Southbend Contractors, Inc. v. Parish of Jefferson

408 So. 2d 1158, 1981 La. App. LEXIS 5753
CourtLouisiana Court of Appeal
DecidedDecember 22, 1981
DocketNo. 12187
StatusPublished
Cited by5 cases

This text of 408 So. 2d 1158 (Southbend Contractors, Inc. v. Parish of Jefferson) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southbend Contractors, Inc. v. Parish of Jefferson, 408 So. 2d 1158, 1981 La. App. LEXIS 5753 (La. Ct. App. 1981).

Opinion

BOUTALL, Judge.

A contractor sues for extra work allegedly done pursuant to a construction contract and the owner reconvenes for liquidated damages for delay in completion of the contract. From a judgment granting only a portion of the main demand and awarding liquidated damages on the reconventional demand, the contractor has appealed. We affirm.

Southbend Contractors, Inc., entered into a contract with the Parish of Jefferson to repair, replace and modify certain subsurface water lines within the area of East Jefferson Water District No. 1 at a price of $493,208.73. The contract provided that the contractor shall commence work within ten days from the date of the written order to proceed issued by the Parish and shall complete all work under the contract within two hundred and forty calendar days from the date of the order to proceed. The contract further provided for damages for a delay in completion of the contract at the rate of $100.00 per calendar day. The contract was not completed by the contractor in accordance with its terms and a series of discussions and negotiations were had by the Parish and the contractor in order to bring about the completion of the contract and settlement of the disputes between the parties. Finally, a partial agreement was [1160]*1160reached between the parties and the contract was finally completed, leaving the issues not agreed upon to be settled by court action. Accordingly, Southbend brought this suit for the cost of extra work done beyond the terms of the contract, and the Parish reconvened for its contractual liquidated damages for delay.

Southbend sued for slightly more than $50,000.00 contending that it incurred additional labor, equipment and material costs plus overhead as a result of differing site conditions at certain specified locations. The defense of the Parish to this claim is that much of the extra work was a result of the mistakes and errors of the contractor, that some of the work was included in the contract and the contract price payable on a unit cost basis, and that some of the work was due to the delay of the contractor itself in not diligently proceeding under the contract. The Parish conceded that there was due for extra exploratory work not covered under the contract forty six hours at $87.79 per hour equalling a total of $4,038.34. The trial judge awarded Southbend only that amount on the main demand. We agree.

The issue of whether or not the items claimed constituted extra work beyond the contract depends upon the testimony of the witnesses produced by the litigants in this case. Southbend produced the testimony of James B. Graham, Jr., President of South-bend Contractors, Inc., and Gerard J. Black, Secretary-Treasurer of Mollere-Black Services, Inc. Both of these witnesses testified in conformity with the plaintiff’s position. Opposed to this, the Parish produced the testimony of Robert E. Rice, the chief field engineer for Jefferson Parish, who was the general supervisor on the job, and Geoffrey Nordgren, who was the resident engineer with Burks and Associates, employed by the Parish for this particular project. There is a direct conflict in the testimony of these two sets of witnesses which can only be resolved by an evaluation of the credibility of the witnesses. Although the trial judge did not give reasons for judgment, it is apparent that he gave greater credibility to the witnesses produced by the Parish. During the course of the trial, he noted that there was an issue of credibility and was particularly concerned with the relationship of witness Black to the plaintiff and his participation in any amount that may be recovered by Southbend. The evidence shows that Black was an officer of the company which subcontracted the labor furnished on the job, despite the contract’s requirement that labor could not be subcontracted unless approved by the Parish, and that that company was the major participant in whatever judgment might be obtained. It is apparent that the trial judge found the credibility of the Parish’s witnesses to be stronger than the credibility of plaintiff’s witnesses and resolved the issues in favor of the Parish. Thus, there is presented to us the classic issue of “evidence before the trier of fact which, upon its reasonable evaluation of credibility, furnishes a reasonable factual basis for the trial court’s finding” established as a standard of appellate review in the case of Canter v. Koehring Co., 283 So.2d 716 (La.1973) and further explained in Arceneaux v. Domingue, 365 So.2d 1330 (La.1978). We have examined the record and we agree with the conclusion of the trial judge. Accordingly, we affirm the judgment on the main demand.

The other matter before us is the judgment on the reconventional demand in favor of the Parish awarding it liquidated damages in the amount of $36,500.00, computed at the rate of $100.00 per day for 365 days.

The appellant has assigned two specifications of error: 1) the trial court erred in holding that Southbend was liable for liquidated damages for delay in view of the fact that the Parish had made full payment under the original contract and had accepted the work as complete; 2) additionally, the trial court erred in finding that Southbend completed the work one year after the original completion date of the contract. The calendar of events shows that the completion date of the contract would have been October 24, 1977, and that the Parish, through its engineers, granted a thirty-five [1161]*1161day extension because of rain, etc., to November 28,’ 1977. On May 18, 1978, the Parish wrote a letter to Southbend notifying it that it was in default and that the liquidated damages would be imposed. This was followed on July 19, 1978, with another default letter to the same effect. On November 27, 1978, an escrow agreement was entered into between the contractor and the Parish in which the Parish agreed that the work called for in the contract had been substantially completed with the exception of installation of seven fire hydrant extensions to be installed later and that the Parish would accept the work as substantially complete, file a notice of acceptance in the mortgage records, and forty-five days later, after the clear lien and privilege certificate had been secured, the Parish would pay $41,305.35, calculated to be the balance due under the contract price minus $7,000.00 held in escrow for the completion of the fire hydrants.

Superimposed upon this calendar of events is the testimony of Southbend’s witnesses who testified that the job was substantially completed prior to April 21, 1978, when Southbend wrote a letter requesting recognition of that fact, and testimony from the Parish witnesses that some parts of the water lines were being used, and that final inspections were being made. However, the evidence is clear that the contract work was not completed at that time and that a considerable amount of installation of new items and repair of a number of old items still remained. We note for example that even as far as August 11, 1978, the contractor was involved in installing three fire hydrants and fourteen extensions, and on October 7, 1978, installed another fire hydrant and did other miscellaneous work. There still remained the seven fire hydrant extensions to be done on November 27, 1978, at the time of the escrow agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harp v. Autrey
121 So. 3d 1260 (Louisiana Court of Appeal, 2013)
Myers v. Burger King Corp.
618 So. 2d 1123 (Louisiana Court of Appeal, 1993)
Hogan v. Hogan
465 So. 2d 73 (Louisiana Court of Appeal, 1985)
Southbend Contractors, Inc. v. Parish of Jefferson
413 So. 2d 496 (Supreme Court of Louisiana, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
408 So. 2d 1158, 1981 La. App. LEXIS 5753, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southbend-contractors-inc-v-parish-of-jefferson-lactapp-1981.