Steel Const. Co. v. Louisiana Highway Commission

60 F. Supp. 183, 1945 U.S. Dist. LEXIS 2363
CourtDistrict Court, E.D. Louisiana
DecidedMarch 21, 1945
DocketNo. 82
StatusPublished
Cited by7 cases

This text of 60 F. Supp. 183 (Steel Const. Co. v. Louisiana Highway Commission) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Steel Const. Co. v. Louisiana Highway Commission, 60 F. Supp. 183, 1945 U.S. Dist. LEXIS 2363 (E.D. La. 1945).

Opinion

BORAH, District Judge.

Findings of Fact

I. There exists in this case a diversity of citizenship and the amount involved far exceeds the jurisdictional amount.

2. The Steel Construction Company did not follow the administrative procedure outlined in subsections 1, 7 and 8 of Section 5, Division 1 of the contract, to correct the abuses alleged to exist in this case, but in most instances acquiesced in the requirements of the inspectors and/or resident engineer.

3. The Steel Construction Company only made general complaints and these were in most instances made after the work involved in the dispute had been performed in compliance with the request of the inspectors and/or resident engineer.

4. In some instances plaintiff protested during the work and put the resident engineer on notice that it would make a claim but in all instances plaintiff met the requirements of the inspectors and the resident engineer and performed the work demanded of it without ever submitting the matter or dispute to the State Highway Engineer for his ruling or decision.

5. During the progress of the work the State Highway Engineer received a few letters from the officers of the Steel Construction Company complaining generally about the unreasonable inspection requirements of his subordinates but in none of these letters did plaintiff request a ruling from the State Highway Engineer.

6. At no time during the progress of the work did the Steel Construction Company refer any of the disputed items to the State Highway Engineer and request a ruling thereon.

7. The Steel Construction Company did not obtain any extra work order or supplemental contract in respect to any of the items involved in this suit, nor did they request one from any of the highway engineers.

[185]*1858. It was not until after the work was completed that any claim of any nature or kind was presented by the Steel Construction Company to the State Highway Engineer, and then a claim was presented by the attorneys for the plaintiff to the State Highway Engineer unaccompanied by any supporting evidence, statements, affidavits, or even arguments as to why the said State Highway Engineer should allow the claim.

9. The claim was not itemized or broken down until the very day this suit was filed against the Louisiana Highway Commission for recovery.

10. The State Highway Engineer gave consideration to the claim as presented and decided that plaintiff was not entitled to be paid any additional amounts in addition to that offered in the final check which it had refused to- cash.

11. The engineers and inspectors acted throughout in good faith. Fraud, bad faith or gross error on the part of the State Highway Engineer, the resident engineer or the inspectors is not alleged and the evidence adduced at the trial would not sustain such a charge.

12. The court finds that the balance due plaintiff on the final estimate amounts to $1,435.11; that of this amount $420 is in dispute; that defendant, tendered a check for $1,015.11 in payment of the balance due on the contract and withheld and deducted $420 as liquidated damages for 12 days’ delay but that defendant did not put plaintiff in default for failure to complete the contract within the allotted time.

13. Inspector Senn did not reject rivets which were according to specifications and his inspection of the rivets was not unreasonable.

14. Inspector Senn did not require plaintiff to clean and paint steel in a manner not in accordance with the specifications. The inspection and requirements were reasonable as to cleaning and painting in the shop.

15. The defendant did not request or order plaintiff to sand blast the steel in lieu of cleaning it with rotary wire brushes.

16. Inspector Senn did not require steel to be loaded in a manner different from the requirements of the railway and his requirements were not unreasonable under the circumstances.

17. The inspection and requirements as to field painting by the Steel Construction Company and its subcontractor Carlson were not unreasonable under the circumstances.

18. The requirements of the State Highway Inspectors, including Roland and Baker, were not unreasonable in regard to the cutting out and replacing of field rivets. The inspectors did not order rivets cut out that were up to specifications.

19. Plaintiff did at the request of Erickson dig ditches and do some grading on the west approach to restore the grade to as good a condition as it was before plaintiff commenced operations.

20. In respect to the claim for reaming rivet holes the court finds that there were shop errors in punching and it was necessary to ream these mismatched rivet holes to get fair holes in which to drive the rivets and secure the connection.

21. The plaintiff has been paid for the extra ties which had to be replaced because of the settlement of the east and west railway abutments.

22. Plaintiff received payment for shims at the contractor’s price which included the cost of labor and it was not due to the fault of the Highway Commission that these shims had to be placed under the tie plates at the curve transition point.

23. Plaintiff neither requested nor received any work order, supplemental agreement or written force account for the work of raising span 22. This work was done upon the order of Inspector Roland to permit him to inspect the bearing plate.

24. The realigning of the towers was not to correct surveying errors but was done under an agreement between Inspector Roland and plaintiff’s General Superintendent Campbell in order to facilitate the plaintiff, and this agreement did not provide for extra compensation for this work and no written order was obtained.

25. The furnishing of bolts and pins was in accordance with the specifications and agreement between plaintiff’s general superintendent and the resident engineer and plaintiff was paid for these items in accordance with the terms of the contract.

26. The court finds that all shims were paid for under the terms of the contract and that the plaintiff was required to furnish shims in no larger amount than was anticipated in view of the nature of this contract; that the shims were required because of errors in fabrication of the steel [186]*186and because of settlement in the foundations and not because of any error or negligence on the part of the highway engineers.

27. The court finds that any additional storage or expense of unloading steel was due to the delay in the preparation of the foundations by the superstructure contractor, the Uvalde Construction Company, and that the Steel Construction Company had full knowledge of Uvalde’s construction schedule and knew when it commenced erection that it might be delayed by the superstructure contractor. The court makes the same finding in regard to the realigning of tracks.

28.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J.T.P. Development Corp. v. Majestic Realty Corp.
130 P.R. Dec. 456 (Supreme Court of Puerto Rico, 1992)
Urseth v. City of Dayton
680 F. Supp. 1150 (S.D. Ohio, 1987)
Federal Savings & Loan Ins. Corporation v. Szarabajka
330 F. Supp. 1202 (N.D. Illinois, 1971)
Gulotta v. Swinney
143 So. 2d 775 (Louisiana Court of Appeal, 1962)
Simmons v. American Export Lines, Inc.
26 F.R.D. 111 (S.D. New York, 1960)
Jerrie Ice Company v. Col-Flake Corporation
174 F. Supp. 21 (E.D. Louisiana, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
60 F. Supp. 183, 1945 U.S. Dist. LEXIS 2363, Counsel Stack Legal Research, https://law.counselstack.com/opinion/steel-const-co-v-louisiana-highway-commission-laed-1945.