U-Finish Homes, Inc. v. Lanzl

202 So. 2d 339, 1967 La. App. LEXIS 5287
CourtLouisiana Court of Appeal
DecidedJune 30, 1967
DocketNo. 7118
StatusPublished
Cited by8 cases

This text of 202 So. 2d 339 (U-Finish Homes, Inc. v. Lanzl) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
U-Finish Homes, Inc. v. Lanzl, 202 So. 2d 339, 1967 La. App. LEXIS 5287 (La. Ct. App. 1967).

Opinion

SARTAIN, Judge.

Plaintiff, appellant here, as the owner of one certain mortgage note executed by-Harold A. Lanzl and Vada Hyman Lanzl, husband and wife, defendants, appellees, here, instituted this action for collection thereon. Plaintiff further alleges that said, note is secured by a first lien and mortgage-executed by appellees as security for said. [340]*340note. The amount sought in recovery is the sum of $12,474.70, representing the balance due on said note, together with legal interest thereon from date of judicial demand and for reasonable attorneys fees. Plaintiff further seeks recognition of its lien and privilege resulting from the aforesaid mortgage.

Defendants filed a general denial which in essence urges that the aforementioned note was not paraphed for identification with the act of mortgage nor are the note and mortgage similar in terms and conditions to the extent that one supports the other and therefore urges that said mortgage is invalid. By way of reconvention, defendants further allege that they are entitled to a substantial reduction in the amount sued upon and in addition are entitled to damages from plaintiff because of plaintiff’s breach of contract with defendants. The trial judge held that plaintiff had in fact breached its contract with defendants, reduced the amount of the note to $8,855.12 and rendered judgment in favor of plaintiff against defendants in this amount. The trial judge also held that defendants were entitled to recover from plaintiff damages in the amount of $1,585 and rendered judgment in favor of defendants in this amount. The trial judge further decreed that the purported mortgage entered into between the parties was null and void and of no effect. The judgment of the district court failed to award plaintiff attorneys fees. From this judgment plaintiff has appealed devolutively contending that the trial judge erred (1) in failing to award the full amount sued for, (2) in failing to award plaintiff reasonable attorneys fees, and (3) in failing to recognize plaintiff’s mortgage. Defendants have not answered the appeal but in brief urge the affirmation of the judgment rendered in the district court.

Under date of April 26, 1961 defendants entered into a contract with plaintiff for the construction of three “shell” homes to be located on Lots 48 and 49 of the Nidda Subdivision, situated in St. Tammany Parish, Louisiana. These three homes are respectively known as the “Suburbia”, the “Lanier Special” and the “Bayou Special”. According to the testimony the cost of the Suburbia was $3,195, the Lanier Special $2,095, and the Bayou Special $2,395, making a total of $7,685 for all three. In addition, closing costs were in the amount of $250 and $1,350 for three concrete slabs. The total costs amounted to $9,285. $500 was paid in cash, leaving a balance of $8,785 to which was added 7 years interest at 6%, or $3,689.70. The total of these sums less the cash payment amounts to $12,474.70, which is the amount stated on and represented by the note sued upon. On the same date, that is April 26, 1961, defendants signed what was purported to be a first lien and mortgage on Lot 48. The note and mortgage were to be paid in 84 monthly installments of $148.50, except that the last and final installment is in the amount of $149.20. Defendants made one payment on December 15, 1961 in the amount of $100 and refused to pay any other installments because of plaintiff’s alleged breach of contract.

Plaintiff commenced the construction of these three homes and ultimately completed the same. The Lanier Special and the Bayou Special were completed in accordance with the list of materials and respective plans. For reasons more fully stated hereinafter the Suburbia which was located on said Lot 48 was not completed in a satisfactory manner. The bulk of the testimony in this matter involves the Suburbia home and the alleged defective and improper workmanship thereon.

The trial judge held that plaintiffs by virtue of their satisfactory completion of two of the three homes had substantially complied with the overall contract but that in view of the fact that the Suburbia home was not completed in a satisfactory manner defendants were entitled to a diminution in the total contract price by the amount necessary to properly complete the third home. [341]*341We are in accord with this conclusion. The .law applicable to cases such as this is found in LSA-C.C. art. 2769 which reads as follows:

“If an undertaker fails to do the work he has contracted to do, or if he does not execute it in the manner and at the time he has agreed to do it, he shall he liable in damages for the losses that may ensue from his noncompliance with his contract.”

In the case of Aireo Refrigeration Service, Inc. v. Fink, 242 La. 73, 134 So.2d 880, on page 882, the Supreme Court of Louisiana stated:

“[1,2] The contract involved in the instant case is a building contract within the definition of Article 2756 of the LSA-Civil Code. Article 2769 is therefore controlling. Under this codal provision the law is well settled that when the contractor has substantially performed a building contract which he has breached, he is entitled in a suit on the contract to recover the contract price less whatever damages the owner may prove attributable to the breach.
[3] Substantial performance of the contract is essential to warrant the application of this rule of law. For if the breached contract has not been substantially performed, the contractor may not recover on the contract, but is limited to recovery on quantum meruit.
[4] The principal question presented in this case is whether or not there has been substantial performance so as to permit recovery on the contract. This is a question of fact. Among the factors to be considered are the extent of the defect or non-performance, the degree to which the purpose of the contract is defeated, the ease of correction, and the use or benefit to the defendant of the work performed.”

In Lillis v. Anderson, La.App., 21 So.2d 389, the difference between procedure in this type of action from that which pertains to other commutative contracts is clearly set forth, where the court stated:

“While it is the general rule that a person suing to recover on a commutative contract must allege and prove that he has fully performed his part of the engagement in order to recover, it is the well-settled jurisprudence of this state that this doctrine is without application to suits brought on building contracts. Article 2769 of the Civil Code provides: ‘If an undertaker fails to do the work he has contracted to do, or if he does not execute it in the manner and at the time he has agreed to do it, he shall be liable in damages for the losses that may ensue from his noncompliance with his contract.’
The foregoing article has been construed by the courts to mean that, where a contractor sues on a building contract and it is shown that the work delivered is defective or unfinished, the contractor is, nonetheless, entitled to recover the contract price if the defendant fails to establish the damages he has sustained by reason of the contractor’s partial default. The remedy of the owner in such cases is for a reduction in the price to an amount necessary to perfect or complete the work according to the terms of the contract. See Cairy v. Randolph, 6 La.Ann. 202; Babst v. Peritz, Orleans No. 7548 (unreported, see La. and So.Dig.) ; Berns & Bros. v. Reiss, 12 Orleans App. 126; Davidson v. McGrath, 6[5] La. App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aetna Life Insurance Co. v. Lama Trusts
674 So. 2d 1086 (Louisiana Court of Appeal, 1996)
Opinion Number
Louisiana Attorney General Reports, 1992
Simonetti v. Lovermi
546 A.2d 331 (Connecticut Appellate Court, 1988)
France v. American Bank
505 So. 2d 1175 (Louisiana Court of Appeal, 1987)
Colonial Financial Service, Inc. v. Stewart
481 So. 2d 186 (Louisiana Court of Appeal, 1985)
NAT. ROOFING & SIDING CO. v. Gulf Coast Oil Co.
422 So. 2d 204 (Louisiana Court of Appeal, 1982)
Guitreau v. Kinchen
361 So. 2d 316 (Louisiana Court of Appeal, 1978)
Burks v. Williams
246 So. 2d 690 (Louisiana Court of Appeal, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
202 So. 2d 339, 1967 La. App. LEXIS 5287, Counsel Stack Legal Research, https://law.counselstack.com/opinion/u-finish-homes-inc-v-lanzl-lactapp-1967.