Wickliffe v. Cooper & Sperier

120 So. 52, 167 La. 689, 1928 La. LEXIS 2098
CourtSupreme Court of Louisiana
DecidedNovember 26, 1928
DocketNo. 29059.
StatusPublished
Cited by8 cases

This text of 120 So. 52 (Wickliffe v. Cooper & Sperier) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wickliffe v. Cooper & Sperier, 120 So. 52, 167 La. 689, 1928 La. LEXIS 2098 (La. 1928).

Opinions

OVERTON, J.

This suit grows out of a contract to repair and remodel an old residence, located in the city of New Orleans. The objects of plaintiff, in entering into the contract, were to convert the building into an apartment house, containing four apartments ; to provide for the heating of the apartments ; and to put the building in repair. It-is plaintiff’s contention that the contractors, Cooper & Sperier, who are among the defendants herein, breached their contract by not only refusing to install, in accordance with its terms, the kind of heating system she desired, but also by doing inferior work and by failing, though put in default, to complete the contract in accordance with the plans and [691]*691specifications. It is also her contention that the Security Building & Loan Association— another of the defendants in the case — which had agreed, under the terms of a mortgage granted by plaintiff on the premises to be improved, to furnish for her benefit money with which to carry out the contract, and to disburse the money in accordance with the terms thereof, breached its agreement by making the first and only payment made to Cooper & Sperier improperly, in that the association made the payment for inferior work done, and in that it refused to permit the use of the amount it had agreed to furnish, to enable her, through other contractors, to complete the contract and to minimize the loss that was being occasioned by the breach of the contract by Cooper & Sperier. It is also her contention that the surety of the contractors, the United States Fidelity & Guaranty Company, one of the defendants herein, breached its contract, by failing to complete the work, undertaken -by its principals, and to remedy the defects in the work done by them.

The purposes of the suit are to have it decreed that Cooper & Sperier, the United States Fidelity & Guaranty Company, and the Security Building & Loan Association have violated their contracts; to have it decreed that the first and only payment made to Cooper & Sperier by the Security Building & Loan Association, amounting to $2,940, was improperly made; to recover of that association $14,700, the amount that the association agreed to furnish and disburse, to the end that the amount may be used in the completion of the building contract; to recover of all three defendants, in solido, $7,300, as penalties, already accrued, for the failure to complete the work within the time specified in the contract, and for such future penalties,' at the rate of $10 a day, as may accrue, arising from the same cause; to recover further judgment against defendants in such sum as the evidence may justify for the deterioration of the building, brought about by defendants’ leaving it in an unfinished and unprotected condition, following their alleged default; to recover of Cooper & Sperier and their surety the cost beyond the amount of the formers’ bid, which, due to the rise in material and labor, may be necessary to complete the building in accordance with the contract; and to require the surety on Cooper & Sperier’s bond to cause to be canceled the liens recorded and which may be recorded against the building, growing out of the building contract.

The defendants answered the suit. They deny, among other things, that they, breached their contracts, or were in default, or that the work done by Cooper & Sperier was not done in accordance with the contract. They aver that plaintiff, in effect, terminated the contract with Cooper & Sperier to remodel and repair the building by refusing to comply with her part of the contract to furnish the plumbing and heating fixtures, contemplated by that instrument, at a time when the work of remodeling and repairing could not progress properly until these fixtures were sui> plied, and by insisting, after the contract was signed and the work commenced and partly completed, that the contractors install a system of heating, not contemplated by the contract, which could not be successfully installed without making material changes in the construction of the building, and by refusing to permit Cooper & Sperier to continue with their work. In addition to the foregoing, which is substantially alleged by all defendants, Cooper & Sperier aver that they did certain extra work for plaintiff, consisting of the erection of a garage on the premises, for which they claim they are entitled to- $489.05, and sue for that sum in reconvention. They also aver that the work actually done by them on the building they contracted to remodel and repair amounts to $6,920.02, [693]*693including extras thereon, and they also sue plaintiff for this amount in reconvention.

On the trial of the case it appeared that plaintiff purchased property on Peters avenue, in the city of New Orleans, on which stood a large residence, built over 50 years ago. The building on this property, which was in fact a duplex apartment house, was moved some years ago from the center of the plot of ground on which it stood to a point near the property line. Plaintiff desired to remodel this building, so as to convert it into an apartment house, containing four apartments, and to make extensive repairs on it. She applied to one of the defendants herein, the Security Building & Loan Association, for the money with which to make the desired improvements. The association virtually agreed to lend her the money she desired, on her having plans and specifications made, provided the plans and specifications were approved by J. J. Baehr, the building expert of the association, whose duty it was to examine the plans and specifications to better enable the association to determine whether to make the loan. Plaintiff then employed the Home Construction Company, of which J. W. Billingsley was manager, to prepare the plans and specifications. In due course, and after various consultations between Billingsley and the employees of his company and plaintiff, the plans and specifications were prepared and submitted to plaintiff. Plaintiff, it seems, then asked for an estimate of the cost of doing the work. Cooper & Sperier, defendants herein, submitted an estimate of $26,000. Plaintiff informed them that she did not care to expend that much money in repairing and remodeling the building, and that, under the circumstances, she would have new plans and specifications prepared. Cooper, of the firm of Cooper & Sperier, offered to make suggestions to plaintiff as to how the plans and specifications could be amended so as to reduce the costs. Plaintiff accepted the offer and Cooper assisted in making the amendments. Finally, the work of making the ámendments was completed. The plans and specifications were then submitted to Baehr, the building expert of the Security Building & Loan Association, and upon their receiving his approval the loan was perfected in the usual manner pursued by building and loan associations.

Plaintiff then asked for bids under the plans and specifications, as amended, and Cooper & Sperier submitted a bid of $14,TOO, which was accepted. A contract was signed providing, among other things, that the work should be done in strict accordance with the plans and specifications, which were made part of the contract. The contract also contained a provision to the effect that the money loaned by the Security Building & Loan Association to plaintiff should be paid to Cooper & Sperier by the association in installments as the work progressed, and a clause reading as follows:

“All of said work is to be done to the satisfaction and under the direction of John J.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

C. H. Leavell & Co. v. Board of Commissioners
309 F. Supp. 626 (E.D. Louisiana, 1970)
Delta Paving Company v. Woolridge
209 So. 2d 581 (Louisiana Court of Appeal, 1968)
Jerrie Ice Company v. Col-Flake Corporation
174 F. Supp. 21 (E.D. Louisiana, 1959)
Beeson v. Oden
58 So. 2d 221 (Louisiana Court of Appeal, 1952)
Gowan v. Stone & Webster Engineering Corp.
48 So. 2d 95 (Supreme Court of Louisiana, 1950)
Vazquez v. Gairens
26 So. 2d 319 (Louisiana Court of Appeal, 1946)
P. Olivier & Sons, Inc. v. Board of Com'rs
160 So. 419 (Supreme Court of Louisiana, 1935)
Pittman v. Bourgeois
152 So. 765 (Louisiana Court of Appeal, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
120 So. 52, 167 La. 689, 1928 La. LEXIS 2098, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wickliffe-v-cooper-sperier-la-1928.