Lehigh Structural Steel Co. v. Joseph Langner

43 So. 2d 335, 1949 Fla. LEXIS 1048
CourtSupreme Court of Florida
DecidedNovember 1, 1949
StatusPublished
Cited by8 cases

This text of 43 So. 2d 335 (Lehigh Structural Steel Co. v. Joseph Langner) is published on Counsel Stack Legal Research, covering Supreme Court of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lehigh Structural Steel Co. v. Joseph Langner, 43 So. 2d 335, 1949 Fla. LEXIS 1048 (Fla. 1949).

Opinion

The order of the lower court which this court is asked to review was entered in a proceeding below wherein the plaintiff Lehigh Structural Steel Company, petitioner here, sought to foreclose its lien for materials alleged to have been furnished for the construction of three buildings — one on each of three separate parcels of land, hereinafter referred to as Parcels A, B and C. The bill of complaint, as amended, joined as parties defendant the fee simple title owners of said property, the three corporate lessees of same, the general contractor employed by said lessees to construct the buildings, and the holder of escrow funds deposited for the construction of the buildings.

The facts, as alleged by the amended bill of complaint, are in substance as follows:

The three parcels of land are owned by the respondents Betty Roney Fitzpatrick and her husband, and are under 99-year leases to three corporations, as follows: Parcel A to the Glenwood Corporation; Parcel B to the Fremont Corporation; and Parcel C to the Pan American Lincoln Road Arcade, Inc. The leases, it is alleged, "called for" the erection of a building by each of said corporate lessees on its respective parcel, and required the deposit in escrow by the lessee of sufficient money to pay for the construction of same. The three corporate lessees engaged the same general contractor, to wit, Joseph Langner, Inc., to construct the buildings, and the general contractor entered into a contract with the plaintiff-petitioner for the fabrication of steel for the three buildings. The steel for all three buildings was specially fabricated by plaintiff, but only that fabricated for the building on Parcel A was actually delivered and incorporated into the structure. The remainder is stored at Allentown, Pa., "awaiting shipping instructions," as alleged in the Claim of Lien filed by plaintiff, or, as alleged in the Notice of Intention to Claim a Lien, "delivery of further materials covered by said contracts is ready to be made and furnished at any date upon which the contractor shall comply with the terms and provisions and conditions of said contracts." The amounts claimed to be due and for which the liens were sought to be foreclosed are approximately as follows: Parcel A, $5,000; Parcel B, $9,000; and Parcel C, $57,000. *Page 337

The bill of complaint attached as exhibits a copy of a Notice of Intention to Claim a Lien directed by the plaintiff to the Fremont Corporation, the Glenwood Corporation, and the Fitzpatricks (but not to the Pan American Lincoln Road Arcade, Inc.), as well as a copy of a Claim of Lien which was duly filed and recorded in the Public Records of Dade County, Florida. Neither the Notice of Intention to Claim a Lien nor the Claim of Lien described the property designated herein as Parcel C, (which, as has been noted, was leased to the Pan American concern), although the Claim of Lien included a claim for the materials in the amount of approximately $57,000 designated as for "Building C."

The holder of the escrow funds, namely, the National Title Company, filed its Answer in the cause, alleging that escrow funds in the amount of $52,000 had been deposited with it for the construction of a building on Parcel A, of which almost $5,000 remained; and that a similar amount had been deposited with it for the construction of a building on Parcel B, of which $2,700 remained; that no other escrow funds were now held by the said defendant, the National Title Company.

The other defendants filed motions to dismiss the bill of complaint; and, upon hearing on said motions, the lower court dismissed the bill as to Parcels B and C, on the ground that the plaintiff had not "furnished or incorporated or stored on the site of the premises or delivered at the site of the premises any of the material involved in the claim" and that "regardless of any common law action which the plaintiff might have against the contractor for breach of contract, there is no statutory lien which could be held against the owner of the fee simple title, who is not alleged to have entered into the contract or guaranteed the contract personally." It is this order which this court is asked to review.

The petitioner has posed the following question for adjudication by this court:

"Does a material-man have a lien for structural steel that is completely fabricated for a building although it is not delivered or erected, but is stored awaiting shipping instructions from the general contractor?"

The respondents, Betty Roney Fitzpatrick and E.J. Fitzpatrick, her husband, have re-phrased the question, as follows:

"Can a materialman have a lien upon the lessor's interest in Florida land for materials which are specially fabricated for a building pursuant to a contract between the materialman and general contractor to be erected upon the land by the lessee, pursuant to a contract between the lessee and the general contractor, when the lessor has not contracted directly with the materialman and when the materials have never been delivered upon the land and are still held by the materialman in Pennsylvania?"

No brief was filed on behalf of the corporate lessees, the general contractor, or the National Title Company.

The pertinent provisions of our Mechanics' Lien Law, being Chapter 84, Florida Statutes, 1941, F.S.A. are as follows:

Section 84.02:

"A contractor, sub-contractor, materialman or laborer shall * * * have a lien on the real property improved for any money that shall be owing to him for * * * materials furnished in accordance with his contract and with the direct contract * * *."

Section 84.01:

"`Furnish materials' means supply materials which are incorporated in the improvement * * *; or specially fabricate materials for incorporation in the improvement; * * *. The delivery of materials to the site of the improvement shall be prima facie evidence of incorporation of such materials in the improvement."

Section 84.03(2):

"* * * such liens shall extend to, and only to, the owner's right, title or interest existing at the time of the visible commencement of operations * * *. When an improvement is made by a lessee, in accordance with a contract between such *Page 338 lessee and his lessor, liens shall extend also to the interest of such lessor."

"`Owner' means the owner of real property or any interest therein who enters into a contract for the improvement of such real property * * *."

Section 84.31:

"The liens provided by this chapter may be enforced against the real property specified in the claim of lien and which is subject thereto and against any person liable for the debt upon which the lien is founded."

At the outset, it may be stated that the bill of complaint has failed to allege sufficient facts to show the existence of a lien against Parcel C, since it affirmatively appears that only Parcels A and B were "specified in the claim of lien." Section 84.31, supra. Strict compliance with the statute is required in order to acquire a lien upon the property. Buker v. Webster,140 Fla. 471, 191 So. 835.

As to Parcel B, however, the question is not so easily resolved.

The steel for the building on Parcel B was specially fabricated for such building and, it is to be presumed, is not generally suited for nor readily adaptable to use in any other building. While there is some conflict in the decisions, in our opinion the better view is that the real property proposed to be improved by specially fabricated materials is subject to a lien for such materials when their use or delivery is prevented by the act or direction of the owner of such real property and without the fault of the materialman.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stunkel v. Gazebo Landscaping Design, Inc.
660 So. 2d 623 (Supreme Court of Florida, 1995)
Oolite Industries, Inc. v. MILLMAN CONST. CO.
501 So. 2d 655 (District Court of Appeal of Florida, 1987)
Hollostone Co. v. Klements
19 Fla. Supp. 11 (Miami-Dade County Circuit Court, 1961)
State ex rel. Westinghouse Electric Corp. v. Clutter Construction Corp.
132 So. 2d 21 (District Court of Appeal of Florida, 1961)
Ideal Roofing & Sheet Metal Works, Inc. v. Katzentine
127 So. 2d 116 (District Court of Appeal of Florida, 1961)
Anderson v. Sokolik
88 So. 2d 511 (Supreme Court of Florida, 1956)
Tremont Company v. Paasche
81 So. 2d 489 (Supreme Court of Florida, 1955)
Surf Properties v. Markowitz Bros.
75 So. 2d 298 (Supreme Court of Florida, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
43 So. 2d 335, 1949 Fla. LEXIS 1048, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lehigh-structural-steel-co-v-joseph-langner-fla-1949.