Sickels v. United States

1 Ct. Cl. 214
CourtUnited States Court of Claims
DecidedOctober 15, 1865
StatusPublished
Cited by9 cases

This text of 1 Ct. Cl. 214 (Sickels v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sickels v. United States, 1 Ct. Cl. 214 (cc 1865).

Opinion

Peck, J.,

delivered the opinion of the Court.

This claimant states in his petition that on the 27th day of January, 1852, he entered into a contract with the government for the erection of a liglit-house on Seven-Foot Knoll, at the mouth of the Patapsco river.

By the terms of the contract the plans and specifications for the structure were to he furnished by an engineer to be appointed by the Fifth Auditor of the Treasury Department, who appointed B. F. Isherwood as such engineer.

That it was stated to claimant that the bottom of the knoll consisted of hard sand, and that plans and specifications would be prepared adapted to such soil, which was indispensable to their use.

That the claimant made no soundings or examinations of the knoll, it being his duty to follow strictly the plans and specifications furnished by said Isherwood.

That upon the receipt by him of the plans and specifications he forthwith entered upon the performance of the contract, and employed Murray & Hazelhurst to furnish all the iron work, and Gault & Brother to furnish all the stone required.

That after all the iron and a greater portion of the stone had been delivered, and the work commenced, it was discovered that the bottom of the knoll was not hard sand, but consisted of soft mud, into which the piles sunk of their own weight to a depth of sixteen feet.

That these facts having been represented to the Light-house Board, soundings were made which verified their truthfulness and showed that the work could not be prosecuted pursuant to the plans furnished.

[215]*215That the Light-house Board declined to take any further action in the premises, because the plans had been furnished by other officers, under a different organization, and the new board declined to modify the original plan or to take any responsibility about it; therefore, the further prosecution of the work being impossible, all the material provided was left on the hands of the contractors, unavailable for the uses for which they were designed.

Application was made to the Secretary of the Treasury, reciting the contract, the impossibility of its performance, and asking relief, which was refused.

That Murray & Hazelhurst and Gault & Brother are the only parties interested with the claimant, who seeks to recover $10,301 33.

The contract and specifications, as also the letter of the Secretary of the Treasury, with the statement of claimant to him, asking relief, are made exhibits.

The petition is verified by James Murray, of the firm of Murray & Hazelhurst.

The specifications were made a part of the contract, and the two will be considered as one instrument.

The claimant covenanted that he would, on or before the first day •of July, 1853, find all the materials and build a light-house, in a substantial manner, on what is called Seven-Foot Knoll, &c., the said light-house to be built on what is called Potts’s pile principle, and in all other respects according to the specifications; to fit the same up, ■&C., with French lenticular apparatus, ready for public use, &c.; the light-house to remain good for three years after completion ; for which he was to be paid $11,000 when the piles should be driven and completely prepared for the first course of masonry, and, when the entire work should be completed, including the lens, to the satisfaction of Benjamin F. Isherwood, or of such other person as the Secretary of the Treasury might appoint to oversee or inspect the work, the further sum of $16,000.

The specifications appear to be very minute in detail, both as to iron and stone work.

The foundation was to consist of hollow cast-iron piles, the outer circle, measuring from centres of piles, to be 21 feet diameter; the inner circle, 15| feet diameter, &c., and to be sunk “ fifteen feet” into the sand by “ Potts’s patent pneumatic system of driving hollow piles;” the tops of the caps and rough-stone to be at the level of extreme low water.

It was insisted at the hearing of this cause that the precise spot for [216]*216the location of the light-house was indicated to the claimant on the Coast Survey maps, at the execution of the contract; that he took upon himself every hazard as to the sufficiency of the soil for a foundation, and was hound to ascertain the character of the land covered with water, and therefore could not recover. Authorities were cited to us which it was assumed sustained this position. We .do not so understand the obligation entered into by the claimant.

It was conceded on the argument that Seven-Foot Knoll is about five eighths of a mile long by two-fifths of a mile wide. This was a large surface to examine, even if that duty had devolved upon the claimant; but the record shows that Mr. PleasontoD, then in charge of light-houses, concluded “that it would be safer to send an officer of the Coast Survey to fix upon the site than to rely upon that marked on the chart,” and directed that an officer should be sent to fix the site. (See his letter of 7th September, 1852.) The specifications, apart from all other proofs, control this question, the first of which is as follows : “ The site of the light-house to be in about ten feet water, to be selected by the engineer appointed by the Fifth Auditor,” &e. Under these circumstances Sickels was not called ripon to examine for himself as to the character or suitableness of the soil for a foundation, even had he known the exact site in time to do so ; but the proof shows that the officer who was to select the site, and who drove the stake as a guide to the contractor, did not do so until the time when the iron piles were taken to it to be sunk for permanent location. It must be remembered that Mr. Sickels did not suggest the plan ; that was chosen for him; his judgment and skill were not called into requisition ; he did not propose to guarantee in any way the adequacy of the foundation, or its adaptation to the desired use. His agreement was to furnish iron piles of the required dimensions and of sufficient length to reach the top of the water, and to penetrate fifteen feet into the earth under it, and to sink them where directed so to do by this particular Potts process. This was the extent of his obligation as to foundation; the rest was assumed by the government.

Independent of all deductions from the specifications, the government engineer states that the appropriation was insufficient to erect a light-house upon any other principle, and that this plan was adopted of necessity, the officer in charge of this branch of governmental duty believing he knew exactly the character of the soil upon which the structure was to rest.

When the piles were placed in position to be sunk by the process named, “ they were forced with difficulty through the first three feet [217]*217of the soil, the ground for that distance being perfectly firm, when its character suddenly changed into a bed of quicksand of so little resistance that the heavy iron pile sunk by its own weight, and entirely disappeared from sight.” This is the language of the engineer in charge, and seems to be conclusive as to the want of adaptation of the plan to the purposes designed.

This witness also testifies that it was a “physical impossibility” to complete the structure upon the plan proposed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fru-Con Construction Corp. v. United States
42 Cont. Cas. Fed. 77,399 (Federal Claims, 1998)
J. L. Simmons Company, Inc. v. The United States
412 F.2d 1360 (Court of Claims, 1969)
Spearin v. United States
51 Ct. Cl. 155 (Court of Claims, 1916)
Penn Bridge Co. v. City of New Orleans
222 F. 737 (Fifth Circuit, 1915)
Kinzer Construction Co. v. State
125 N.Y.S. 46 (New York State Court of Claims, 1910)
United States v. Behan
110 U.S. 338 (Supreme Court, 1884)
Behan v. United States
18 Ct. Cl. 687 (Court of Claims, 1883)

Cite This Page — Counsel Stack

Bluebook (online)
1 Ct. Cl. 214, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sickels-v-united-states-cc-1865.