Florida Wood Services, Inc. v. Osprey Links Joint Venture

720 So. 2d 591, 1998 Fla. App. LEXIS 13166, 1998 WL 727352
CourtDistrict Court of Appeal of Florida
DecidedOctober 16, 1998
DocketNos. 97-2480, 97-2503
StatusPublished
Cited by3 cases

This text of 720 So. 2d 591 (Florida Wood Services, Inc. v. Osprey Links Joint Venture) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Florida Wood Services, Inc. v. Osprey Links Joint Venture, 720 So. 2d 591, 1998 Fla. App. LEXIS 13166, 1998 WL 727352 (Fla. Ct. App. 1998).

Opinion

PETERSON, Judge.

Florida Wood Services, Inc. (FWS), a materialman who furnished lumber and hardware to JM Construction Co., Inc. (JM), a subcontractor who was to perform framing and rough carpentry on a construction project, appeals the trial court’s discharge of its claim of lien. We reverse.

Osprey Links Joint Ventures (Osprey), the appellee and owner of the property against which FWS’s claim of Ken was filed, contracted with Royal American Construction, Inc. (RAC), a general contractor, to construct an apartment complex. RAC obtained the services of JM who began to perform while obtaining supphes from FWS. FWS timely and correctly served its Notice to Owner pursuant to section 713.06, Florida Statutes (1995). JM failed to complete the framing and rough carpentry, after having been paid $573,027.50, and failed to pay FWS all that it was owed for lumber and hardware furnished to the project. FWS then recorded its claim of Ken for $467,123.48 as aKowed by Section 713.08, Florida Statutes (1995).

Osprey then attempted to invoke the Notice of Recommencement provisions of Section 713.07(4), Florida Statutes (1995), by recording in the pubKc records an “Affidavit of Partial Abandonment and Intent to Recommence Construction” and a “Notice of Partial Commencement” relating only to the framing and rough carpentry portion of the project. The total amount ultimately paid by RAC to JM and others to complete the framing and rough carpentry was $2,677,435.65. JM’s contract with RAC was for $1,950,000. Osprey claims it should be reKeved of FWS’s claim of Ken because the amount remaining unpaid on the RAC-JM subcontract, $1,376,-972.50 ($1,950,000 — 573,027.50), should be offset against the cost of completion thereby leaving no funds with which to pay FWS’s claim.

When FWS sought to foreclose its lien, Osprey’s motion to discharge FWS’ claim of Ken was granted. The trial court found:

1. Osprey and RAC had a “common identity” because they were related entities. Therefore, Osprey was in direct privity with JM and could not be required to pay more than the contract price with JM, to wit: $1,950,000 to complete the framing and rough carpentry.
2. Osprey compKed with section 713.07(4), Florida Statutes (1995), by recording the Affidavit of Partial Abandonment and Intent to Recommence Construction.
3. Because Osprey had to pay more than the original price established in the contract price between RAC and JM to complete the framing and rough carpentry, no further obKgation existed to pay Kenors for unpaid claims.
4. FWS failed to properly respond to a request for a sworn statement of account pursuant to section 713.16(2), Florida Statutes (1995) and its president failed to observe the formaKties of giving the oath in that statement. The deficiency rendered void the earKer claim of Ken.

In an imaginative attempt to eompKcate a simple construction Ken dispute, Osprey argued successfully to the trial court that because Osprey and RAC were related, and shared a common identity, Osprey was in privity with JM. This concept formed the foundation for the next step of the argument.

[593]*593Osprey, now in privity with JM, could invoke the recommencement provisions of subsection 713.07(4), Florida Statutes (1995), file its “Notice of Partial Recommencement”, and eliminate any obligations to FWS because the cost of completing the framing and rough carpentry after JM defaulted was in excess of the original contract with JM. Osprey relied upon subsection 713.06(1), Florida Statutes (1995), in concluding that it could not be responsible to FWS for its $467,124 claim of lien. We admire the imagination used to formulate this concept but decline the invitation to adopt it, given its total lack of statutory or case law support.

A. COMMON IDENTITY

Osprey argues that it should be treated as having a direct contract with JM because it had a “common identity” with RAC, based on Aetna Casualty & Surety Co. v. Buck, 594 So.2d 280 (Fla.1992), rev. denied, 639 So.2d 976 (Fla.1994), and accordingly, is in privity with JM and entitled to offset based on the liability limits of the RAC-JM contract price.

In Aetna, the president and sole shareholder of both the owner and general contractor were the same individual. A materi-alman’s claim of lien was served only upon the general contractor and not the owner. The court ruled that service of the lien only on the general contractor constructively provided notice to the owner of the claim. See also C.L. Whiteside & Associates Constr. Co., Inc. v. Landings Joint Venture, 626 So.2d 1051 (Fla. 4th DCA 1993). The court also concluded that the constructive service rendered the claim effective because the owner and contractor had a common identity, to wit: the same individual is the president and sole shareholder of the two entities. This common identity concept was established in order to allow a lienor, who serves notice to an individual serving in a dual corporate capacity for both the owner and general contractor, to enforce its lien when no prejudice exists for failing to serve the owner. We do not find the concept of common identity applicable where as here, its use by the related parties who chose to make themselves separate entities would defeat the claim of a materialman who diligently and accurately followed the construction lien law. Such an inequitable result would frustrate the rationale behind the concept of common identity, i.e., to prevent the related parties from reaping a windfall.

B. RECOMMENCEMENT

Subsection 713.07(4), Florida Statutes (1995), provides:

713.07 Priority of Liens.—
(4) If construction ceases before completion and the owner desires to recommence construction, he may pay all lienors in full or pro rata in accordance with s. 713.06(4) prior to recommencement in which event all liens for the recommenced construction shall take priority from such recommencement; or the owner may record an affidavit in the clerk’s office stating his intention to recommence construction and that all lienors giving notice have been paid in full except those listed therein as not having been so paid in which event 30 days after such recording, the rights of any person acquiring any interest, lien or encumbrance on said property or of any lienor on the recommenced construction shall be paramount to any lien on the prior construction unless such prior lienor records a claim of lien within said 30-day period. A copy of said affidavit shall be served on each lienor named therein. Before recommencing, the owner shall record and post a notice of commencement for the recommenced construction, as provided in s. 713.13.

Even if we were to find Osprey’s common identity/privity argument persuasive, we interpret subsection 713.07(4) as prescribing a procedure that may be invoked when the owner has contracted with a general contractor and the entire construction project ceases, not when only a portion of the project ceases upon the default of a subcontractor not in privity with an owner. Throughout this “partial recommencement procedure” employed by Osprey, RAC never defaulted but continued to act as general contractor under its original contract with Osprey. The only difference before and after the “recommencement” in this case was that a different [594]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marble Unlimited, Inc. v. Weston Real Estate Investment Corp.
125 So. 3d 286 (District Court of Appeal of Florida, 2013)
Stock Building Supply of Florida, Inc. v. Soares Da Costa Construction Services, LLC
76 So. 3d 313 (District Court of Appeal of Florida, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
720 So. 2d 591, 1998 Fla. App. LEXIS 13166, 1998 WL 727352, Counsel Stack Legal Research, https://law.counselstack.com/opinion/florida-wood-services-inc-v-osprey-links-joint-venture-fladistctapp-1998.