Jack v. Henry

128 So. 2d 62
CourtLouisiana Court of Appeal
DecidedMarch 6, 1961
Docket5203
StatusPublished
Cited by15 cases

This text of 128 So. 2d 62 (Jack v. Henry) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jack v. Henry, 128 So. 2d 62 (La. Ct. App. 1961).

Opinion

128 So.2d 62 (1961)

William T. JACK d/b/a Jack Construction Co.
v.
Stephen G. HENRY.

No. 5203.

Court of Appeal of Louisiana, First Circuit.

March 6, 1961.

*63 White & May, Baton Rouge, for appellant.

Taylor, Porter, Brooks, Fuller & Phillips, Frank W. Middleton, Jr., Baton Rouge, for appellee.

Before ELLIS, LOTTINGER, JONES, HERGET and LANDRY, JJ.

LANDRY, Judge.

Plaintiff William T. Jack, d/b/a Jack Construction Co., a building contractor, instituted this action against defendant, Stephen G. Henry, to recover an aggregate of $2,833.65 allegedly due pursuant to the terms of a written contract wherein the former agreed to construct a residence for the latter in consideration of the price and sum of $25,293.39. The amount for which plaintiff seeks judgment herein is composed of the sum of $2,529.33, representing 10% of the contract price withheld by defendant as provided for in the agreement and the additional sum of $304.32, consisting of $44.60 premium on builder's risk insurance and $259.72 premium on the performance bond furnished by plaintiff as called for in the contract; it being plaintiff's contention responsibility for said performance bond and insurance premium is imposed on defendant according to the terms of the contract between the parties involved in this litigation.

To plaintiff's petition defendant filed an answer consisting of a general denial and reconventional demand for judgment against plaintiff in the sum of $2,871.01, representing the cost of repairing certain alleged flaws, defects and imperfections in the dwelling as well as certain expenses chargeable to plaintiff under the contract but paid by defendant.

Plaintiff filed exceptions of no right and no cause of action to defendant's reconventional demand predicating same on the ground defendant accepted the contract despite the presence of patent defects in the work and in so doing released plaintiff of all responsibility therefor. In this connection, plaintiff also contends defendant is estopped to recover the cost of repairing any defects or imperfections because defendant contributed to said defects, stood idly by permitting them to be made and subsequently prohibited plaintiff from entering the premises to effect the necessary repairs and corrections.

After a prolonged trial in the court below (resulting in a record in which 750 pages of testimony were introduced together with innumerable exhibits in the form of letters and pictures) judgment was rendered: (1) overruling plaintiff's exceptions of no right and no cause of action to defendant's reconventional demand; (2) rejecting plaintiff's claim for $304.32, representing premiums paid on builder's risk insurance and contractor's performance bond; (3) in favor of defendant on the reconventional demand in the aggregate sum of $2,210.86; (4) in favor of plaintiff and against defendant in the sum of $318.47 (said amount evidently being the difference between the retained percentage of $2,529.33 sought by plaintiff contractor and the offset allowed defendant in reconvention of $2,210.86). From said judgment plaintiff has taken this appeal.

In his brief, learned counsel for appellant complains of many alleged errors on the part of the trial court, however, in oral argument before this court esteemed counsel specifically abandoned all complaints of error save the following: (1) The failure of the trial court to sustain plaintiff's exceptions *64 of no right and no cause of action to defendant's reconventional demand; (2) The allowance of credit to defendant in the sum of $573.16 for repair of a tile porch, said item not having been contained in the reconventional demand; (3) The award to defendant in the sum of $500 for inconvenience and discomfort; (4) The allowance of credit to defendant in the sum of $570.26 to repair defective plaster; (5) Rejection of plaintiff's claim for builder's risk insurance premium in the sum of $44.60 and performance bond premium in the sum of $259.72; (6) The granting of credit to defendant in the sum of $250.93 to repair the exterior South and East brick walls and (7) Rejection of plaintiff's claim for certain extras allegedly ordered by defendant.

We shall first consider the exceptions of no right and no cause of action filed by plaintiff in opposition to defendant's reconventional demand. As previously stated, the exceptions are founded on the theory that defendant having unconditionally accepted the contract may not recover the costs of repairing patent defects therein and additionally, that defendant is estopped because he contributed to the defects, stood idly by without complaining and ultimately prevented plaintiff from entering the premises to correct the imperfections in question.

The voluminous transcript of evidence in this case reveals that defendant decided to build two homes, one for himself and one for his son, (both of which said residences were to be in approximately the $25,000 class). Plans and specifications for the homes were prepared by John F. Wilson, an architect, and submitted to various contractors for bids. Plaintiff Jack submitted the low bid for the construction of the proposed residences but all bids were rejected by defendant and negotiations then conducted with Jack for the construction of the residence to be built for the occupancy of defendant himself. Pursuant to certain telephone conversations, the price of construction of the single residence was agreed upon and a written contract for the construction thereof entered into between the parties. The contract in question provides that defendant owner specifically reserved the right of supervision and that there would be no supervision of construction by the architect.

At the outset relations between plaintiff and defendant were extremely cordial but obviously deteriorated because defendant, having retained personal supervision, demanded near perfection in the work. During the latter stages of construction (and long before defendant's formal acceptance of the contract) defendant wrote plaintiff numerous letters complaining bitterly of various alleged flaws and defects in the work. The tone of said letters indicated clearly defendant's progressive irritation at the manner in which certain aspects of the construction were being performed. Following defendant's formal acceptance of the contract, plaintiff made several visits to the premises in an attempt to rectify some of the defects about which defendant complained but the feeling between the parties ultimately became so strained that upon an undisclosed date defendant denied plaintiff further access to the premises.

The obligation of a contractor to perform a work or undertaking in the manner agreed is imposed by Article 2769, LSA-R. C.C. which not only sets forth the duty of the undertaker but the liability which ensues upon his non-performance, as follows:

"Art. 2769. If an undertaker fails to do the work he has contracted to do, or if he does not execute it in the manner and at the time he has agreed to do it, he shall be liable in damages for the losses that may ensue from his non-compliance with his contract."

In interpreting the foregoing codal authority the courts of this state have repeatedly and consistently held that notwithstanding the contractor's default, where the owner derives benefit from the work, the contractor is nevertheless entitled to recover the contract price less whatever damages the owner may prove attributable to such default, the remedy of *65 the owner being a reduction in price equal to the cost of completing or repairing the work. Home Service v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mayerhofer v. Three R's Inc.
597 So. 2d 151 (Louisiana Court of Appeal, 1992)
Hancock v. Northcutt
808 P.2d 251 (Alaska Supreme Court, 1991)
State v. Wilco Const. Co., Inc.
393 So. 2d 885 (Louisiana Court of Appeal, 1981)
Seymore v. LA. SOIL STABILIZATION CO., INC.
381 So. 2d 571 (Louisiana Court of Appeal, 1980)
Ostrowe v. Darensbourg
369 So. 2d 1156 (Louisiana Court of Appeal, 1979)
Mid-State Homes, Inc. v. Bice
361 So. 2d 275 (Louisiana Court of Appeal, 1978)
Geisler v. Louisiana Power & Light Co.
346 So. 2d 339 (Louisiana Court of Appeal, 1977)
Meador v. Toyota of Jefferson, Inc.
332 So. 2d 433 (Supreme Court of Louisiana, 1976)
Hoover v. Beatty
323 So. 2d 490 (Louisiana Court of Appeal, 1975)
Charles C. Cloy, General Contractors, Inc. v. DiVincenti Brothers, Inc.
308 So. 2d 495 (Louisiana Court of Appeal, 1975)
Palmer v. Asaff
297 So. 2d 487 (Louisiana Court of Appeal, 1974)
CO-OPERATIVE C. STOR, BLDRS., INC. v. Arcadia Foods, Inc.
291 So. 2d 403 (Louisiana Court of Appeal, 1974)
Clay-Dutton, Inc. v. Plantation Nursing Home of New Orleans, Inc.
239 So. 2d 442 (Louisiana Court of Appeal, 1970)
Charest v. Busby
141 So. 2d 466 (Louisiana Court of Appeal, 1962)
Justiss-Mears Oil Company v. Pennington
132 So. 2d 700 (Louisiana Court of Appeal, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
128 So. 2d 62, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jack-v-henry-lactapp-1961.