Industrial Homestead Ass'n v. Junker

2 Pelt. 79, 1919 La. App. LEXIS 5
CourtLouisiana Court of Appeal
DecidedFebruary 13, 1919
DocketNo. 7402
StatusPublished

This text of 2 Pelt. 79 (Industrial Homestead Ass'n v. Junker) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Industrial Homestead Ass'n v. Junker, 2 Pelt. 79, 1919 La. App. LEXIS 5 (La. Ct. App. 1919).

Opinion

CHARLES F. CLAIBORNE, JUDGE.

In this case an owner sues a contractor for the return of money^paid to-him- on a building contract.

The petition alleges that Charles A. Junker transferred to the plaintiff a certain lot of ground in order to make the plaintiff the record owner of it so as-to let out a building contract and erect for account of said Junker a building which was thereafter to be retransferred to him in accordance with the Homestead plan; that in pursuance of said agreement, the plaintiff, on July 9th, 1915, made-a contract with Frederick Junker, builder, for the erection of a two story frame residence for which the said plaintiff was to pay $2300 represented by five installments or payments of $460 each; that the Southwestern Insurance Company signed as surety for Frederick Junker; that after the plaintiff had made two payments of $460 each^Frederick Junker, the building was practically destroyed and Frederick Junker abandoned the work and announced his intention not to reconstruct said building; wherefore the plaintiff prayed for judgnent against Charles A. Junker, Frederick Junker, and the Insurance Company for $92,0.

Charles Junker filed an exception of no cause of action which was maintained, and the suit was dismissed as to him.

Frederick ¥. Junker and the Surety Company admitted the building contract; they averred that work under the contract had been commenced, and a first payment had. been earned, when a storm of unprecedented violence visited the City and entirely demolished the work which had been done; that the work was recommenced and had been executed up to a point at which the second payment was due, when, for the second time, the City was visited [81]*81by a terrific atora of greater violence than the firat, and again the work which had been done waa entirely demolíahed; that the City Architect then notified Frederick Junker that the plana of the building were defective and that he would not permit the erection of the building in accordance therewith, that the double deatruction of the work waa due to the violence of the two atoraa and to the defect's in the plans and in no way t'o the fault of the contractor; that the plans were furnished by the plaintiff Association and were approved by its expert appointed by the Association for that purpose; that Junker was not an architect and that it waa no part of Kis duty to pass upon the plans of the building; that more than $920 were expended by Junker on the work which was actually done on the building, and that liens in excess of that amount'have been filed against the building.

There was judgment for the plaintiff as prayed for against Fred Junker and the Insurance Company and they have appealed.

As we understand the plaintiff'a case he pitches his cause of action upon two propositions: first,that the building was blown down before Junker completed and delivered it to the plaintiff, and that the destruction of it was his loss; and second, that he abandoned the work.

The abandonment of the work by the contractor Junker did not obligate him to return the money which he had received from the owner in payment of the first and second installments which he had earned; it only gave the owner the right to complete the building at the expense of the’ contractor and of his surety.

Article C. C., 2769 (2740) says: ,

"If an undertaker fails to do the work he has contracted to do, or if he does not execute it in the manner and at the time he has agreed to do it, he shall be liable in damages for the losses that may ensue from his nonoompliance with his contract". 12Ct. App., 126; 3 La., 1; 4 La., 465; 7 La., 134; [82]*824 A., 97; 6 A., 202; 9 A., 31; 15 A., 220; 124; 36 A., 555 (558); 50 A., 351; 49 A., 863; 124 La., 306; 15 Am. & Eng. Enc. Law p 1093 10; 99 Pac., 723; 9 C. J. 739 78 - id 818 155 - id 820 157.

The last clause of the building contract itself contains provisions and gives the owner rights exactly in accordance with the authorities hereinabove a_uoted.

But in the present case there were two reasons which justified the contractor in refusing to rebuild. The first one va.3 that the 'destruction of the building out an end to the contract 'both da to him and as to the owner, according to the English and to the common law. 113 Pac., 121; 46 N. E., 449 (451); 2 Law Rep. Common Pleas 651 (659); 8 Elliott on Contracts 3702; 1 Am. An. Cas. 466 - id 1913 A. p 458, 459.

The other reason^that the plans had been condemned by the City Engineer who had refused to give a permit for the construction of a house ir. accordance therewith.

In Shepard vs Hero, No. 6830 of this Court we said:

"Where a contractor is required by the owner to erect a part of a building contrary to correct orir.-ciples of architecture and in violation of the building laws of the City, he is justified in refusing and quitting, and is entitled to the conmission he would ..have earned had he been allowed to do the work in a 'proper..manner." 9 C. J., 804 143 - id 821 158 - id 805 - id 822 159; 41 A., 375.

It- Seems that the contractor Junker did get a permit t6 erect'thertuilding, when he first started. ' He had got as far as' hisjthird payment and was p.bout to lath and olaster, . when,' oh .'August‘-7th, the building wes blown down; he then demolished it'¡- and.proceeded to reconstruct it as before; he had finished the-plastering and had' the locks .on the doors and was ' within.ten flayá t>f finishing-the building,, when On Seotember • 2Sth it- whs again blown down by'a.stona; he took it apart again; .but, this’tiihé the City authorities refused "the issuance of the ,'necbBaairyV búilding .permit for the erection" Of said structure in ,.'a,tí’ííoi4áthóí:v&th;,thé.5lahs and specifications submitted" "be[83]*83cause", in the opinion of the City Engineer, “the building was not properly braced and anchored to the footings."

The other ground of action of the plaintiff is that the building was blown down before Junker completed arid delivered it, and that the destruction of it was hiB loss.

The law upon the subject is contained in the following articles of the Civil Code.

Art. 2758 (2729):

"When the undertaker furnsihe^s the materials for the work, if the work be destroyed, in whatever manner it may happen, previous to its being delivered to the owner, the lossshall be sustained by the undertaker, unless th,e proprietor be in default for not receiving it, though duly notified to.do so?, C.N.1788.

Wg interpret this article as apolyine exclusively to' building contracts^which provide for payment after th^ completion and delivery of the entire work to the owner. >’B.ut .when the building contract provides for the acceptance, delivery, and payment of the work in installments as the work progresses, as in this case, the law is different and is governed by- the ■ . following

Art. 2761 (2732)r

^If the work is composed of detached pieces, or made at the rate of so much a'measure, the patfts may be delivered separately:, and that delivery shall' be presumed to have .taken place, if the proprietor has paid to the undertaker the price due for-the ’ parts of the work which have already been completed". C. N. 1791.

In this case two parts had been completed and delivered and paid for, for it' is the payment of those two parts’ which the plaintiff seeks to réqbver.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hettinger v. Thiele
113 P. 121 (California Court of Appeal, 1910)
Fair Haven & Westville Railroad v. City of New Haven
49 A. 863 (Supreme Court of Connecticut, 1901)
Watson v. Grand Trunk Railway Co.
36 A. 555 (Supreme Court of New Hampshire, 1894)
MacKnight Flintic Stone Co. v. Mayor of New York
54 N.E. 661 (New York Court of Appeals, 1899)
Hinckley v. Breen
9 A. 31 (Supreme Court of Connecticut, 1887)
Culbertson v. Ashland Cement & Construction Co.
139 S.W. 792 (Court of Appeals of Kentucky, 1911)
Loreau v. Declouet
3 La. 1 (Supreme Court of Louisiana, 1831)
Etie v. Sparks
4 La. 463 (Supreme Court of Louisiana, 1832)
Randall v. Parkison
7 La. 134 (Supreme Court of Louisiana, 1844)
Hebert v. Weil
39 So. 389 (Supreme Court of Louisiana, 1905)
State v. Duryee
47 A. 1064 (Supreme Court of New Jersey, 1900)
Bliss v. F. & M. Schaeffer Brewing Co.
50 A. 351 (Supreme Court of New Jersey, 1901)

Cite This Page — Counsel Stack

Bluebook (online)
2 Pelt. 79, 1919 La. App. LEXIS 5, Counsel Stack Legal Research, https://law.counselstack.com/opinion/industrial-homestead-assn-v-junker-lactapp-1919.