Charles C. Cloy, General Contractors, Inc. v. DiVincenti Brothers, Inc.
This text of 308 So. 2d 495 (Charles C. Cloy, General Contractors, Inc. v. DiVincenti Brothers, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
CHARLES C. CLOY, GENERAL CONTRACTORS, INC.
v.
DIVINCENTI BROTHERS, INC.
Court of Appeal of Louisiana, First Circuit.
*496 Gordon A. Pugh and F. Charles McMains, Jr., Baton Rouge, for appellant.
W. P. Wray, Jr., Baton Rouge, for plaintiff-appellee.
Emile M. Weber, Baton Rouge, for appellee Wm. L. Bowman.
Before LANDRY, BLANCHE and NEHRBASS, JJ.
NEHRBASS, Judge.
Plaintiff, Charles C. Cloy, General Contractors, Inc. (Cloy), instituted this action against defendant, DiVincenti Brothers, Inc. (DiVincenti), to recover a $3,674.10 retainage due on a bonded building contract wherein Cloy agreed to construct a warehouse for DiVincenti for a price of $36,741.00. DiVincenti reconvened seeking damages for defects resulting from alleged improper workmanship or improper execution of the contract. DiVincenti also filed a Third Party Complaint against William L. Bowman, the project engineer, alleging alternatively that the defects complained of were caused by improper plans and specifications. Bowman reconvened against DiVincenti seeking damages for defamation and this action was dismissed on an exception of no cause of action filed by DiVincenti.
The trial court rendered judgment on the principal demand in favor of Cloy for the sum of $3,674.10 and against DiVincenti dismissing its reconventional demand against Cloy and its Third Party Demand against Bowman. Defendant, DiVincenti, has perfected this devolutive appeal from the final judgment on the principal demand and on its reconventional demand against Cloy. That portion of the judgment dismissing *497 the Third Party Demand has not been appealed, nor have Cloy and Bowman appealed.
No contested issues of law are present in the main demand. As a general rule, a party suing to recover on a commutative contract must allege and prove performance of his agreement. L.S.A.-C.C. Article 1913. However, the jurisprudence of this state is settled to the effect that upon substantial completion of a work the contractor is entitled to the value thereof as constructed; the remedy of the owner in the event of defect or imperfections therein, being the right to seek a diminution in the price to the extent of the loss or damage sustained by virtue of the contractors failure to perform the work as agreed. Justiss-Mears Oil Company v. Pennington, 132 So.2d 700 (La.App. 1st Cir. 1961); Jack v. Henry, 128 So.2d 62 (La.App. 1st Cir. 1961).
We agree with the trial judge that the facts set forth and established in the pre-trial order are sufficient to support a judgment on the main demand in favor of Cloy and against DiVincenti for the sum of $3,674.10. Plaintiff has sufficiently documented the facts with exhibits filed on the trial.
DiVincenti maintains that the trial court was in error in dismissing the reconventional demand for damages for defects resulting from improper workmanship or improper execution of the contract. In this vein, defendant maintained that the trial court was in error in holding that the signing of a formal and unqualified acceptance by the defendant operated as a waiver barring the owner from recovering damages for patent and easily discoverable defects.
On August 4, 1971, Cloy and DiVincenti entered into a building contract wherein Cloy agreed to construct a warehouse immediately south of and adjacent to an existing building owned by defendant. What was formerly the outside south wall of the old building has become the inside wall between the old and the new building, and what was formerly an outside door on the old building has become a door or passageway connecting the two buildings.
During construction, DiVincenti noticed certain clearly obvious defects which he urges as the basis of his reconventional demand for damages. His two principal complaints are that the elevation of the floor in the new building is two (2) inches higher than the floor in the old building, and that the loading and unloading ramps at the outside doors of the new building are too steep to be safely used by a lift truck. The difference in the floor elevation and the steepness of the loading ramps are alleged to cause a loss of work time in loading and unloading operations. He also alleges that the concrete floor is cracked in many places but no evidence was presented on this matter and the trial judge who observed the building noted that the minor cracks that were present did not amount to a defect.
DiVincenti also urges that certain downspouts located on the interior wall between the old and new building which served the purpose of roof drainage and which discharged into piping located beneath the slab, are not constructed in accordance with plans and specifications. These downspouts are not constructed flush against the interior wall, but are slightly offset causing some loss of floor space. It is also alleged that these interior downspouts leak during heavy rains. He also alleges that the exterior gutters are not of sufficient size to take care of drainage from the roof in heavy rain.
All of the defects of which the owner complains are clearly obvious on casual inspection. The owner testified that he noticed all of these defects and registered his complaints with Cloy's representatives on the job and with Cloy himself. In response to these complaints, and at the request of the owner, Cloy poured a small ramp inside the old building to correct the difference in floor elevation and fixed the *498 leaks in the interior downspouts. On cross-examination the owner admitted that these corrective steps were taken during the final stage of construction, and Cloy testified that construction was still in progress at that time. No further complaints were registered subsequent to the taking of these corrective measures. We believe that these corrective measures were taken prior to the acceptance of the building on November 11, 1971.
An acceptance of the building as being complete was signed by the owner on November 11, 1971, and this notice of acceptance was recorded. The owner testified that he occupied the new building on that date. On the same date, the owner made a payment to Cloy in the sum of $26,216.90 which brought the total sum paid to ninety percent (90%) of the contract price. No complaints were registered by the owner at this time, nor did he retain any additional sums for incomplete work as he had the right to do under the contract. On December 27, 1971, a certificate disclosing that no labor or material liens had been filed was issued by the East Baton Rouge Parish Clerk of Court. This certificate was subsequently presented to the owner and demand was made for the ten percent (10%) retainage due under the contract.
Defendant in reconvention, Cloy, contends that DiVincenti is precluded for recovering for defects that were known to him or which were apparent at the time he signed the affidavit of acceptance, relying on the legal principles set forth in Maloney v. Oak Builders, Inc., 224 So.2d 161 (La. App. 4th Cir. 1969) modified 256 La. 85, 235 So.2d 386 (1970):
"It is also well settled that even if the owner proves the existence of the defects or omissions and the cost of repairing them, he is nevertheless barred from recovering the cost thereof if he accepted the work despite the patent defects or imperfections discoverable upon reasonable inspection.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
308 So. 2d 495, Counsel Stack Legal Research, https://law.counselstack.com/opinion/charles-c-cloy-general-contractors-inc-v-divincenti-brothers-inc-lactapp-1975.