Kesk, Inc. v. National Union Indemnity Co.

224 F. Supp. 766, 1963 U.S. Dist. LEXIS 7664
CourtDistrict Court, W.D. Louisiana
DecidedDecember 20, 1963
DocketCiv. A. Nos. 8149, 8188, 8224, 8197
StatusPublished
Cited by2 cases

This text of 224 F. Supp. 766 (Kesk, Inc. v. National Union Indemnity Co.) is published on Counsel Stack Legal Research, covering District Court, W.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kesk, Inc. v. National Union Indemnity Co., 224 F. Supp. 766, 1963 U.S. Dist. LEXIS 7664 (W.D. La. 1963).

Opinion

BEN C. DAWKINS, Jr., Chief Judge.

These suits began as actions by suppliers against the principal contractor, and its surety, on a Capehart housing project, for failure of a subcontractor to. pay for materials furnished and used in the project. Summary judgments were granted in favor of the original complainants in cases numbered 8149, 8188, and 8224, against the prime contractor Kesk, Inc. Cross-claims and a third party demand were filed in these three cases, against National Union, surety for Mojave, the subcontractor, by Kesk and USF&G, its surety.1 The fourth case, number 8197, is a direct action by Kesk. against National Union. The cases were consolidated since in each indemnity is; sought from National Union.

The basic facts are that on March 9, 1959, the United States, acting through the Department of the Army and under the authority of the Capehart Act, 42 U.S.C. § 1594 et seq., executed a contract with Kesk and Bossier Base Development Co., Inc., a so-called mortgagor-builder. By this contract, Kesk undertook to furnish all labor, materials and equipment necessary to construct two hundred (200) Capehart permanent family housing units at Bossier Base, Louisiana, under Contract No. DA-03-050-eng-3441, FHA Project No. 059-81015 Army No. 4. Kesk previously had caused the mortgagor-builder to be in[768]*768corporated, all of its stock being placed in escrow with a private lending mortgagee. Provision was made for transferring the entire stock to the Government upon completion of the project.

This procedure for establishing a mortgagor-builder corporation is essentially a device for obtaining private capital to finance government military housing projects. Private lenders are protected since such projects are FHA insured under provisions of the Armed Services Housing Mortgage Insurance Act, 12 U.S.C. § 1748 et seq. Contemporaneously with the execution of the housing contract the Government leased the land upon which the houses were to be built to the mortgagor-builder. Rentals later to be received from persons occupying the houses Were to be paid upon the indebtedness due the lending mortgagee, and upon its payment in full, the mortgagor-builder was to be dissolved, with title to the houses passing to the Government.

As the prime contractor, Kesk was required to give a payment and performance bond, which it did with USF&G as surety. For its own protection, Kesk, in turn, required a conventional surety-ship bond from its electrical subcontractor, Mojave Electric Company. Mojave defaulted on the contract in early 1960, and bankruptcy soon followed. Kesk immediately notified National Union, Mojave’s surety, that Kesk would hold National Union responsible for any loss and demanded that it take steps to fulfill its suretyship obligations. National Union denied all responsibility upon the ground that it was released by reason of allegedly premature payments made to Mojave by Kesk in violation of the subcontract agreement.

There is but one primary question to he decided: Did Kesk make premature payments to Mojave, and, if so, was National Union thereby released ?

The parties agree that solution of this question lies in a correct interpretation of the subcontract between Kesk and Mojave. Kesk contends that it had a duty to make progress payments on account to Mojave for 90% of the work completed and inventory on the job site. National Union argues that Kesk was obligated to make payments only for work completed and materials in place, and that payments for inventory were premature. Each relies upon typed provisions in Section 4 of the subcontract, pertinent portions of which provide:

“ * * * The Subcontractor shall submit a requisition for payment five (5) days in advance of Contractor’s requisition to the Owners. Contractor shall pay to Subcontractor an amount equal to 90%- of all work completed and in place (less any work rejected by Contractor or Owner) except that no claim for payment shall be made by Subcontractor which is in excess of the amount approved by the Owners for payment by the Owners to the Contractor.
“Contractor shall pay to the Subcontractor the total of approved requisitions for work completed and inventory on job site within five (5) days of receipt of receipt [sic] of Contractor’s payment from the Owners.” (Emphasis added.)

Accepted rules of contract interpretation will resolve the superficial conflict between the provisions quoted above.2 Wherever possible, if consistent with the intention of the parties and the general purpose of the agreement, a construction which gives effect to all provisions of the contract should be adopted.3

In the first paragraph quoted above it is clearly provided that payment shall be made for all work completed. The second paragraph just as plainly states that payment shall be made for work completed and for inventory on the job site. [769]*769Any inference from the first that payment is to be only for work completed is negated by the second paragraph. Effect can be given to both by applying the broader provisions of the second. This is the interpretation placed upon the agreement by the parties, Kesk and Mojave.4

The reasonableness of this interpretation also is emphasized by the fact that Kesk, under its prime contract, received payment for inventory.5 The composition of this inventory for which Kesk wa^\ paid included inventory belonging to subcontractors as well as Kesk’s own inventory. That the parties intended to provide for a portion of this payment to be turned over to subcontractors for their share of the inventory seems reasonably to follow.

National Union relies upon the principle that ambiguous provisions in a contract should be resolved against the drafter, in this case, Kesk. However, this rule of interpretation is one of last-resort, not to be utilized when the intent of the parties otherwise can be discerned.6 We thus conclude that the quoted provisions of Section 4 of the subcontract required Kesk to pay both for work completed and for inventory on the job site.

An alternative and rather tenuous defense urged by National Union is that Article 24 of the 1958 AIA General Conditions 7 applies to the Mojave subcontract. The subcontract was written on an AIA standard form for subcontracts which contained the statement: “For Use in Connection with the Sixth Edition of the Standard Form of Agreement and General Conditions of the Contract.” The Sixth Edition was the 1951 version, and its Article 24 does not support National Union’s contention.8

[770]*770A further effort to escape this result is made by argument that since the subcontract was written after 1958 the parties must have had reference to the newer 1958 General Conditions, even though the subcontract used expressly specified the Sixth Edition (1951 version).

Section 1 of the subcontract states:

“The Subcontractor agrees to furnish all material and perform all work as described in Section 2 hereof for FHA Project No. 059-81015-Army No. 4 and ENG. Serial No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
224 F. Supp. 766, 1963 U.S. Dist. LEXIS 7664, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kesk-inc-v-national-union-indemnity-co-lawd-1963.