Jerrie Ice Company v. Col-Flake Corporation

174 F. Supp. 21, 1959 U.S. Dist. LEXIS 3018
CourtDistrict Court, E.D. Louisiana
DecidedMay 27, 1959
Docket7300
StatusPublished
Cited by9 cases

This text of 174 F. Supp. 21 (Jerrie Ice Company v. Col-Flake Corporation) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jerrie Ice Company v. Col-Flake Corporation, 174 F. Supp. 21, 1959 U.S. Dist. LEXIS 3018 (E.D. La. 1959).

Opinion

WRIGHT, District Judge.

The plaintiffs, members of a partnership doing business as The Jerrie Ice Company, brought this action against the Col-Flake Corporation and its surety, Travelers Indemnity Company, for damages for breach of a construction contract to build a flake ice plant. Plaintiffs claim that the ice plant, as completed, is deficient in several respects, particularly the capacity of the ice storage bin. Col-Flake, asserting that the iee plant has been constructed in accordance with the contract, has counterclaimed for $75,000, the balance due on the contract price.

On May 4, 1956 a written contract was executed between plaintiffs and Col-Flake, with Travelers Indemnity as surety, whereby Col-Flake bound itself to construct an ice plant on plaintiffs’ land on the banks of Bayou Lafourche near Galiano, Louisiana. The contract, as well as the plans and specifications made part thereof, were prepared by Col-Flake. With reference to the ice storage bin, the contract provided “one 200 ton *23 ice storage capacity, bin; built in accordance with accepted plans attached.” The plans, made part of the contract, showed a storage bin, marked “200 ton ice storage,” with dimensions 65 feet in length by 18 feet in width by 10 feet in height and specifying 8 feet maximum height of ice.

The contract also provided for an ice leveling device installed under the ceiling of the storage bin to spread the ice forward in the storage bin away from the four ice makers installed on the second floor of the bin toward the rear. In addition, the contract provided for a conveyor system for unloading ice from the storage bin at a minimum rate of one ton per minute. The four ice machines, according to the contract, were to produce 60 tons of ice per day. The contract also provided that on receiving the contractor’s notice of completion of the work, the owner would have ten days to notify contractor of any defects, otherwise the contract would be deemed accepted. The contract further provided, however, that the acceptance by the owner “in no way lessening the responsibility of said contractor.” 1

In January 1957 the plant was ready for test operation. Various mechanical deficiencies were disclosed and corrected. The leveling device had to be replaced and the conveyor system changed to some extent. As replaced, the leveling device extended three feet below the ceiling of the storage bin, leaving a maximum height in the bin of only seven feet for ice storage instead of eight feet as specified in the plan.

Despite further mechanical difficulties reasonably to be anticipated, on March 1, 1957, after giving away ice manufactured during the test period, plaintiffs began the sale of ice from the plant, primarily to shrimp boats. On March 4, 1957, Col-Flake by letter notified plaintiffs of completion of the contract. Plaintiffs denied receiving the letter notice, and consequently made no complaints of defects in construction within the ten days specified in the contract. The plant, however, did not perform to their satisfaction. The mechanical breakdowns continued. Rust from the chain on the leveling system polluted the ice as it lay in the storage bin. The chains on the conveyor system scraped Thermocon 2 from the floor, further polluting the ice. The cross conveyor which brought the ice from the conveyors on each side of the storage bin to a hopper device outside, from which it was loaded into shrimp boats, continually broke down. According to the plaintiffs, even when the cross conveyor worked, it did not remove one ton of ice per minute from the storage bin as required by the contract.

Plaintiffs’ complaints to Col-Flake about the operation of the plant continued through most of 1957 and Col-Flake continued to send repair personnel to the plant. Finally, plaintiffs brought consulting engineers of their own into *24 the plant who advised that, among other deficiencies, the capacity of the storage bin was less than 120 tons. After fruitless attempts by the parties, with their lawyers, to settle their differences, this suit was filed on November 26, 1957.

The plaintiffs contend that the ice plant has not been built according to specifications, that the plant machinery is defective and below stipulated production capacity, that the conveyor system does not work properly, that the leveling device, as well as the conveyor system, dirties the ice, making it unpotable and unsalable, that the capacity of the ice storage bin is substantially less than 200 tons, and that there is no way the plant can be brought into compliance with the contract and plans and specifications made part thereof. Relying on Article 1928 3 of the LSA-Revised Civil Code, and the Louisiana decisions 4 interpreting that article, plaintiffs demand that “things be restored to the situation in which they were” before the contract was let, that Col-Flake be required to remove the plant from plaintiffs’ premises, return the $25,000 down payment on the contract price, and pay damages, not only to cover those sums otherwise invested by plaintiffs in the ice plant operation, but also for loss of profits which would have been realized by the partnership had the plant operated as per contract. In the alternative, relying on Article 2769 5 of the LSA-Civil Code, plaintiffs demand a diminution in the contract price by reason of the deficiency in performance.

Col-Flake begins by making several legal defenses. It first says that the failure of plaintiffs formally to complain of the defects in the plant within ten days after notice of completion estops them from denying completion and forecloses them from asserting any defenses based on noncompliance with the contract. Col-Flake also asserts it was not placed in default by plaintiff before suit was brought as required by Louisiana law. 6

Moving to the merits, Col-Flake asserts that the plant has been completed in strict compliance with the contract, that the mechanical breakdowns in the plant and deficiencies in ice production result directly from lack of proper maintenance of the plant facilities, and that, the rust and other foreign matter which finds its way into the ice is attributable-to the failure of the plaintiffs properly to-clean the plant and its equipment, particularly that part of the plant where the-conveyor chain scrapes on the Thermocon slab which serves as its foundation.

With respect to the claim that the ice storage bin does not have a capacity of 200 tons as required by the contract, Col-Flake says that the dimensions of the bin are in fact in excess of those required by the contract. It states further that if the entire bin were filled to its four walls with ice, the capacity would be in excess of 200 tons. It admits, however, that as far as the- *25 practical operation of the ice plant is concerned, the storage bin does not have a capacity of 200 tons because the height cf ice in the 10-foot-high bin can only be seven feet since the leveling device projects down from the ceiling three feet.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
174 F. Supp. 21, 1959 U.S. Dist. LEXIS 3018, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jerrie-ice-company-v-col-flake-corporation-laed-1959.