Highway Const. Co. of Ohio, Inc. v. City of Miami

126 F.2d 777, 1942 U.S. App. LEXIS 4255
CourtCourt of Appeals for the Fifth Circuit
DecidedFebruary 25, 1942
DocketNo. 9938
StatusPublished
Cited by13 cases

This text of 126 F.2d 777 (Highway Const. Co. of Ohio, Inc. v. City of Miami) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Highway Const. Co. of Ohio, Inc. v. City of Miami, 126 F.2d 777, 1942 U.S. App. LEXIS 4255 (5th Cir. 1942).

Opinion

McCORD, Circuit Judge.

The highway Construction Company of Ohio, Inc., brought suit against the City of Miami, Florida, to recover amounts alleged to be due for work performed and materials furnished in and about the construction and improvement of certain streets and sewers of the City. The case was tried to a jury. After a three-months trial, the jury returned a verdict in favor of the defendant on all claims with the exception of one for $23,263.15 which the City admitted it owed. Judgment was entered in accordance with the verdict, and the Construction Company appealed.

After due advertisement and competitive bidding, the Construction Company on April 30, 1926, entered into seven contracts with the City of Miami for the paving and improvement of approximately twenty-five miles of streets. The seven contracts, including plans and specifications, are identical in every respect, except as to description of the streets to be improved, the quantity of work to be performed, and the amount of the contractor’s performance bond. Work under the contracts progressed through 1926, and was finally and fully completed in December of that year.

In April, 1927, the Construction Company was advanced the sum of $100,000 in addition to amounts which had been previously paid on monthly estimates. In June, 1927, the engineer made and submitted his final report in which he found that the contractor was entitled to receive $123,-263.15 as a final payment for work, materials, and extras. The engineer’s report was accepted and approved, and on June 8, 1927, the Commission of the City of Miami authorized payment of the sum of $123,-263.15, less the April advance payment of $100,000. Under the findings of the engineer and resolution of the City Commission, the contractor was entitled to receive $23,263.15 as a final payment under [779]*779the several contracts. The Construction Company refused to accept this amount as full payment of all claims, and on August 24, 1929, filed suit in equity against the City. The cause was thereafter transferred to the law side of the docket.

The declaration as first filed claimed damages in the sum of $700,000 and was in seventy-one counts. The Construction Company changed counsel several times, and on January 5, 1931, it filed an amended declaration. Upon stipulation of the parties the cause was referred to an auditor in 1932. The auditor filed his report in 1934, and both parties filed exceptions. The case had become complicated by a prolixity of pleadings, and on October 5, 1937, the parties by stipulation agreed to suppress the report of the auditor, and abandon all pleadings, motions, and mutual stipulations offered since the filing of the amended declaration. It was further agreed that the City would plead over to the amended declaration. The trial court approved the stipulation on October 7, 1937, and vacated its orders mentioned therein. The amended declaration was then tested by demurrer, and was held to be good.

The amended declaration as finally presented was in many respects different from the declaration as first offered, in that the amounts of claims were changed, and the theories of many of the claims were different. The amended declaration was in seventy-one counts; the first sixty-seven being special counts, and the last four being the common counts. The declaration as amended sought recovery for “Additional Depth of Inlets and Rock Foundation”, “Reconstructing Old Manholes", “Additional Grading”, “Additional Cost of Coarse Aggregate”, “Additional Depth of Sewer Pipe”, “Additional Cost of Finishing Subgrade”, “Additional Cost of Rock Used in Foundation”, “Extra Work”, amounts due under “Final Estimates”, and other claims under the “Common Counts”. The Construction Company also added the following allegation to its declaration: “And all conditions were fulfilled and all things happened and all times elapsed necessary to entitle the plaintiff to receive the payment of the said several sums of money hereinabove set forth and to maintain this action; yet the defendant has not paid the said several sums or any part thereof.”

To this long list of counts the City of Miami filed pleas denying the facts alleged, and set up numerous general and special pleas. The case then proceeded to trial.

Important here is Section 54 of the Charter of the City of Miami: “When it becomes necessary in the opinion of the City Manager to make alterations or modifications in a contract for any public work or improvement such alterations or modifications shall be made only when authorized by the Commission upon the written recommendation of the City Manager. No such alteration shall be valid unless the price to be paid for the work or material, or both, under the altered or modified contract shall have been agreed upon in writing and signed by the contractor and the City Manager prior to such authorization by the commission.”

Of further importance are excerpts from the contracts entered into by the Construction Company and the City:

“4. * * * it is understood that the contractor has, by personal examination and inquiry if necessary, satisfied himself as to the local conditions and as to the meaning, requirements and reservations of the specifications and plans; for after the letting, no deviation will be allowed from the Engineer’s interpretation of the plans, specifications and contract. In case errors or omissions are discovered, they are to be corrected or supplied by the Contractor, without extra cost to the City, according to the apparent intention of the designing engineer. * * *
“5. * * * work and dimensions must be in strict accord with them, [referring to the engineer’s interpretation of the plans, specifications, and contract] except only when the Director of Public Service may in writing authorize an exception. H*
“6. * * * All work done or materials furnished are to be subject to the acceptance or rejection of the Engineer, who shall in all cases determine the amount, quality, fitness and acceptability of the work and materials to be paid for and decide finally and conclusively all questions or differences of opinion that may arise as to the interpretation of the plans and specifications, or the fulfillment of the terms of this contract; and in the event of such question or difference, his decision is to be a condition precedent to the contractor’s right to receive any money from this contract. * * *
[780]*780“7. * * * The right is expressly reserved for the Engineer to increase or decrease these quantities to such extent as he may find necessary for the proper completion of the work, or from the limits of the appropriation; if such alterations increase the quantities, the added work or materials will be paid for along with the original, at the rates stipulated in the contract, and subject to all the terms and conditions herein. * * *
“9. Extra Work. Quantities of work or materials in excess of those named in the instructions to bidders and of the same kind, are not to be considered as extra work, and such excess when ordered by the Engineer, will be paid for at contract rates, as hereinbefore specified.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State, Department of General Services v. Cherry Hill Sand & Gravel Co.
443 A.2d 628 (Court of Special Appeals of Maryland, 1982)
Dep't of Gen. Serv. v. CHERRY HILL S & G CO.
443 A.2d 628 (Court of Special Appeals of Maryland, 1982)
Ago
Florida Attorney General Reports, 1982
Goodwin, Inc. v. City of Lafayette
418 F.2d 698 (Fifth Circuit, 1969)
Tidwell v. Ray
208 F. Supp. 952 (N.D. Mississippi, 1962)
Blake Construction Company v. United States
252 F.2d 658 (Fifth Circuit, 1958)
Blake Construction Co. v. United States
252 F.2d 658 (Fifth Circuit, 1958)
Chicago Sugar Co. v. American Sugar Refining Co.
176 F.2d 1 (Seventh Circuit, 1949)
Steel Const. Co. v. Louisiana Highway Commission
60 F. Supp. 183 (E.D. Louisiana, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
126 F.2d 777, 1942 U.S. App. LEXIS 4255, Counsel Stack Legal Research, https://law.counselstack.com/opinion/highway-const-co-of-ohio-inc-v-city-of-miami-ca5-1942.