Midland Bridge Co. v. Houston & B. V. Ry. Co.

268 F. 931, 1920 U.S. App. LEXIS 2386
CourtCourt of Appeals for the Fifth Circuit
DecidedNovember 24, 1920
DocketNo. 3480
StatusPublished
Cited by3 cases

This text of 268 F. 931 (Midland Bridge Co. v. Houston & B. V. Ry. Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Midland Bridge Co. v. Houston & B. V. Ry. Co., 268 F. 931, 1920 U.S. App. LEXIS 2386 (5th Cir. 1920).

Opinion

KING, Circuit Judge.

The Midland Bridge Company, a partnership consisting of Henry Freygang and Albert A. Trocon, on July 1, 1914, made a contract with the Houston & Brazos Valley Railway Company and the county of Brazoria, Tex., as owners, to build a bridge across the Brazos river between Freeport and Velasco, Tex., about four miles from the Gulf of Mexico, according to certain plans and specifications prepared by the owners through their engineers, attached to and made a part of said contract, known and hereinafter referred to as the “construction contract.”

The construction of said bridge proceeded to the completion of three piers on the Velasco side, pier 3 being a pivot pier located about one-third of the way across the river, and carrying a revolving steel span 290 feet long. So much of this steel span was completed as connected pier,2, which was at the shore line, with pier 3, and two members of the span beyond pier 3 were also completed, when, on May 7, 1915, pier 3 toppled over and fell into the river, throwing the steel span attached to it more than 50 feet downstream from the pier site.

A dispute arose between the bridge company and the owners as to whether the pier fell by reason of improper construction 1¡>y the bridge company or defective plans furnished by the owners. The dispute being unsettled, in order to provide, meanwhile, for the removal of said steel from the river, a contract was entered into, on June 21, 1915, between said bridge company, the contractors, and said railway company and said county of Brazoria, the owners, for the removal of said steel by the contractors. The contractors were to keep an accurate account of the cost of all (1) labor employed; (2) material used; and (3) the rental, or use value, of all boats, equipment, machinery, and appliances, other than what they then owned and had at or near the bridge site. Fifteen per cent, of these sums was to be added, for the personal services of the contractors and for the rental of the boats, equipment, machinery, and appliances then owned by them, and the sum of the items 1, 2, and 3, and said 15 per cent, thereon should be the contract value, as that term was used in said second contract. If the contract value did not exceed $4,000, the owners should pay one-half thereof in full discharge of their obligations under this contract; if it exceeded $4,000, the owners should pay to the contractors one-half of $4,000 and all of the contract value exceeding said sum, said payments to be made biweekly on receipt of statements from said contractors.

Said contract recited the existence of said dispute as to the responsibility for said fall, and provided that it should not estop either party in respect to said contention, and that if it should be thereafter established or agreed by the parties interested, or be judicially determined [933]*933that the contractors were right in their claim and assertion, then the portion of said contract value, which by the terms of this contract they agreed to bear, should be allowed and paid to them by the owners; on the other hand, if it should be established, agreed, or judicially determined that the contractors were liable for the loss or damage caused by the fall of said part of said bridge, the portion of the contract price that the owners had paid under this contract should be repaid to them by the contractors. The contract value for removing said steel was reported as required, and aggregated $9,226.48; but no biweekly or other payments of any part thereof were made by the owners.

On October 27, 1915, the defendant railway company was put in the hands of a receiver on, a creditors’ bill, filed in the United States District Court for ihc Southern • District of Texas. Subsequently a bill to foreclose a first mortgage on the property of said railway company was filed in said court by the Mercantile Trust Company, a-corporation of Missouri, against said railway company. The two cases were consolidated, and the receivership extended under this second bill.

On June 26, 1916, an intervening petition was filed in said consolidated cause by said Midland Bridge Company, seeking to recover- said sum of $9,226.48, the contract value under said second contract, and also the further sum of $625.32 for items of material and labor furnished on other accounts. It was claimed in said petition that said contractors were not liable or responsible for the collapse of said pier 3, and that therefore the owners were liable for said entire contract value; that all the labor and material sued for was furnished within six months of the date of the appointment of the receiver, and that under the terms of the order of appointment such items were entitled to be adjudged preferential claims, superior to the mortgage.

The answer of the railway company and the receiver set up that the interveners were liable and responsible for the loss or damage that had occurred, because a part of the bridge constructed by them did not stand up, and denied all liability under said contract for removing said steel. While admitting most of the items composing said $625.32, the defendant pleaded a counterclaim, which by stipulation was admitted to be $2,018.67, arising out of matters disconnected with the contract sued on. Interveners’ right to a preference was also denied. The intervention and defenses thereto were referred to a master, to take testimony and report his findings, judgments, and recommendations to the court.

The master heard voluminous testimony as to the original contract and the building of said collapsed pier 3 thereunder. He found that the contractors were responsible and liable for the collapse of said pier 3, and that they were not entitled to recover any part of said contract value for removing said steel. On the other items he found a balance in favor of the defendant railway company on said admitted counterclaim of $1,692.08.

On exceptions to the master’s report, which challenged the correctness of his finding that interveners were liable for the collapse of said pier 3, the District Judge, after a careful review of the evidence, held that on the findings of fact by the master, in which he concurred, the [934]*934interveners were responsible for the collapse of said pier, and overruled the exceptions to the master’s report. A decree in accordance therewith was entered.

The errors assigned, insisted on in appellant’s brief, attack the correctness of the decision that the interveners are not entitled to recover on the contract for removing said steel, because liable and responsible for the collapse of pier 3.

Three causes were assigned for the fall of the pier: First, that the original plan called for an excavation of 35 feet below mean low tide, in which the pier should be erected, and that this was stopped at 32 feet; that only 21 piles were .driven' when the excavation was carried to this depth, at intervals greater than 3feet between centers, when the construction contract made this the maximum distance, and when proper piling required many more piles; second, that the concrete at the base of said pier was defective, and had become disintegrated, causing the pier to topple; third, that the interveners (contractors) had negligently dredged an excavation near the lower side of pier 3, which occasioned the river to scour, thus weakening the foundations under the pier. •

[1,2]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Silver Bridge Disaster Litigation
381 F. Supp. 931 (S.D. West Virginia, 1974)
United States v. Ingram
99 F. Supp. 465 (E.D. Arkansas, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
268 F. 931, 1920 U.S. App. LEXIS 2386, Counsel Stack Legal Research, https://law.counselstack.com/opinion/midland-bridge-co-v-houston-b-v-ry-co-ca5-1920.