Stunkel v. Gazebo Landscaping Design, Inc.

660 So. 2d 623, 20 Fla. L. Weekly Supp. 479, 1995 Fla. LEXIS 731, 1995 WL 273933
CourtSupreme Court of Florida
DecidedMay 11, 1995
Docket84075
StatusPublished
Cited by12 cases

This text of 660 So. 2d 623 (Stunkel v. Gazebo Landscaping Design, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stunkel v. Gazebo Landscaping Design, Inc., 660 So. 2d 623, 20 Fla. L. Weekly Supp. 479, 1995 Fla. LEXIS 731, 1995 WL 273933 (Fla. 1995).

Opinion

660 So.2d 623 (1995)

Sheldon E. STUNKEL, et al., Petitioner,
v.
GAZEBO LANDSCAPING DESIGN, INC., Respondent.

No. 84075.

Supreme Court of Florida.

May 11, 1995.
Rehearing Denied September 21, 1995.

Steven E. Stark and William R. Clayton, Fowler, White, Burnett, Hurley, Banick & Strickroot, P.A., Miami, for petitioner.

*624 Robert E. Ferencik, Jr., and David H. Brodie, Leiby, Ferencik, Libanoff and Brandt, P.A., Fort Lauderdale, for respondent.

HARDING, Justice.

We have for review a district court decision certifying the following question to be of great public importance:

DOES A SUBCONTRACTOR BEGIN TO FURNISH SERVICES, FOR THE PURPOSE OF TIMELY PROVIDING A NOTICE TO OWNER IN ACCORDANCE WITH SECTION 713.06(2)(a), FLORIDA STATUTES (1991), WHEN, WITHOUT ANY BINDING CONTRACTUAL OBLIGATION TO DO SO, HE OR SHE BEGINS TO SELECT MATERIALS AT SOME LOCATION OFF THE JOB SITE, FOR FUTURE INSTALLATION ON THE JOB SITE?

Gazebo Landscape Design, Inc. v. Bill Free Custom Homes, Inc., 638 So.2d 87 (Fla. 4th DCA 1994). We have jurisdiction based on article V, section 3(b)(4) of the Florida Constitution.

We answer the certified question in the negative because a binding contract is necessary to file a mechanic's lien. We also hold that the forty-five-day period for giving notice to the owner of a possible lien claim under section 713.06, Florida Statutes (1991), starts when a subcontractor begins to furnish services or materials at the job site.

I. FACTS

Sheldon and Sally Stunkel contracted with Bill Free Custom Homes, a general contractor, for the construction of a home on their property. The contractor then orally contracted with Gazebo Landscaping Design, Inc., a landscaping subcontractor, to plant trees selected by the Stunkels. On November 7, 1990, the Stunkels flew with a Gazebo representative on the Stunkels' private plane to inspect trees at Turner Tree and Landscape near Tampa. The Stunkels selected and tagged several trees for Gazebo to deliver and plant. On December 5, 1990, Gazebo workers dug holes on the Stunkels' property in preparation for planting the trees. Two days later, on December 7, Gazebo planted the trees sent from Turner Tree and Landscape.

Gazebo tried unsuccessfully to notify the Stunkels on January 15, 1991, of an impending claim of lien. On January 18, 1991, Gazebo posted a notice to owner on the gate of the Stunkel residence. Section 713.06(2)(a) requires a notice to owner to be posted within forty-five days after a subcontractor begins to furnish services or materials.[1] Thus, the time of commencement — either when the Stunkels traveled with Gazebo representatives on their plane to select trees or when Gazebo actually began work at the Stunkels' residence — is critical to whether Gazebo timely posted its notice to owner.

Gazebo filed suit on February 11, 1992, against the Stunkels and the contractor for breach of contract and to foreclose its claim of lien. A bankruptcy proceeding stayed the claim against the contractor. Trial began on September 17, 1992, with the Stunkels as sole defendant. After Gazebo presented its case, the trial court entered an involuntary dismissal against Gazebo's claim of lien after finding that Gazebo did not serve the Stunkels with a notice to owner within forty-five days after commencing to furnish services or materials, as required by section 713.06(2)(a). Because of the involuntary dismissal at the close of Gazebo's case, the Stunkels did not present any evidence.

Gazebo appealed, and the Fourth District Court of Appeal reversed the trial court's *625 ruling. The district court noted that there was no authority either to support the trial court's conclusion that Gazebo began furnishing services to the Stunkels when a representative went with the Stunkels to select trees or for concluding that a contractor does not begin to furnish services until its employees actually begin to work at the job site. Gazebo, 638 So.2d at 89. The court distinguished Arlington Lumber & Trim Co. v. Vaughn, 548 So.2d 727 (Fla. 1st DCA 1989), which held that the time for a material supplier to notify an owner about a possible lien begins to run when the contractor purchases materials over-the-counter. Gazebo, 638 So.2d at 88-89. The district court reasoned that Arlington dealt with the provision of materials by a material supplier and this case concerns the provision of services by a subcontractor. Id.

The district court reversed the circuit court's entry of an involuntary dismissal, stating that there were triable issues when the court considered the facts in the light most favorable to Gazebo, the nonmoving party. Id. at 89. The district court specifically did not hold that a contractor begins to furnish services when work is performed at the job site. Id. Instead, the court suggested that the trial court consider all of the relevant factors "based on the totality of the circumstances" in determining when the subcontractor actually began to provide services. Id.

II. CERTIFIED QUESTION

The question certified to this Court asks whether subcontractors begin to furnish services when they first select materials off the job site even though there is no binding contractual obligation to do so. A contract is essential to a mechanic's lien. See Viking Communities Corp. v. Peeler Constr. Co., 367 So.2d 737, 739 (Fla. 4th DCA 1979); § 713.06(1), Fla. Stat. (1991) ("[A] subcontractor ... has a lien on the real property improved for any money that is owed to him for labor, services, or materials furnished in accordance with his contract." (emphasis added)). Without a contractual obligation, a subcontractor cannot bring a claim of lien against the owner. Thus, we answer the certified question in the negative.

We also take this opportunity to clarify that a subcontractor begins to furnish services or materials for the purpose of giving notice to the owner under section 713.06(2)(a) when the services or materials are delivered to the job site.[2] We reject the district court's suggestion of a "totality of the circumstances" test, see Gazebo, 638 So.2d at 89, because that test would not provide certainty about when the forty-five-day period begins to run.

In reaching this conclusion, we are guided by principles of statutory construction. Mechanic's lien law is a creature of statute and must be strictly construed. Aetna Casualty and Sur. Co. v. Buck, 594 So.2d 280, 281 (Fla. 1992). Section 713.01 defines both "commencement of the improvement" and "improvement."[3] When read together, these two definitions suggest that the legislature intended commencement to begin when services or materials are furnished at the job *626 site because the statute allows liens only for services or materials that improve specific real property.

In addition, we note that mechanic's lien law serves at least two purposes. First, mechanic's liens protect suppliers who furnish labor or materials to the property by assuring them of full payment. Prosperi v. Code, Inc., 626 So.2d 1360, 1362 (Fla. 1993) (citing Emery v. International Glass & Mfg., Inc., 249 So.2d 496, 500 (Fla. 2d DCA 1971)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Snell v. Mott's Contracting Services, Inc.
141 So. 3d 605 (District Court of Appeal of Florida, 2014)
Premier Finishes, Inc. v. Maggirias
130 So. 3d 238 (District Court of Appeal of Florida, 2013)
Stock Building Supply of Florida, Inc. v. Soares Da Costa Construction Services, LLC
76 So. 3d 313 (District Court of Appeal of Florida, 2011)
Trytek v. Gale Industries, Inc.
3 So. 3d 1194 (Supreme Court of Florida, 2009)
W.W. Plastering, Inc. v. Chism Construction Inc.
867 So. 2d 600 (District Court of Appeal of Florida, 2004)
Gulfside Properties Corp. v. Chapman Corp.
737 So. 2d 604 (District Court of Appeal of Florida, 1999)
Florida Wood Services, Inc. v. Osprey Links Joint Venture
720 So. 2d 591 (District Court of Appeal of Florida, 1998)
Zalay v. Ace Cabinets of Clearwater, Inc.
700 So. 2d 15 (District Court of Appeal of Florida, 1997)
American Rural Cellular, Inc. v. System Communication Corp.
939 P.2d 185 (Court of Appeals of Utah, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
660 So. 2d 623, 20 Fla. L. Weekly Supp. 479, 1995 Fla. LEXIS 731, 1995 WL 273933, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stunkel-v-gazebo-landscaping-design-inc-fla-1995.