Book v. Schoonmaker

26 So. 2d 366, 210 La. 94, 1946 La. LEXIS 770
CourtSupreme Court of Louisiana
DecidedApril 22, 1946
DocketNo. 37983.
StatusPublished
Cited by11 cases

This text of 26 So. 2d 366 (Book v. Schoonmaker) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Book v. Schoonmaker, 26 So. 2d 366, 210 La. 94, 1946 La. LEXIS 770 (La. 1946).

Opinion

HAMITER, Justice.

A written contract was entered into on April 27, 1944, by and between F. A. Book and G. C. James of ElDorado, Arkansas, on the one hand (referred to as contractor), and G. C. Schoonmaker of Evansville, Indiana, on the other hand (referred to as owner), by the terms of which the contractor agreed to drill for the owner a well in search of oil or gas at a selected location in DeSoto PaTish.

The contractor undertook to furnish “everything necessary, including all labor, water and supplies except services specifically hereinafter to be furnished by the owner.” Among the excepted services was that mentioned in the following provision, exceedingly important in the determination of this litigation, namely: 1‘Owner shall furnish to contractor gas for fuel from owner’s well on the Anders farm, about one and one-half miles west of the location herein, contractor to lay and make connections to said gas well at his own risk and expense.”

The contract further provided: “Owner shall pay to contractor for the drilling of the well herein provided, the sum of Twenty two thousand five hundred and no/100 Dollars, ($22,500.00) plus the sum of Six and no/100 Dollars ($6.00) per foot for any hole drilled below 5,000 feet, and not deeper than 5,300 feet, and such extra rig time as hereinafter provided, upon completion of contractor’s obligation hereunder.”

The referred to extra rig time (several possible forms were detailed) was valued by the parties at $15 per hour.

Drilling operations under the contract began on June 1, 1944, and continued until *98 the early part of August, 1944, when the agreed depth of the well was reached, at which time the contractor was paid the stipulated sum of $22,500. Meanwhile, during the course of the drilling, the owner advanced to the contractor the additional sum of $1250 (two payments of $750 and $500, respectively), this item being more fully discussed hereinafter.

On or about August 21, 1944, the contractor (then F. A. Book and J. H. Trotter, the latter having previously acquired the interest of G. C. James) sent to the owner a statement of account claiming a balance due and owing under the contract by the latter of $5071.92. This statement listed various extra services and materials furnished in connection with the drilling of° the well, and also the above-mentioned credit of $1250.

Upon the owner’s disputing the correctness of several of the items charged to him, the contractor recorded in the mortgage records of DeSoto Parish an instrument giving notice of a claim to a lien and privilege under the provisions of Act No. 68 of 1942. Thereafter F. A. Book and J. H. Trotter (the contractor) instituted this suit against Schoonmaker (the owner) to recover judgment for the alleged indebtedness of $5071.92, and, in connection therewith, obtained the issuance of a writ of provisional seizure.

The defendant answered admitting an indebtedness of $122.19, this representing certain charges totaling $1372.19 less the advance on the contract of $1250. Defendant denied owing the remaining charges totaling $4949.73, which, according tO' the notice of lien filed and the itemized statement attached to plaintiffs’ petition, were for:

Down time caused by lack of fuel $1755.00 Fuel oil purchased by contractor 3194.73

$4949.73

Plaintiffs’ position in the suit, with reference to these two disputed items, is that under the contract defendant obligated himself to furnish all of the fuel required in drilling; that the gas supply from the owner’s well on the Anders farm was insufficient for carrying on the work and defendant failed to otherwise provide fuel; and that, because of such insufficiency and failure, the drilling rig had to be shut down a total of 117 hours with a resulting loss to the contractor of $1755 ($15 per hour), and also the purchasing of fuel oil costing $3194.73 was necessary.

In denying liability for the two items the defendant, to quote from the brief of his counsel, offers two reasons:

“1. That the contract sued on and especially the clause relied on by plaintiffs-appellants do not provide that he shall furnish all of the fuel necessary for the drilling of the well, but simply such gas as would be furnished by the well on the'Anders farm and known as the Anders well.

*100 “2. That the failure of a sufficient supply of gas from the Anders well with which to drill the Anthony well was the fault of the plaintiifs-appellants and not his fault.”

In reconvention defendant prayed for judgment against the plaintiffs for $7800 as damages resulting to the Anders well, this representing the cost to him of reconditioning it.

The district judge, after a trial of the merits, rendered judgment in favor of plaintiffs for $684.69 (as well as costs of court) which is for the following items:

Balance admitted to he unpaid $122.19

Thirty-six hours shut down time at $15.00 per hour 540.00

Fee for preparing and filing lien claim ■ 15.00

Cost of filing lien 7.50

Defendant’s reconventional demand was rejected.

Appeals from the judgment were perfected by both plaintiffs and defendant.

Defendant has since abandoned the re-conventional demand, his counsel conceding here, in oral argument and in brief, that the evidence adduced during the trial of the case is not sufficient to sustain it. Serious and strong complaint is made, however, about the award to plaintiff of shut down time.

With reference to the main demand, counsel for plaintiffs, in their brief, call attention to the admissions made in defendant’s answer and then comment: “As a result of this as is shown by the above computation the defendant has admitted an indebtedness of $122.19 in excess of the $1250.00 which he has paid. Accordingly, the issues of the case are reduced to the denial by the defendant of owing the down time shown in Item IV of the statement * * * and the cost of fuel oil shown in Item VIII of the statement * * Further, counsel state:

“The only legal question presented by the issues in this cáse is • an interpretation of the contract which existed between the parties. As a matter of fact there is only one' clause to be interpreted, though another relates to it and explains it; The clause to be interpreted and applied to the facts in the case is the following:

“ ‘Owner shall furnish to contractor gas for fuel from owner’s well on the Anders, farm, about 1% miles West of the location herein, contractor to lay line and make connections to said gas well at his own risk and expense/ ”

At the outset it is to be observed that if by the controversial clause the parties intended that defendant should furnish only such gas as was available from the Anders well which he owned (the interpretation placed on the clause by the district judge), clearly defendant is not responsi *102 ble for any of the disputed charges, not even the thirty-six hours shut down time at $15 per hour which has been awarded plaintiffs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Acadian Diagnostic Lab, L.L.C. v. Quality Toxicolo
965 F.3d 404 (Fifth Circuit, 2020)
Nelson v. Nelson
985 So. 2d 1285 (Louisiana Court of Appeal, 2008)
Crooks v. Placid Oil Co.
981 So. 2d 125 (Louisiana Court of Appeal, 2008)
Steve H. Crooks, Et Ux. v. Placid Oil Company
Louisiana Court of Appeal, 2008
TRAINA PLUMBING & HEATING CONTRACTORS, INC. v. Palmer
580 So. 2d 525 (Louisiana Court of Appeal, 1991)
Kenner Industries, Inc. v. Sewell Plastics, Inc.
451 So. 2d 557 (Supreme Court of Louisiana, 1984)
Kesk, Inc. v. National Union Indemnity Co.
224 F. Supp. 766 (W.D. Louisiana, 1963)
Elliott v. Dupuy
135 So. 2d 54 (Supreme Court of Louisiana, 1961)
Texas & New Orleans Railroad v. City of New Orleans
185 F. Supp. 85 (E.D. Louisiana, 1960)
Simmons v. Hanson
82 So. 2d 757 (Supreme Court of Louisiana, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
26 So. 2d 366, 210 La. 94, 1946 La. LEXIS 770, Counsel Stack Legal Research, https://law.counselstack.com/opinion/book-v-schoonmaker-la-1946.