Franklinville Realty Co. v. Arnold Const. Co.

120 F.2d 144, 1941 U.S. App. LEXIS 3443
CourtCourt of Appeals for the Fifth Circuit
DecidedJune 3, 1941
DocketNo. 9801
StatusPublished
Cited by6 cases

This text of 120 F.2d 144 (Franklinville Realty Co. v. Arnold Const. Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Franklinville Realty Co. v. Arnold Const. Co., 120 F.2d 144, 1941 U.S. App. LEXIS 3443 (5th Cir. 1941).

Opinion

McCORD, Circuit Judge.

Arnold Construction Company, a Florida corporation, brought suit against Franklin-ville Realty Company, a Pennsylvania corporation, to enforce a contractor’s lien against certain lands in Palm Beach County, Florida, under the provisions of the Uniform Mechanic’s Lien Act of Florida, Compiled General Laws of Florida, Perm. Supp., Vol. 4, Sec. 5396(1) et seq., Chapt. 17097, General Laws of Florida, 1935. On July 19, 1939, the court entered an order of reference as provided by Rule 53 of the Rules of Civil Procedure for District Courts, 28 U.S.C.A. following section 723c. About twenty hearings were held before the Special Master, who filed his report on July 30, 1940. After a hearing on the report and exceptions filed by the defendant, the court referred the matter back to the Special [146]*146Master for further findings of fact. The Special Master filed his supplemental report on October 29, 1940, and after a hearing the court confirmed the report with few minor changes. Thereupon judgment was entered for the plaintiff and Franklinville Realty Company appealed.

The record reveals that Arnold Construction Company and R. B. Strassburger, president of Franklinville Realty Company, entered into negotiations on or about March 7, 1937, for the construction of an elaborate beach house in Palm Beach. On March 8, 1937, Strassburger and Arnold visited the property and Strassburger instructed Arnold to go right ahead with the job. Although the parties at first agreed that Arnold Construction Company was to do the work upon the basis of cost plus a ten per cent contractor’s fee, this agreement was altered by an exchange of letters between Strassburger and Arnold on March 19th and 24th whereby Arnold agreed to construct the development according to plans and specifications prepared by Strassburger’s architects, Treanor & Fatio, for a total fee of $3,000.00 “above all costs involved in the construction of the project mentioned.” Actual construction was commenced on the project shortly after March 24, 1937, and the two letters above mentioned constituted the only written agreement between the parties until May 5, 1937, when Arnold signed a written contract with Franklinville Realty Company.

Between March 24th and May 5th Arnold Construction Company proceeded to make verbal contracts with sub-contractors for electrical wiring, plumbing, millwork, and masonry, according to the completed plans and specifications available, and by May 5th a considerable amount of work had been done by sub-contractors. On April 29th Kite, the secretary of Franklinville Realty Company, advised Arnold by telegram that the company’s representative would arrive in Palm Beach the following Sunday morning relative to the “Strassburger job”. On May 3, 1937, George M. Hitchcock arrived in Palm Beach with letters of introduction from Strassburger and Kite. The letters were addressed to the architects, Treanor & Fatio. The letter from Strassburger was dated April 25, 1937, and stated: “This will serve to introduce to you Mr. G. M. Hitchcock who represents the Franklinville Realty Company.” The letter from Kite

bore date of April 28, 1937, and stated: “This will introduce to you Mr. George M. Hitchcock who has been designated by the Franklinville Realty Company to work with you on the construction of Mr. Strassburger’s beach house. Mr. Plitchcock has been working for this company since its inception. Both Mr. Strassburger and I have utmost confidence in his ability, and will thank you to extend every courtesy to him during his visits to Palm Beach. He will verbally explain to you the various changes and the progress of the work as desired by Mr. Strassburger.”

W. H. Arnold, vice-president of Arnold Construction Company, called at the offices of the architects and read the letters of introduction from Strassburger and Kite. Arnold and Hitchcock conferred with each other, and Hitchcock delivered to Arnold a copy of the proposed construction contract he had brought with him. Arnold discussed the contract with his attorney, certain additions were made, and it was signed by Arnold on May 5th. Hitchcock took the contract to Pennsylvania where it was signed by Kite for the Realty Company. The contract was returned to Arnold about two weeks later. Prior to the signing of the contract and on April 28, 1937, Strassburger sailed for France, where he remained for several months.

After execution of the contract, work continued on the job, and Hitchcock, who was a graduate architect, supervised the construction, made suggestions, conferred with the architects and contractor from time to time, and according to the testimony of Arnold and the architects, he inspected the various sub-contracts as they were received, and approved and passed on them. There is testimony that the subcontracts let by Arnold Construction Company were approved by the architects, and that all contracts let after May 5th were let with the knowledge and approval of Hitchcock. Hitchcock admitted that he knew sub-contractors were on the job, but he denied that he knew the amount of subcontracts until after June 21, 1937.

In accordance with the contract, requisitions were presented to the architects by Arnold Construction Company. The statements were checked, and architect’s certificates were issued, and Franklinville Realty Company made payments to Arnold from time to time as provided by the contract. However, payments by the owner later fell behind, and on June 22, 1937, [147]*147Arnold Construction Company sent a cable to Strassburger in Paris, Prance, advising him, “We have at present time twenty thousand dollars in money in your job and outstanding obligations to all subcontractors for a considerable sum of money.” Thereafter on June 24th Kite advised Arnold that he had heard from Strassburger and that “he will forward you on July 1st a substantial payment on your expenditures for beach house.” On June 30th Strassburger advised Arnold that he was instructing Kite to make a payment of $20,-000 on July 1st. The $20,000 payment was made, and part of this sum was used by Arnold to pay sub-contractor’s bills for labor and materials.

Strassburger, becoming displeased at the mounting costs of his house, ordered the job shut down in July, 1937, and in August directed that it be boarded in. Architect’s certificates for the job through the shut down date aggregated $53,129.50, as compared with payments ox $30,500 made by Franklinville to Arnold. Using these figures and allowing certain credits to the owner the Special Master determined the defendant’s liability to Arnold to be $20,-805.89. With a few minor exceptions the court approved the findings and conclusions of the Special Master and added to the amount found to be due certain items of interest and allowed a total recovery of $26,253.18.

The appellant insists that the court erred in sustaining the report of the Special Master, and contends that the sub-contracts “were not approved and let directly by the owner and plaintiff cannot recover therefor since it did not comply with Article 10 of the contract.” Appellant relies upon that portion of Article 10 of the contract which provides: “Separate Contracts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ace Electric Supply Co. v. Terra Nova Electric, Inc.
288 So. 2d 544 (District Court of Appeal of Florida, 1973)
L & A Contracting Co. v. Oxley
261 F. Supp. 469 (N.D. Oklahoma, 1966)
Lehigh Structural Steel Co. v. Joseph Langner
43 So. 2d 335 (Supreme Court of Florida, 1949)
Franklinville Realty Co. v. Arnold Construction Co.
132 F.2d 828 (Fifth Circuit, 1943)
In re Central of Georgia Ry. Co.
47 F. Supp. 786 (S.D. Georgia, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
120 F.2d 144, 1941 U.S. App. LEXIS 3443, Counsel Stack Legal Research, https://law.counselstack.com/opinion/franklinville-realty-co-v-arnold-const-co-ca5-1941.