Elite Homes, Inc. v. Herrmann

242 So. 2d 614
CourtLouisiana Court of Appeal
DecidedMarch 10, 1971
Docket3647
StatusPublished
Cited by12 cases

This text of 242 So. 2d 614 (Elite Homes, Inc. v. Herrmann) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elite Homes, Inc. v. Herrmann, 242 So. 2d 614 (La. Ct. App. 1971).

Opinion

242 So.2d 614 (1970)

ELITE HOMES, INC.
v.
Dorothy L. YOUNGBLOOD, wife of/and Harold M. HERRMANN et al.

No. 3647.

Court of Appeal of Louisiana, Fourth Circuit.

July 15, 1970.
Writ Refused November 9, 1970.
On Rehearing December 7, 1970.
Rehearing Denied January 11, 1971.
Writ Refused March 10, 1971.

*615 Morphy & Freeman, A. D. Freeman, Jr., New Orleans, for Elite Homes, Inc. and Boston Insurance Co., plaintiffs, defendants in reconvention-appellants.

David L. Morgan, Jr., New Orleans for Dorothy L. Youngblood, wife of/and Harold M. Herrmann, defendants, plaintiffs in reconvention-appellees.

Before SAMUEL, BARNETTE and DOMENGEAUX, JJ.

SAMUEL, Judge.

This suit on a $18,200 building contract was brought by the contractor against the owners and their lending institution, Dryades Savings & Loan Association, for the final two payments, totaling $5,460, allegedly due under the contract. The owners answered in the form of a general denial and reconvened against the contractor and its surety, Boston Insurance Company, for damages in the sum of $16,300 to correct alleged deficiencies, liquidated damages of $5 per day under the demurrage clause of the contract for failure to timely perform, and a ten percent attorney's fee.

Thereafter plaintiff filed third-party demands against various subcontractors and reconvenors filed two supplemental petitions increasing their demand by the sum of $12,000 for failure to grade the property. The following year reconvenors filed a third supplemental petition increasing their demand for damages to the sum of $51,459.17. At a pretrial conference plaintiff offered to buy the property for the sum of $27,100 less the outstanding indebtedness. The offer was declined.

Following trial on the merits, and after stipulation by all counsel that Dryades had acted only as an escrow agent, judgment was rendered on the main demand in favor of defendants, dismissing plaintiff's suit, and on the reconventional demand in favor of plaintiffs in reconvention and against the contractor and its surety in the sums of $4,734.18 for damages and $473.42 as an attorney's fee and expert fees in the amount of $100 for each of three experts called by plaintiffs in reconvention. The expert fees were taxed as costs to be paid by the contractor and its surety. There was also judgment in favor of the contractor on its various third-party demands against the subcontractors but, no appeal *616 having been taken therefrom, those demands are not before us. The judgment orders Dryades to apply the $5,460 it held in escrow to the payment of the judgment, first to the owners, second to the attorney's fee, and third to the expert fees.

Plaintiff and its surety have appealed suspensively. In this court they contend: (1) the trial court awards for defects in construction were made without adequate evidence that the defects existed and despite positive testimony the residence was completed to a high standard of workmanship; and (2) a $2,000 award of damages for improper grade, as well as awards for demurrage and an attorney's fee, were erroneous. The owners have answered the appeal, primarily praying that the judgment be amended to include complete demolition and reconstruction of the existing house, and, alternatively, that the judgment in their favor be increased to the sum of $51,459.17, with a corresponding increase in the attorney's fee, and that the award for demurrage be increased to the sum of $3,285.

On August 4, 1966 plaintiff and the owners entered into the written contract for the construction of a residence on property then owned by the latter in the Parish of Orleans at a price of $18,200. Dryades, which financed construction, was a party to the contract and Boston Insurance was the contractor's surety. The contract provided the work was to be done to the satisfaction and under the direction of Dryades' building expert, Sidney A. d'Armas, and in strict accordance with the drawings and specifications identified therewith. Completion was required by February 1, 1967 under penalty of $5 per day liquidated damages for each day the work remained incomplete "without demand or putting in default". The contract further provided for a reasonable attorney's fee, the surety's obligation thereon being limited to ten percent of the amount of the bond.

On February 28, 1967 plaintiff requested acceptance of the house and the fourth payment under the contract. The owners refused to accept; instead they presented the builder with a list of 55 items requiring correction. In March, 1967, after correcting 22 items on the list, plaintiff again requested acceptance and payment and the owners again refused. Plaintiff then instituted this suit.

Twenty-three witnesses testified at the trial. Plaintiff's witnesses who offered pertinent testimony to the issues now involved were: Joseph R. Fritscher, a construction expert; Murvan M. Maxwell, an architect; Jefferson Ruck, a general contractor; Gerald Vanderford, a general contractor; and Joseph J. Krebs, Jr., civil engineer and surveyor. Various salesmen and third-party defendant subcontractors testified as to their specialties, all testifying they had performed in a workmanlike manner. Pertinent testimony offered on behalf of defendants was given by the owners, E. Eean McNaughton, Jr., an architect, Errol E. Kelly, a surveyor, and Erwin Deutsch and Ernest Stahler, construction experts.

The owners complained of 18 deficiencies, including inferior cement work, improper installation of fixtures, materials and/or equipment, unauthorized substitutions not called for by the plans and specifications, defects in the den floor, improper painting, and improper elevation of the slab.

The trial judge viewed the premises after the case had been submitted. In detailed reasons for judgment he outlined individually most of the awards he refused to make, those he made and the amounts thereof, and the testimony on which his refusals and awards were based. He awarded a total of $2,439.18 for unsatisfactory cement work, dressing and finishing, a brick entrance stoop, stripping on a jalousied door, a defect in an imitation marble top in the lavatory, improper installation of a soap dish, lavatory bowl, trap cover and kitchen counter top, the den floor which was not level, repainting certain ceilings and walls, and the substitution *617 of a heating-air condition unit of different make and lesser capacity than agreed upon between the owners and the contractor.

We find unnecessary a detailed discussion of all of the testimony relative to these awards and refusals. It suffices to say that, from our review of the entire record, we are of the opinion the evidence as a whole amply supports these factual findings and conclusions.

The remaining issues to be considered relate to grade (or height of the slab), demurrage, the attorney's fee and the expert fees. The issue relating to the height of the slab is the most serious presented. The slab is 11¼" lower than required by the specifications. The lot on which the house is built slopes from front to rear, the present grade is the highest elevation in the square, higher than any of the seven buildings in the immediate area, and a slab at the specification level would have caused the lot to drain on the adjacent properties to the extent that the owners may have been compelled to erect a retaining wall. The testimony contained in the record, even including that given by Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

North Central Utilities, Inc. v. East Columbia Water District
497 So. 2d 326 (Louisiana Court of Appeal, 1986)
Sweetser v. Streva
450 So. 2d 1007 (Louisiana Court of Appeal, 1984)
State v. Wilco Const. Co., Inc.
393 So. 2d 885 (Louisiana Court of Appeal, 1981)
Klumpp v. Colonial Pipeline Co.
389 So. 2d 457 (Louisiana Court of Appeal, 1980)
Foster v. Jackson
339 So. 2d 865 (Louisiana Court of Appeal, 1976)
G. Salvaggio & Co., Inc. v. Delta Heights, Inc.
277 So. 2d 754 (Louisiana Court of Appeal, 1973)
Irby Steel v. W. R. Fairchild Construction Co.
270 So. 2d 233 (Louisiana Court of Appeal, 1972)
Natkin & Company v. George A. Fuller Company
347 F. Supp. 17 (W.D. Missouri, 1972)
Polmer v. Spencer
256 So. 2d 766 (Louisiana Court of Appeal, 1972)
Elite Homes, Inc. v. Youngblood
242 So. 2d 884 (Supreme Court of Louisiana, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
242 So. 2d 614, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elite-homes-inc-v-herrmann-lactapp-1971.