Rea Construction Company and Aetna Casualty and Surety Company v. B. B. McCormick & Sons, Inc.

255 F.2d 257, 1958 U.S. App. LEXIS 5212
CourtCourt of Appeals for the Fifth Circuit
DecidedMay 13, 1958
Docket16929_1
StatusPublished
Cited by12 cases

This text of 255 F.2d 257 (Rea Construction Company and Aetna Casualty and Surety Company v. B. B. McCormick & Sons, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rea Construction Company and Aetna Casualty and Surety Company v. B. B. McCormick & Sons, Inc., 255 F.2d 257, 1958 U.S. App. LEXIS 5212 (5th Cir. 1958).

Opinion

JOHN R. BROWN, Circuit Judge.

The question here is whether the District Court in a non-jury trial properly denied recovery to Contractor 1 for items claimed to have been the responsibility of Subcontractor 2 on the ground that the contract was ambiguous and unclear, thus allowing receipt and decisive consideration of parol evidence. That is the crucial issue for once it is determined that the contract was ambiguous, Contractor concedes that it cannot overturn the consequent fact findings on interpretation which come here with the buckler and shield of F.R.C.P. 52(a), 28 U.S.C.A.

The immediate problem concerns the sand-shell backfill of that portion of trenches dug for the installation of the drainage system which traversed paved runways or taxiways at NAAS, Corry Field, Pensacola, Florida.

The prime contract was between the United States Navy and Contractor. It covered the general rehabilitation of two contiguous East and West fields, the runway pattern of which resembled: XX. Runways and taxiways of this war-weary field were inadequate for planes of the jet-age primarily because of poor drainage of the field occasioned by an insufficient drainage system and grade of paved areas and adjacent turfed ground. The contract was for the “resurfacing, grading and storm drainage” of the field. It covered the necessary regrading, removal of the old drainage system, installation of a new drainage system, addition at extensive areas specified of a hot mix sand-asphalt leveling course to bring runways and taxiways up to grade, *259 the addition of a two-inch hot mix as-phaltic concrete wearing course on the runways and some taxiways, the addition of a bituminous sand-seal coat on some taxiways, installation of runway lights, painting and marking the fields, and seeding and fertilizing some 263 acres of turfed area. The contract bid price was approximately $1,500,000. For that part undertaken by Subcontractor, the bid was approximately $414,000.

A description in a broad general way of the work to be done serves to put the specific problem of the subcontract in its context. The runways and taxiways were not level. They were dished out and uneven. As water collected and remained in these low spots, this aggravated the problem of general inadequate drainage and caused further subsidence, settling or destruction of the surfaces. To remedy this, the turfed area was to be lowered while the surfaces of taxiways and runways were to be raised considerably to conform to new and higher grades.

To increase elevation of the runways-taxiways and to provide a smooth continuous surface, the plans and specifications called for a leveling course to be applied on top of existing paved runways at variable thicknesses necessary to meet grade. Where the leveling course was 6 inches or less in thickness, sand-asphalt was required. Where it exceeds 6 inches in thickness, sand-shell, a 50/50 mixture of both, was called for. Sand-asphalt, as the name implies, was a hot mix of sand, aggregate and specified asphalt to be prepared and laid in a carefully prescribed manner. On the top of the added leveling course (of sand-shell or sand-asphalt as the case might be) or directly on the original top surface of the existing runways in areas where no leveling course was required to meet grade, a two-inch hot mix asphaltic concrete wearing course was prescribed. This too, was a hot mix of asphalt, aggregate, mineral cement and filler mixed, prepared and applied in accordance with meticulous specifications. As can readily be seen, this was essentially a road-building operation.

The plans also called for an extensive new drainage system consisting of an intricate pattern of subterranean concrete drainage pipe laid in trenches at prescribed sub-elevations. These drainage lines following the prescribed contour patterns were, of course, run under both paved and turfed areas. To lay the pipe under paved runways-taxiways, it was therefore necessary to cut the existing paved surface, dig the trench, install the pipe, backfill the trench to the bottom of the the previous pavement slab, restore the pavement surface or somehow fill the void up to the surrounding top surface of the existing pavement on which to put the leveling course, if required, and the asphaltic concrete wearing course.

Our controversy narrows down to whether the space 3 formerly occupied by the pre-existing paved slab thus removed to cut the trench was a “backfill” to be done by Subcontractor as a part of his contract for installation of the drainage system, or was, on the other hand, part of the work reserved by Contractor.

The Contractor contends that since the written agreement 4 prescribed that Subcontractor would, among other things *260 not involved here, furnish all materials, labor and equipment necessary to “complete * * * in all respects as is therein required of the Contractor * * * all work incidental * * * ” to “(3) The complete drainage system * * * ” less specified items, this had the effect of making Subcontractor obliged to do all that which the specifications, Section 5 “Drainage System,” outlined in detail. Specifically, Contractor asserts, these specifications prescribed the type of backfill 5 required and put the responsibility, formerly on Contractor as between it and the Navy, on the shoulders of Subcontractor.

While the use of parol evidence is not permitted to create ambiguities, Knabb v. Reconstruction Finance Corp., 144 Fla. 110, 197 So. 707, 715; Highway Construction Co. v. City of Miami, 5 Cir., 126 F.2d 777; Restatement, Contracts, §§ 230, 231, so that such uncertainties may thereafter be eradicated by more of the same kind of evidence, the process of interpreting a series of written documents as complex as the intricate assortment of plans, drawings and specifications covering a major industrial construction project is not merely the simple task of picking out and then applying words literally in their normal connotation. There is a preliminary matter of understanding at least enough of the setting to have assurance that the words employed by parties in a technical undertaking are read in the light of that activity. Baker v. Nason, 5 Cir., 236 F.2d 483, 491; Petroleum Financial Corp. v. Cockburn, 5 Cir., 241 F.2d 312, 317; Fidelity-Phenix Fire Insurance Co. v. Farm Air Service, Inc., 5 Cir., 253 F. 2d 407. With this approach, and in the absence of a specific definition of some terms, notably “trench” and “subgrade,” we think the District Court was right in concluding that this contract was sufficiently unclear as to warrant the receipt of evidence of the negotiations, contemporaneous understandings and the subsequent actions of the parties which stamp their own construction on the agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
255 F.2d 257, 1958 U.S. App. LEXIS 5212, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rea-construction-company-and-aetna-casualty-and-surety-company-v-b-b-ca5-1958.