Blymer Ice Machine Co. v. McDonald

19 So. 459, 48 La. Ann. 439, 1895 La. LEXIS 568
CourtSupreme Court of Louisiana
DecidedJune 17, 1895
DocketNo. 11,768
StatusPublished
Cited by9 cases

This text of 19 So. 459 (Blymer Ice Machine Co. v. McDonald) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blymer Ice Machine Co. v. McDonald, 19 So. 459, 48 La. Ann. 439, 1895 La. LEXIS 568 (La. 1895).

Opinion

The opinion of the court was delivered by

Breaux, J.

The Blymyer Ice Machine Company seeks to recover from the defendants a balance under a contract, and legal interest, for erecting an ice machine.

The contract between the plaintiffs and the defendants was prepared with some care, and contains a number of stipulations.

The plaintiffs agreed to make for the defendants an ice machine of the latest improved pattern and of a capacity of one hundred thousand pounds of the best quality of artificial ice per twenty-four hours, with cooling water at ninety degrees Fahrenheit, during the months of July and August, and to erect it in the city of New Orleans prior to the 1st day of June, 1891, with full charge of ammonia and salt for brine in the freezing tank, all' complete for the manufacture of ice. The Blymyer Ice Machine Company guaranteed that the plant would make five tons of good, clear merchantable ice to one ton of coal.

The plaintiffs agreed to make the retort of heavy steel and the coils therein with the joints on the outside; to make the tank of plate iron, with the freezing and brine tank insulated, encased in wood and furnished with covers. The plaintiffs also promised to make the ammonia pipes subject to pressure of extra thickness, of the best iron and steel, and workmanship, and of special pattern for saving ammonia. The test for these pipes was fixed at three hundred pounds per square inch.

The plaintiffs also contracted to furnish a complete distilling apparatus, filter, cranes, lifting apparatus and automatic can fillers.

The plaintiffs, in addition, was to prepare and deliver plans and furnish dimensions for buildings and foundations and platforms for machinery.

The plaintiffs engaged during two years to make needful repairs of [441]*441the machinery caused by defective material or defective workmanship.

The defendants hound themselves to have the buildings ready for the machine and not cause delay.

They also agreed to furnish a competent person to aid in the work of erecting the machinery under the direction of plaintiffs’ engineer, in order that he might acquire needful experience to operate the machine for the defendants.

The defendants bound themselves to furnish the boilers.

They were also to have in readiness, when needed, a sufficient supply of water “convenient for the said party of the first part to make connections for distributing to the machine, tank and boilers.

“ The parties of the first part agrees to and does sell to the parties of the second part machinery and apparatus complete for making ice in New Orleans, erected on the grounds of the parties of the second part, and the parties of the second part are to pay for the same the sum of forty-one thousand five hundred dollars, and to build the necessary buildings according to the plans and specifications to be furnished by the parties of the first part, and furnish the boiler set ready for first party to make steam connections.”

Subsequently, in a separate agreement modifying the first, in consideration of an allowance of three thousand dollars in the price, the defendants consented to postpone the date of delivery from June 1 to July 1. On the 30th of January, 1892, the defendant, Judah Hart, who held a controlling interest, sold the entire plant; the property sold consisted of the ice machine, lands, and the other improvements thereon for full consideration.

The defendants denied in their answer that the machine came to the capacity required. They specially allege that plaintiff began to work on the ice machine late in June, 1891, too late to timely comply with their contract.

They claim judgment for damages growing out of the delay in not having delivered the ice plant at the time fixed, on the 1st of July, and they urge that, by plaintiff’s fault and negligence, the ice machine was not constructed and ready to make ice prior to the 4th day of September, 1892, and that they thereby were made to lose the opportunity of selling fifty tons of ice per day during the months of July and August, 1892, which they would have sold at a clear profit of four dollars per ton.

[442]*442The issues on. the reconventional demand are abbreviated by the admission that the amount due the plaintiffs on the ice machine was the balance twenty-six-thousand six hundred and seven dollars and seventy-one cents, and that judgment should be rendered for this sum, unless the defences interposed should be held to be good. The following items are sustained by the lower court’s decision:

Item of eight hundred and forty-six dollars and twenty-six cents claimed in account E.

The learned Judge of the District Court allowed only fourteen dollars and eight cents of this account. The remainder was rejected by him for the reason that it bore date subsequent to January 30, 1892, when the defendant sold the ice machine and plant to the Municipal Ice Company.

He held that after that date, defendants having ceased to own the machine, or to control it, they were without capacity to claim for expenditures made on the plant.

He also, assi.ning substantially the same reason, rejected the claim of five thousand dollars made by the. defendants to pay the cost of a new absorber to put in the place of the one which the defendants claimed was deficient in capacity and too small to make fifty tons of ice with water at ninety degrees. By supplemental answer the defendants sued for a reduction of ten thousand dollars on the price of the machine because of the alleged failure to make five tons of ice with one ton of coal.

From a judgment for the plaintiff for twenty-six thousand five hundred and ten dollars and fifty-three cents, with interest from judicial demand, the defendants appeal.

PACTS REGARDING THE ALLEGED DELAY IN DELIVERING THE MACHINE.

In our summary of the evidence, we enter in the first place on the subject of defendants’ claim for plaintiffs’ delay alleged in erecting the machinery — sixty-six days at one hundred and twelve dollars per day. From the terms of the contract we infer, as there was no stipulation made regarding the date the plans of the building for the ice factory were to be delivered by the plaintiffs to the defendants, that they were to be furnished within a reasonable time. There were delays on each side — the plaintiffs in delivering the plans, and defendants in having alterations made in the plans,.and afterward by [443]*443delays in undertaking the erection of the building under the plans. With reference to the delivery of the machine after the building had been erected, the facts are, that the defendants were slow in placing the boilers in the proper place. They were net put up, nor sufficient steam supplied on the 1st of July, the date agreed upon between the contracting parties.

The plaintiffs, also, were not ready at that date to operate the machine.

It is a fact, also, on the other hand, that the defendants did not employ a person to aid in the work of erecting the machine as required by the terms of the contract.

FACTS OF ABSORBING APPARATUS.

The absorber was too small; the machine was designed for a different climate and temperature are defendants’ complaints. We have deemed it necessary, to a conclusion, to examine each of the constituent elements of the ice machine and give some study to the modus operandi.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gustin v. Shows
377 So. 2d 1325 (Louisiana Court of Appeal, 1979)
Board of Levee Com'rs for Orleans Levee Dist. v. Dalton
139 So. 487 (Louisiana Court of Appeal, 1932)
Labit v. Standard Motors Finance Co.
6 La. App. 425 (Louisiana Court of Appeal, 1927)
United Iron Works v. Twin City Ice & Creamery Co.
296 S.W. 109 (Supreme Court of Missouri, 1927)
Kelly & Son v. Yellow Cab Co.
5 La. App. 69 (Louisiana Court of Appeal, 1926)
Bennett v. Weinberger
107 So. 780 (Supreme Court of Louisiana, 1926)
Pere v. Dalgarn
3 La. App. 775 (Louisiana Court of Appeal, 1926)
Feeney & Bremer Co. v. Stone
171 P. 569 (Oregon Supreme Court, 1918)
Hebert v. Weil
39 So. 389 (Supreme Court of Louisiana, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
19 So. 459, 48 La. Ann. 439, 1895 La. LEXIS 568, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blymer-ice-machine-co-v-mcdonald-la-1895.