Court, 1978)
St. Joseph Hospital v. Corbetta Construction Co.
316 N.E.2d 51 (Appellate Court of Illinois, 1974)
J. L. Simmons Company, Inc. v. The United States
412 F.2d 1360 (Court of Claims, 1969)
Broyles v. Brown Engineering Co.
151 So. 2d 767 (Supreme Court of Alabama, 1963)
McCree & Company v. State
91 N.W.2d 713 (Supreme Court of Minnesota, 1958)
McKAY ENG. & CONSTR. CO. v. Sanitary Dist.
108 N.E.2d 39 (Appellate Court of Illinois, 1952)
McKay Engineering & Construction Co. v. Sanitary District
108 N.E.2d 39 (Appellate Court of Illinois, 1952)
Brasher v. City of Alexandria
41 So. 2d 819 (Supreme Court of Louisiana, 1949)
Sandy Hites Co. v. State Highway Commission
149 S.W.2d 828 (Supreme Court of Missouri, 1941)
Federal Land Bank of New Orleans v. Lococo
178 So. 192 (Louisiana Court of Appeal, 1938)
United States Ex Rel. Demarois v. Farrell
87 F.2d 957 (Eighth Circuit, 1937)
Montrose Contracting Co. v. County of Westchester
80 F.2d 841 (Second Circuit, 1936)
Decatur County v. Praytor, Howton & Wood Contracting Co.
137 S.E. 247 (Supreme Court of Georgia, 1927)
Louisiana Shipbuilding Co. v. Bing Dampskibsaktieselskab
104 So. 364 (Supreme Court of Louisiana, 1925)
State Ex Rel. Pollock v. Becker
233 S.W. 641 (Supreme Court of Missouri, 1921)
State Bank v. Pew
195 P. 852 (Montana Supreme Court, 1921)
Midland Bridge Co. v. Houston & B. V. Ry. Co.
268 F. 931 (Fifth Circuit, 1920)
Walsh Const. Co. v. City of Cleveland
271 F. 701 (N.D. Ohio, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
222 F. 737, 138 C.C.A. 191, 1915 U.S. App. LEXIS 1477, Counsel Stack Legal Research, https://law.counselstack.com/opinion/penn-bridge-co-v-city-of-new-orleans-ca5-1915.