Beeson v. Oden

58 So. 2d 221, 1952 La. App. LEXIS 538
CourtLouisiana Court of Appeal
DecidedMarch 28, 1952
DocketNo. 7795
StatusPublished
Cited by1 cases

This text of 58 So. 2d 221 (Beeson v. Oden) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beeson v. Oden, 58 So. 2d 221, 1952 La. App. LEXIS 538 (La. Ct. App. 1952).

Opinion

GLADNEY, Judge.

This case presents an appeal by the defendant, Caswell W. Oden, from a judgment rendered against him in favor of the plaintiffs, Johnnie Beeson and Gloria Jean Beeson, “in the full sum of $600.00, less a credit of $400.00 represented by a note filed in evidence, Defendant to pay all costs of this suit * * * No answer to the appeal has been filed.

Plaintiffs’ petition was filed March 30, 1950, for injunctive relief to restrain the negotiation of a promissory note given in payment of certain contractual work. It alleges the note was obtained through fraud and that it should be decreed null and void. In addition thereto damages for $1,000 and $350 attorney’s fees were claimed for breach of contract. As grounds for the issuance of a restraining order and preliminary writ of injunction, petitioners averred they would “suffer immediate irreparable injury as it is feared and believed that defendant will disburse funds so received and a money judgment against him could not be collected.” The Court granted a restraining order and signed a rule nisi requiring defendant to show cause why a preliminary injunction should not issue. Defendant, by plea of no cause and no right of action excepted to the petition as not alleging grounds for injunctive relief, and then answered the rule. The exception was overruled and the writ of injunction issued as prayed for, whereupon defendant filed a motion to dissolve the writ averring the petition disclosed plaintiffs’ demands were compensable by a money judgment and therefore subject to an adequate remedy at law. The motion was denied whereupon defendant filed his answer in the form of a general denial and by way of reconvention claimed the full amount of the promissory note with interest and attorney’s fees and certain damages resulting from the illegal issuance of the writ. Following trial the aforementioned judgement was rendered.

The bone of contention between the parties relates to certain contractual work done by defendant for plaintiffs upon a garage apartment pursuant to a written contract dated February 15, 1950. As the job progressed the parties on March 6, listed in writing certain extra work to be done by the defendant for $400. It was for this amount the note was executed and delivered to defendant on March 20, 1950. Plaintiffs occupied the premises on March 14, 1950, at which time presumably the job was substantially complete and accepted by the owners. During the trial plaintiffs abandoned the complaint against the manner of performance of the contract for extra work. Our, consideration will, therefore, be limited to the disputed items mentioned in the original and amended petitions and embraced in the initial contract, which provides:

“Date February 15, 1950
“To Johnnie Beeson 638 Topeka, Shreveport, La.
“We propose to perform the following work on garage apartment at rear of 3942 Mangum, furnishing all materials and labor, and using any salvage material the use of which will not detract from quality of job:
“Remove five feet from front of present structure. Build unto side of structure left two rooms, approximately 10' x 10', with one-way roof, and asphalt tile floors over solid concrete slab. Complete balance of apartment by sheetrocking ceiling and tex-[223]*223tone walls and ceiling. Add approximately five feet to present bath, install new shower stall and lavatory, also new hot water heater. Build large closets in hath and suitable closets, if wanted, in dining area. Install asphalt tile floors throughout. Wire entire apartment, including fixtures, fixture allowance not to exceed thirty dollars. Paint all new work outside two coats, and all new work inside two coats, Build storage house, 14' x 10', unsealed, no floor, one door, no painting.
“For the sum of $1,750.00 payable $600.00 with contract, $600.00 when roof of two new rooms is felted, and $550.00 when job is completed.”

The unsatisfactory work complained of is listed in the original petition as:

“1. No provisions made to keep water out of front door.
“2. No flashing over windows.
“3. Hood over door not properly flashed.
“4. Concrete slab poured on six (6) inches of fill dirt with no provisions made to retain fill dirt around edges of slab.
“5. The roof is not of sufficient strength to support a large snow or firemen that might be called to combat a fire.
“6. The roofing does not project to the outer edges of wood cornish (sic) or decking which will cause immediate rot.
“7. Sheet rock not properly nailed or finished.
“8. Shower not water proof.
“9. Sink not properly installed.
“10. No provisions made to enter attic.
“11. Portions of outside walls with only one coat of paint.
“12. Too many siding joints on one (1) studding.
“13. Holes in outer walls large enough for wood rats to enter the house.”

By amended petition it was alleged that certain violations of the Shreveport Building Code occurred in the construction work and were reported by the Shreveport Building Inspector. During trial it was admitted that no prosecution was attempted by the authorities following such report and we must assume they were without merit. Testimony relative to the items so involved was heard upon the trial and we are not persuaded the work as done will leave the structure in an unsafe condition. Our impression is that the Shreveport ordinance is for the purpose of requiring only that construction work must be such that a certain standard of safety will be imposed and that there is no intent that the law should otherwise interfere with the right of individuals to contract as cheaply and as conveniently as possible.

Upon the witness stand defendant frankly admitted that the items listed as 1, 6,9, 11 and 13 were minor defects which could be repaired at a cost of $25 or $30, but that he had been prevented from doing so by the unexpected and premature filing of the suit. He contended that the contract did not provide for flashing as complained of in items 2 and 3.. In this we agree. Plaintiffs unquestionably desired the work to be done with as little expense to them as possible, and apparently they obtained a close price, one it appears in which the contractor had no profit, and perhaps a loss. .

The evidence as to the remaining disputed items, viz., 4, 5, 7, 8, 10 and 12, is persuasive that there was substantial compliance with the terms of the contract, especially so when we consider that manifestly the owners did not expect a high class job. Item 4, involving the concrete work, furnishes the most serious objection to the work.

The defendant sublet the concrete work. Appellees contend that the concrete was placed on top of a 6" fill of new dirt and that the pilings spaced at intervals to anchor the concrete to firm ground did not reach to the firm clay. It was acknowledged by defendant that one of the pilings [224]*224went only to a depth of 11" and not the 30" as testified to by his subcontractor, and other witnesses.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Airco Refrigeration Service, Inc. v. Fink
134 So. 2d 880 (Supreme Court of Louisiana, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
58 So. 2d 221, 1952 La. App. LEXIS 538, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beeson-v-oden-lactapp-1952.