Florida Ice MacHine Corp. v. BRANTON INSULATION INC.

290 So. 2d 415
CourtLouisiana Court of Appeal
DecidedFebruary 15, 1974
Docket5128
StatusPublished
Cited by8 cases

This text of 290 So. 2d 415 (Florida Ice MacHine Corp. v. BRANTON INSULATION INC.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Florida Ice MacHine Corp. v. BRANTON INSULATION INC., 290 So. 2d 415 (La. Ct. App. 1974).

Opinion

290 So.2d 415 (1974)

FLORIDA ICE MACHINE CORPORATION
v.
BRANTON INSULATION INC. and Commercial Union Insurance Company of America.

No. 5128.

Court of Appeal of Louisiana, Fourth Circuit.

February 15, 1974.

*416 Baldwin, Haspel, Molony, Rainold & Meyer, Lawrence J. Molony and Terence E. Hall, New Orleans, for plaintiff-appellee.

Jackson P. McNeely, New Orleans, for defendants-appellants.

Before SAMUEL, REDMANN and STOULIG, JJ.

SAMUEL, Judge.

Florida Ice Machine Corporation, plaintiff in this matter, was one of several general contractors engaged by New Orleans Cold Storage & Warehouse Company, Ltd., to construct a new refrigerated warehouse facility for it on the Mississippi River at the foot of State Street and Henry Clay Avenue in the City of New Orleans. Plaintiff's portion of this construction job included the plumbing, heating, air conditioning, refrigeration and insulation to be installed in the warehouse facility.

Plaintiff in turn subcontracted with Branton Insulations, Inc., the principal defendant (hereinafter referred to simply as "defendant")[1] for a portion of the insulation work, requiring it to "furnish and install Fiberglass pipe covering on refrigerant and drain lines per drawings and specifications." The subcontract was dated July 1, 1966 and the subcontract price was $24,000. Made a portion of this contract is a letter from the defendant to the plaintiff excluding from the subcontract work requirement hangers, saddles, supports, welding, and painting. While there is no written evidence showing the plaintiff consented to this exclusion from the work requirement, the conduct of the parties clearly indicates that both plaintiff and defendant regarded the subcontract to be amended by this letter.

An acceptance of the defendant's work was filed in the mortgage office on September 21, 1966, and the first indication of complaints concerning the defendant's insulation work was made on October 6, 1966.

The primary contention at the trial in the lower court was that the work done by the defendant was defective in that ice was forming on the outside of the refrigerant lines in numerous locations throughout the cold storage warehouse facility, and that these refrigerant lines were to be insulated by the defendant for the purpose of preventing the formation of such ice. In the *417 trial court the plaintiff's emphasis was on proving the defendant was guilty of poor workmanship. On appeal the emphasis in the plaintiff's argument is that, irrespective of proof or nonproof of defective workmanship, the ultimate result of the defendant's work was defective because its insulation did not in fact insulate.

After an extended trial the lower court rendered judgment in favor of the plaintiff against the defendant and its bonding company solidarily for $3,174, representing the cost of repairing a minor portion of the deficiencies complained of by the owner. In addition, the court rendered judgment in favor of the defendant on its reconventional demand and against the plaintiff for $3,327, representing $2,424 admittedly unpaid to it and an additional sum of $903 for "extras" performed by the defendant in the course of its work. From that judgment both the plaintiff and the defendants have appealed.

The contract specifications provide that a vapor barrier seal be installed regardless of the type of insulation used. The vapor barrier is specified to consist of a continuous membrane to be applied with vapor barrier adhesive, with a water vapor permeance of not than 0.1 perms. Specifications also called for a vapor barrier at all corners and expansion joints, sealing with adhesive over all leaks, tears, nail holes, bolt holes, and other perforations to provide a permeance no greater than that of the vapor barrier membrane, and the use of vapor barrier adhesive of such a nature as to afford a joint seal equal in performance to the permeance of the vapor barrier membrane.

Subsequent to the filing of the acceptance of the defendant's work in the mortgage office, numerous complaints began to develop with regard to ice forming on the insulation. The exact number of ice formations was never established, but all estimates indicate that the number was substantial, varying from 40 to 75 problems.

For approximately 15 months after the appearance of the defects, the defendant made numerous periodic trips to the owner's establishment in order to attempt to remedy them. Eventually, plaintiff obtained the services of Anco Installation of New Orleans, Inc., a related corporation, which performed work to remedy the defects at a cost of $16,056.87. Later, plaintiff used American Refrigeration Contractors, Inc., plaintiff's parent corporation, to perform repairs to the alleged pipe covering deficiencies in the amount of $4,402.28. The record is unclear with regard to exactly what work these two companies performed in order to earn the amounts paid to them.

The lower court found that no deficiencies existed in the plans and specifications and that the material used was not defective. The court further found that the plaintiff failed to prove, "by that preponderance of the evidence necessary for it to do in order to recover, that the work performed by the two contractors called in by plaintiff was made necessary because of `poor workmanship in the application of the vapor seal' as alleged, except as is hereinafter noted." The two exceptions will be discussed below.

The general nature of the defects complained of fall into two distinct categories. First, there were leaks with subsequent ice formations caused by a break in the vapor barrier at joints, elbows, and connections in the pipe. Second, there were failures in the pipe insulation at pipe hangers, apparently caused when the insulation was crushed between the weight of the pipe and the support upon which it was laid. Such a compression at hanger or support locations substantially reduced the thickness of the insulation at that spot with the result that the warm outside air condensed and froze on the cold pipe. Witnesses agreed that the breaking of an ice formation cleanly off the outside of the insulation is indicative of insufficient insulation thickness. On the other hand, they substantially *418 agreed that when ice went through the insulation it was evidence of a leak in the vapor barrier, and that such was the case where the insulation was crushed by the weight of the pipe mashing the insulation against hangers or pipe supports.

The law governing the performance of building contracts has its origin in Article 2769 of the Louisiana Civil Code, which provides:

"If an undertaker fails to do the work he has contracted to do, or if he does not execute it in the manner and at the time he has agreed to do it, he shall be liable in damages for the losses that may ensue from his non-compliance with his contract." LSA-C.C. Art. 2769.

The jurisprudence interpreting this code article has made it clear that construction contracts are treated in a different manner than other commutative contracts. In the latter there can be no recovery in the absence of full performance. In the case of construction contracts, a substantial compliance with the contract is sufficient to justify recovery of the contract price by the contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Red River Parish Port Commission v. Headwaters Resources Inc.
698 F. Supp. 2d 684 (W.D. Louisiana, 2010)
Wike v. Joseph
516 So. 2d 1236 (Louisiana Court of Appeal, 1987)
Havens Steel Co. v. Randolph Engineering Co.
613 F. Supp. 514 (W.D. Missouri, 1985)
Southbend Contractors, Inc. v. Parish of Jefferson
408 So. 2d 1158 (Louisiana Court of Appeal, 1981)
DESIGN & CORROSION ENG., INC. v. Piggly Wiggly of Mansfield, Inc.
408 So. 2d 292 (Louisiana Court of Appeal, 1981)
Foster v. Jackson
339 So. 2d 865 (Louisiana Court of Appeal, 1976)
Stephenson v. Smith
337 So. 2d 570 (Louisiana Court of Appeal, 1976)
Lane Wilson Company, Inc. v. Gregory
322 So. 2d 369 (Louisiana Court of Appeal, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
290 So. 2d 415, Counsel Stack Legal Research, https://law.counselstack.com/opinion/florida-ice-machine-corp-v-branton-insulation-inc-lactapp-1974.