Lillis v. Anderson

21 So. 2d 389, 1945 La. App. LEXIS 323
CourtLouisiana Court of Appeal
DecidedMarch 12, 1945
DocketNo. 17922.
StatusPublished
Cited by28 cases

This text of 21 So. 2d 389 (Lillis v. Anderson) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lillis v. Anderson, 21 So. 2d 389, 1945 La. App. LEXIS 323 (La. Ct. App. 1945).

Opinion

Plaintiff Eugene J. Lillis, operating under the trade name Brandin Slate Company, is engaged in the contracting business in the city of New Orleans. The defendants, Jeff R. Anderson and Annie Anderson (a colored preacher and his wife), are the owners of the real property designated as No. 1411 South Dorgenois Street, New Orleans. On August 29, 1941, plaintiff, acting through one of his salesmen, entered into a written contract with the defendants wherein he agreed to make certain alterations and improvements to defendants' property for the price and sum of $900. The work to be done by the contractor *Page 390 is set forth in the agreement as follows: "Cover all outer walls with Red Blend Brick Ford-v-Neer Siding. Repair floors in one room wherever necessary. Apply Beaverboard in three rooms. Repair both galleries. Reverend Anderson is to furnish the lumber for both galleries with the exception of the posts. Take out bulge in rear of house. Reverend Anderson is to furnish the lumber for the ceiling of porches. Also level entire house. No Paint. Cover the main roof of house with Ruberoid Asbestos Shingles. Also replace bad sheathing and rafters on roof wherever necessary. * * *"

On March 23, 1942, plaintiff brought this suit against defendants to recover the price of the contract. He alleged, in substance, that he had performed all of the work provided for by the written agreement; that he is and has been ready to deliver the building and improvements to defendants free and clear of all liens, etc.; that, despite this, defendants have refused to pay the price agreed upon; that they complained that the contract had not been complied with; that, upon receipt of this complaint, he requested that defendants furnish a list setting forth the particulars upon which the complaint was based; that defendants failed to furnish such list and that, although he contends that the contract has been fully complied with, he is ready and willing to do any and everything necessary to remedy any work which has not been completed according to the agreement.

In answer to this petition, the defendants admitted the execution of the contract but denied any liability to plaintiff on the ground that he had utterly failed to perform the work required of him under the agreement. Defendants further filed a reconventional demand claiming that, since plaintiff had failed to perform the contract in accordance with the stipulations contained therein, they had suffered mental anguish for which they are entitled to damages in the sum of $750; that plaintiff has damaged their property in the performance of the work to the extent of $200 and that they are also entitled to recover $200 for attorneys' fees.

On June 11, 1942, the case proceeded to trial in the District Court on the foregoing issues and, after the court had heard the evidence of three witnesses testifying for plaintiff, it concluded that the work under the contract had not been fully performed. In these circumstances, the judge adjourned the hearing and, apparently with the consent of the litigants and their counsel, appointed a building expert to examine the premises and the work done for the purpose of ascertaining what work would be necessary to complete the job. And, since plaintiff had offered to perform any work which might be found necessary by the building expert appointed by the court, the judge permitted him to complete the work under the supervision of the expert.

In accordance with the judge's order, the building expert, Mr. Richard McCarthy of New Orleans, who was appointed by the court, visited the premises and thereafter directed the plaintiff to perform certain additional work in compliance with his agreement. On August 31, 1942, the expert reported to the Court as follows:

"Dear Judge:

I contacted both of the above litigants and made a careful inspection of the building located at 1411 S. Dorgenois St.

Upon my first visit there (August 12), found that the contract had not been complied with, as the work was not done in a proper manner.

The floors had not been properly repaired and a bulge in the rear wall not removed. The siding on the upper side of the building was loose and there were other matters requiring attention.

I felt, therefore, that the owners were justified in refusing to accept the work and resisting the payment on same.

On August 16th I spoke with Mr. Lillis and Mr. Cook of the Brandin Slate Co. and they agreed to make all necessary corrections in an effort to comply with the contract to the satisfaction of all concerned.

The floors have been repaired in all rooms. The loose siding has been renailed, the bulge of the back wall has been removed and in addition, 1 x 8 boards have been used on rear wall as cross braces which strengthen the building. Screens have been placed and other items have been completed.

In consideration of the above, it is my opinion that the work is completed in accordance with the signed agreement, and the plaintiff in this case should be paid $900.00 in full, provided, of course, that the necessary financial arrangements will be made as outlined in the contract.

Respectfully submitted,

(Signed) Richard McCarthy." *Page 391

The foregoing letter was followed by another letter of Mr. McCarthy dated September 9, 1942, reading as follows:

"Dear Judge: —

For your further information, I believe that the Brandin Slate Co., have used every effort to correct many of the defects.

In my opinion the building must have been in a run down condition before the work started.

Same being out plumb and the old lumber sprung.

A building being in the above condition any of this work done could not make a first class job.

Some of the work done is not in a neat workmanlike manner, but as above stated it is hard to make a neat job, when this condition exist.

The contractors have placed several new brick piers under house and rebuilt apprex 12. They have placed some new sills, the floors were repaired in all rooms. On the drop roof new sheathing and Roll roofing were renewed. All of these latter items are not called for in the contract.

Therefore I am sure the work on this building has helped to increase the value of same.

(Signed) Richard McCarthy Co., Inc., By G.I. Taney."

Subsequently, on October 29, 1942, the trial of the case was resumed at which time considerable evidence was heard. Mr. McCarthy, the building expert, and his foreman, one Madison, took the stand and the court itself, together with the litigants, made an inspection of the premises. Mr. McCarthy's evidence is in accord with the statements contained in his letters to the court, which are quoted hereinabove — that is, he finds that plaintiff has substantially performed the work required of him by the written agreement; that, although plaintiff has failed to level the house as he contracted to do, he has done the best that is possible in view of the previous dilapidated condition of the premises and that, while the work done cannot be regarded as a perfect job, the condition of the premises was such as to make a first-class result impossible.

At this hearing, the defendant, Annie Anderson, testified that the salesman of plaintiff induced her and her husband to sign the contract for the repair work upon the representation that the job to be performed would place their home in a first-class condition and that they would have never agreed to permit plaintiff to do the work but for this representation.

After hearing the evidence and viewing the premises, the judge was convinced that the work required of the contractor had been substantially performed and he accordingly gave judgment in plaintiff's favor for the contract price. Defendants have appealed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Factor King, LLC v. Block Builders, LLC
193 F. Supp. 3d 651 (M.D. Louisiana, 2016)
Price v. Huey Childs Builder, Inc.
426 So. 2d 398 (Louisiana Court of Appeal, 1983)
Ostrowe v. Darensbourg
369 So. 2d 1156 (Louisiana Court of Appeal, 1979)
Ryan v. Alexander
336 So. 2d 944 (Louisiana Court of Appeal, 1976)
Meador v. Toyota of Jefferson, Inc.
332 So. 2d 433 (Supreme Court of Louisiana, 1976)
Inexco Oil Co. v. Crutcher-Tufts Corp.
389 F. Supp. 1032 (W.D. Louisiana, 1975)
RO Roy & Company, Inc. v. a & W TRAILER SALES
277 So. 2d 204 (Louisiana Court of Appeal, 1973)
Prince v. Paretti Pontiac Co.
262 So. 2d 826 (Louisiana Court of Appeal, 1972)
C. H. Leavell & Co. v. Board of Commissioners
309 F. Supp. 626 (E.D. Louisiana, 1970)
Baker v. KELLER CONSTRUCTION CORPORATION
219 So. 2d 569 (Louisiana Court of Appeal, 1969)
AA Home Improvement Company v. Irwin
203 So. 2d 888 (Louisiana Court of Appeal, 1967)
U-Finish Homes, Inc. v. Lanzl
202 So. 2d 339 (Louisiana Court of Appeal, 1967)
Graham v. Lieber
191 So. 2d 204 (Louisiana Court of Appeal, 1966)
Breaux v. Co-Operative Cold Storage Builders, Inc.
187 So. 2d 1 (Louisiana Court of Appeal, 1966)
U-Finish Homes, Inc. v. Michel
183 So. 2d 101 (Louisiana Court of Appeal, 1965)
Airco Refrigeration Service, Inc. v. Fink
134 So. 2d 880 (Supreme Court of Louisiana, 1961)
Papa v. Louisiana Metal Awning Company
131 So. 2d 114 (Louisiana Court of Appeal, 1961)
Loeb v. Neilson
128 So. 2d 447 (Louisiana Court of Appeal, 1961)
Jack v. Henry
128 So. 2d 62 (Louisiana Court of Appeal, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
21 So. 2d 389, 1945 La. App. LEXIS 323, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lillis-v-anderson-lactapp-1945.