Kozlowski v. Fowler

71 So. 2d 246, 1954 La. App. LEXIS 631
CourtLouisiana Court of Appeal
DecidedMarch 29, 1954
DocketNo. 20274
StatusPublished
Cited by10 cases

This text of 71 So. 2d 246 (Kozlowski v. Fowler) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kozlowski v. Fowler, 71 So. 2d 246, 1954 La. App. LEXIS 631 (La. Ct. App. 1954).

Opinion

REGAN, Judge.

Plaintiff, Stanley J. Kozlowski, as owner, instituted this suit against the -defendants, Harry S. Fowler, contractor, and his insurer, American Employers Insurance Company, endeavoring tó: recover the sum of $975, together with attorney’s fees, as damages for the breach of a written building contract entered into on August 10, 1951, by the aforementioned parties.

The defendants pleaded the exceptions of no cause or right of action, which' were overruled, and then answered and denied that the residence had been constructed in an unworkmanlike'' manner, pleading especially that the plaintiff, by his formal acceptance of the residence was, in effect, estopped from, questioning the quality of the work incorporated therein.

From a judgment in the court below in favor of the plaintiff in the sum of $770, plus $200 attorney’s fees, the defendants prosecute this appeal. Plaintiff has answered the appeal requesting that the judgment be increased to the original amount prayed for, together with attorney’s fees in the sum of $447.50.

[248]*248Plaintiff relates that on August 10, 1951, a written building contract was entered into between himself, as owner, the defendant Fowler, as contractor, and 'the American Employers Insurance Company, as surety thereon; the contractor undertook and agreed to erect and finish “in a perfect workmanlike manner” a single dwelling in 623 Central Avenue,. Parish of Jefferson for the sum of $14,897 in accordance with the specifications of the Federal Housing Administration; he has paid to the contractor the full price therefor; on or about January 18, 1952, he was induced to accept the residence with the contractor’s assurance that it was constructed in accordance with the contract, plans and specifications, and was also advised by Ward of the F.H.A. to sign the formal acceptance thereof; it subsequently developed, on January 27, 1952, or nine days after plaintiff moved therein, that the representations were false and untrue, in that:

“(1) Exterior and interior doors throughout the building heeded adjustment- in order to close 'properly.
“(2) Water standing on driveway apron to the extent of a depth of % inch after a rain. Also the front walk from the street to the house had a low place at the front steps leaving water standing to the extent of % inch after a rain.
“(3) Gutters around house improperly sloped for drain so that water remains and stands therein to a depth of 3 inches after rain.
“(4) Flashing at the gable over the dining room improperly installed not ' having been placed under the siding at the point near the gutter.
.“(5)' Driveway-strips improperly graded and below grade to the extent of between % inch and % inch from a point approximately even with the front of house to rear of house.
■“(6) Front porch improperly paved and graded so that water stands in an area approximately four ' feet square in the center of porch near-the house wall.”

Plaintiff, in substantiation of the foregoing, related that after a heavy rainfall on January 27, 1952, he discovered water standing on the front porch, in the driveway and in the gutters attached to the house. He then requested an examination of the dwelling by the F.FI.A.; in compliance therewith Archie Holmes, Chief Architect for the New Orleans Office thereof inspected the residence on March 28, 1952, found the existence of these deficiencies and reported them to the Director of the F.H.A., Lawrence Dumestre, who, in turn, verified their existence and called upon the contractor to remedy them. In order to ascertain the cost of correcting these defects plaintiff has secured the following estimates:

“To adjust doors and doorlock $75.00
To repair paving to front of steps and porch 310.00
To repair paving to walk, driveway strips and garage apron 460.00
To reset gutters and pipes to drain properly and install flashing on eave on side wall of gable 130.00
$975.00”

Plaintiff, in view of the foregoing, insists that he is entitled to recover the sum of $97.50 from the American Employers Insurance Company as statutory attorney’s fees in conformity with the provisions of LSA-R.S. 9:3902 and that, in addition thereto, he is also entitled to recover from the defendants herein, in solido, by virtue of a stipulation contained in the building contract, a reasonable attorney’s fee, which he believes to be $350.

While defendants do not concede the presence of the defects, the record conclusively reveals that they did exist and, therefore, defendants assume the position that they are apparent and, as such, were waived' by the formal acceptance of [249]*249the residence by plaintiff on January 18, 1952.

Plaintiff, on the other hand, contends that he entered into a contract for the construction and completion of a dwelling1 “in a perfect workmanlike manner” and that, therefore, by virtue of the provisions of Article 2769 of the LSA-Civil Code, he is entitled to recover for the breach of the contract. This article reads:

“If an undertaker fails to do the work he has contracted to do, or if he does not execute it in the manner and at the time he has agreed to do it, he shall be liable in damages for the losses that may ensue from his non-compliance with his contract.”

In the lower court the deficiencies were not seriously questioned or, in any event, they were found to exist as a matter of fact from the testimony of a disinterested contractual expert, O. F. Harang; however, that court believing that the defective doors, guttering and flashing were apparent to the plaintiff1 when he accepted the building, it refused -recovery therefor, but permitted plaintiff to recover damages for the latent condition of the paving.

Our careful analysis of the record causes us to conclude that all of the defects .in construction do exist and the cost necessary to effect their repair is reasonable. However, counsel for plaintiff conceded, in oral argument, that his client is not entitled to recover the sum of $75, which is the cost of repairing the doors for the reason' that the plaintiff was, in a measure, responsible for the existing condition thereof, in that he insisted during - the course of the work that these doors be made airtight prior to painting. The result was that after they were painted the •doors required adjustment.

The record fully supports this concession and, therefore, we shall not discuss it further.

The plaintiff occupied this residence only mine days after formal acceptance thereof before discovering the defects therein. The record is devoid of evidence indicating that he had knowledge of the defects and after possession thereof voluntarily waived his rights.

There are four distinct deficiencies complained of, the first of which involved the doors which we have eliminated from our consideration, for the reasons set, forth hereinabove.

The second, is the improper slope or fall of- the gutters and the defective installation of the flashing. The lower court disallowed this claim, believing that it could have ■ been easily observed by mounting a ladder and inspecting the roof of the house. We are of the opinion that the lower court erred in this respect. .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dufour v. Schumacher Grp. of La., Inc.
252 So. 3d 1023 (Louisiana Court of Appeal, 2018)
Wallace C. Drennan, Inc. v. Haeuser
402 So. 2d 771 (Louisiana Court of Appeal, 1981)
Hunter v. Wilson
355 So. 2d 39 (Louisiana Court of Appeal, 1978)
Kesk, Inc. v. National Union Indemnity Co.
224 F. Supp. 766 (W.D. Louisiana, 1963)
Autrey v. Williams & Dunlap
210 F. Supp. 491 (W.D. Louisiana, 1962)
Russell v. Bartlett
139 So. 2d 770 (Louisiana Court of Appeal, 1961)
Engle v. Hardouin
119 So. 2d 510 (Louisiana Court of Appeal, 1960)
Jerrie Ice Company v. Col-Flake Corporation
174 F. Supp. 21 (E.D. Louisiana, 1959)
Hunter v. Mayfield
106 So. 2d 330 (Louisiana Court of Appeal, 1958)
Svendson v. American Indemnity Co. of Galveston
76 So. 2d 737 (Louisiana Court of Appeal, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
71 So. 2d 246, 1954 La. App. LEXIS 631, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kozlowski-v-fowler-lactapp-1954.