Foster v. Jackson

339 So. 2d 865, 1976 La. App. LEXIS 4592
CourtLouisiana Court of Appeal
DecidedNovember 10, 1976
DocketNo. 5617
StatusPublished
Cited by5 cases

This text of 339 So. 2d 865 (Foster v. Jackson) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Foster v. Jackson, 339 So. 2d 865, 1976 La. App. LEXIS 4592 (La. Ct. App. 1976).

Opinions

HOOD, Judge.

Robert Foster instituted this suit against Jeff D. Jackson, d/b/a Jackson Mortgage Service and Construction Company, to recover the cost of repairing alleged defects in a house which defendant constructed for plaintiff. The trial court rendered judgment in favor of plaintiff for $4,885.00. Defendant appealed.

The issues presented are whether defendant failed to construct the house in accordance with the terms of the contract and in a workmanlike manner according to standard practices, and if so, what would be the cost of repairing the defects.

Foster and Jackson entered into a contract on or about March 29,1973, under the terms of which defendant agreed to construct a residence building for plaintiff for the sum of $14,350.00. The written evidence of that contract consists solely of two drawings which were prepared by Jackson and a document identified as a “Proposal.” The two drawings included a lot plan, the front elevation and the floor plan of the house. The “proposal” appears to be an offer submitted by defendant Jackson to Mr. and Mrs. Foster to: “Build house — 3 bedrooms, living room, dining room, kitchen and bathroom.”

None of those documents specified the types of materials which were to be used in any part of the house. The proposal provided, however, that “all material is guaranteed to be as specified,” and that “All work to be completed in a workmanlike manner according to standard practices.”

Although Jackson did not sign any of the above documents, the evidence shows that he prepared them and submitted them to plaintiff. Mr. and Mrs. Foster signed the “Proposal,” indicating their acceptance of the offer submitted by Jackson.

Defendant began constructing the house in July, 1973, and he completed it the latter part of September of that year. Plaintiff and his wife accepted the house, signed the necessary papers to complete first and second mortgages on it, paid defendant the full amount due on the contract, and then moved into the house in October, 1973. Plaintiff has been living in the house continuously since that time.

Mr. and Mrs. Foster testified that the first time it rained after the house was completed water seeped in under the front door and stained or damaged a part of the living room carpet. They stated that some time thereafter, from two to five months after they began occupying the building, other defects in the construction became apparent. They made some complaints to Jackson, who promptly sent workmen out to correct the alleged defects, but he apparently did not correct them to plaintiff’s satisfaction.

[868]*868This suit was filed on February 25, 1975, or about 16 or 17 months after the house was occupied by plaintiff. Plaintiff alleges in Article Six of his petition that the defects in the house consist of the following:

(1) The roof (ceiling) coming loose from the carport;

(2) The eaves of the house coming loose;

(3) Carpet in the living room being ruined due to rain leaking through the house;

(4) Water leaking in around the front door;

(5) Kitchen sink leaking;

(6) Leaks in the bathroom;

(7) Paint on the outside of the house mildewing, peeling and buckling;

(8) Grill in the heater in the bathroom broken;

(9) Molding on the kitchen and bathroom floors mildewing due to leaks from the appliances. '

Foster asserts that the above defects “began to occur in approximately March, 1974,” and that they were caused by the “poor quality of work” performed by defendant and the “poor quality of materials” used by him.

At the trial defendant objected to the introduction of any evidence which tended to enlarge the pleadings. The objection was sustained and was made general. The pleadings have not been enlarged, therefore, and we are concerned on this appeal only with the defects which are specifically alleged in plaintiff’s petition.

The only expert called by plaintiff was Nolan J. Rogers, Sr., an experienced building contractor, who examined plaintiff’s home in February, 1975, about 16 months after the Fosters had moved into it. Rogers testified that he made no attempt to determine whether the materials or workmanship were defective, but that he merely noted the things which plaintiff said he wanted done, and he gave plaintiff an estimate or a bid of the total sum which would be required for performing all of the work which plaintiff pointed out to him. Rogers testified that:

“ . . . I’m not knocking nobody’s work, no. I’m just figuring — I’m just saying what that man made me figure when I went over there. In other words, that’s what I’m stating. Only what he told me. I didn’t tell that man what he should do. He asked me to do this for him, and I wrote it down, and that’s what I figured on . .”
***** *
“I done exactly what he asked me to do.”

Rogers informed plaintiff that he would make all of the repairs which the latter pointed out to him for the total sum of $4,885.00. He did not break down that figure to show the cost of repairing any particular item "or defect, however, and he conceded that the figures he gave included some items which were not specified in plaintiff’s petition. The defendant, who also is an experienced building contractor, did not have the house examined by another expert, but he testified as to the quality of the materials used and the workmanship on the house.

The trial court found that “apparently the contractor was doing his best to give as much home as he could for the price,” but that “he ended up with a home which was unsatisfactory and defective in respects alleged by the plaintiff.” The court found the home to be defective, and he awarded plaintiff the full amount of the bid submitted by Rogers, assigning as his reasons therefor that that was “the only estimate the court has for putting the home in a condition where it should be.”

We have concluded that the trial judge erred in awarding plaintiff the full amount of the bid or estimate submitted by Mr. Rogers.

Applicable here is the rule that a party proceeding against the contractor who has substantially performed a construction contract, bears the burden of proving both the existence of the defects and the cost of repairing or finishing the [869]*869defective work. Florida Ice Machine Corporation v. Branton Insulation, Inc., 290 So.2d 415 (La.App. 4 Cir. 1974); Maloney v. Oak Builders, Inc., 224 So.2d 161 (La.App. 4 Cir. 1969). If the owner fails to present any evidence as to the cost of repairing or correcting the defective work, he will not be entitled to recover. Elite Homes, Inc. v. Herrmann, 242 So.2d 614 (La.App. 4 Cir. 1970); Federico v. Kratzberg, 163 So.2d 843 (La.App. 4 Cir. 1964).

The defendant in the instant suit substantially completed the construction of the house. The burden rests on plaintiff, therefore, to establish the defects alleged and the cost of repairing or correcting those defects.

(1) Roof (Ceiling) of Carport

Plaintiff testified that some time after he moved into the home, the material used in constructing the ceiling of the carport began to sag and to come loose. Mrs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Irby, Christopher
Court of Criminal Appeals of Texas, 2010
Consolidated Roofing & Supply Co. v. Grimm
682 P.2d 457 (Court of Appeals of Arizona, 1984)
Picard Building Corp. v. Tramonte
432 So. 2d 1151 (Louisiana Court of Appeal, 1983)
Foster v. Jackson
342 So. 2d 218 (Supreme Court of Louisiana, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
339 So. 2d 865, 1976 La. App. LEXIS 4592, Counsel Stack Legal Research, https://law.counselstack.com/opinion/foster-v-jackson-lactapp-1976.