Columbus Rock Co. v. Alabama General Insurance

153 F. Supp. 827, 1957 U.S. Dist. LEXIS 3307
CourtDistrict Court, M.D. Alabama
DecidedAugust 6, 1957
DocketCiv. No. 1308-N
StatusPublished
Cited by4 cases

This text of 153 F. Supp. 827 (Columbus Rock Co. v. Alabama General Insurance) is published on Counsel Stack Legal Research, covering District Court, M.D. Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Columbus Rock Co. v. Alabama General Insurance, 153 F. Supp. 827, 1957 U.S. Dist. LEXIS 3307 (M.D. Ala. 1957).

Opinion

JOHNSON, District Judge.

This cause came on for a hearing before this Court sitting without a jury, and was submitted to the Court on July 30, 1957, for a determination of the issues as made by the pleadings, stipulations, and the testimony of several witnesses. The Court now proceeds to make this determination in this memorandum opinion embodying herein the appropriate findings of fact and conclusions of law.

Plaintiff, Columbus Rock Company, a Corporation of the State of Georgia, originally brought this action against the defendant, Alabama General Insurance Company, a Corporation of Alabama, in the amount of $18,655.07, plus interest and attorneys’ fees. Plaintiff’s claim was reduced to $17,887.69, plus interest and attorneys' fees, after pre-trial discovery and pre-trial hearing. Plaintiff’s suit is authorized and is brought as authorized by the provisions of Title 50, § 16 of the 1940 Code of Alabama, as amended.1

[829]*829On or about March 15, 1956, the Hillabee Construction Company, Inc., referred to herein as the contractor, entered into a contract with the State of Alabama for certain highway construction work. This work was designated as project numbers 833, 834, 835, and 836, and was to be made in Bullock County, Alabama. In compliance with this statute, the contractor on the same date executed as principal a bond with the defendant as surety thereon, said bond being conditioned upon the prompt payment to all persons supplying the contractor with labor, materials, or supplies “for or in the prosecution of the work provided for in such contract.”

Plaintiff furnished, at the contractor’s request, crushed stone; the agreement to furnish this stone was after written quotations had been furnished to the contractor by the plaintiff. These written quotations set out a certain price per ton for the stone without the prepayment of the freight and a different and higher price per ton with the freight prepaid. The contractor designated to the plaintiff certain shipping points to which the stone was to be shipped for use on the four bonded projects. These points were relatively isolated places in Bullock County, Alabama, with no railway agents at these points to collect any freight that may have been collectible at the points of destination. Each shipping point was selected and designated for its being relatively close to one of the four bonded projects. The contractor agreed with the plaintiff to “reimburse Columbus Rock for the prepaid freight charges.” These prepaid freight charges constitute $7,207.68 of the amount claimed of this defendant by this plaintiff. Plaintiff shipped this stone to the selected points, each shipment being invoiced and each invoice designating the project the stone was “for,” either by number of the project or by the shipping point that had been designated for that particular project. For instance, one of the shipping points designated by the contractor was Three Notch, Alabama, and one or more of the invoices that designated the stone did so by the designation “Job number Three Notch, Alabama.”

A certain amount of this stone was diverted by the contractor, that is to say, it was used on projects other than those this defendant stood surety for on this bond. This diversion was on one Bullock County road project and on certain gas station entrances. Because of patching work on the bonded projects and loss from stock piling some of this stone, it was impossible for the engineer in charge of the projects to determine the amount so diverted from the bonded projects. However, it is clear that it was a relatively small percentage of the amount of stone plaintiff shipped. This diversion was made by the contractor without the knowledge and without the consent of the plaintiff.

The contractor failed to pay the plaintiff, and the plaintiff, as the statute requires, gave written notice on March 21, 1957, to the defendant surety company that $18,655.07 was claimed by the plaintiff of the surety company. This defendant took no action after receiving this [830]*830notice, and the suit claiming the cost of all the materials, the freight charges, and attorneys’ fees was instituted on May 8, 1957. The defendant at the pretrial hearing on July 17, 1957, offered judgment to plaintiff in the amount of $10,109.79, with interest from March 22, 1957, this amount representing the cost of the materials without the freight charges and without the cost of the diverted materials and without any attorneys’ fees.

The questions presented to the Court by these facts are:

(1) If the vendor pays freight charges on materials he furnished the contractor, can the vendor recover these charges from the contractor’s surety under this Alabama statute?

(2) When materials are furnished to the contractor for bonded projects, but a portion of such materials are used by the contractor without the knowledge or consent of the supplier on non-bonded work, can the supplier recover from the surety on the contractor’s bond for the cost of such diverted materials?

(3) Can plaintiff recover for attorneys’ fees incurred by it under this statute when the claim was for $18,655.07 and the suit as finally amended by plaintiff claims only $17,887.69?

Freight Charges:

The present Alabama statute, supra, was enacted in 1935 and superseded a similar statute that had been enacted in 1927. As stated in the editor’s note, page 601, Title 50, § 16, Alabama Code 1940:

“The Act of 1935 covers the same field as the Act of 1927, but is broader in its scope and comprehends situations in addition to those contemplated in the 1927 Act.”

It should, at this time, be noted that the phrase in both these statutes regarding the payment of materialmen and those who furnish supplies to the contractor is almost identical. The 1927 statute, Gen.Acts 1927, p. 37, states the bond is to assure the payment of:

“ * * * All persons supplying him or them [contractor] with labor, material, feed-stuffs or supplies, in the execution of the work provided for in such contract.” (Emphasis supplied.)

And the present statute, Gen.Acts 1935, pp. 70, 71, states:

“ * * * All persons supplying him or them with labor, materials, feed-stuffs or supplies for or in the prosecution of the work provided for in such contract * * *." (Emphasis supplied.)

There seems to be only one Alabama case deciding this first question of whether freight charges are covered by the bond, as if it were materials, and that is the case of Central of Georgia Ry. Co. v. United States F. & G. Co., 1931, 223 Ala. 458, 137 So. 36, 38, 39; and the court there decided that freight charges were covered by the bond just as were charges for materials. There the court stated:

“In the City of Stuart, for Use and Benefit of Florida East Coast Ry. Co. v. American Surety Co. of New York, 38 F.2d 193, 194, 195, involving a claim for freight and demurrage, decided by the United States Circuit Court of Appeals, Fifth Circuit, the claim was sustained. The reasoning in that case seems to us unanswerable. To quote from the opinion:
* * * *

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
153 F. Supp. 827, 1957 U.S. Dist. LEXIS 3307, Counsel Stack Legal Research, https://law.counselstack.com/opinion/columbus-rock-co-v-alabama-general-insurance-almd-1957.