Norman v. Brown

83 So. 2d 488
CourtLouisiana Court of Appeal
DecidedNovember 2, 1955
Docket8405
StatusPublished
Cited by12 cases

This text of 83 So. 2d 488 (Norman v. Brown) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Norman v. Brown, 83 So. 2d 488 (La. Ct. App. 1955).

Opinion

83 So.2d 488 (1955)

Grover C. NORMAN, Plaintiff-Appellee,
v.
Malone BROWN, Defendant-Appellant.

No. 8405.

Court of Appeal of Louisiana, Second Circuit.

November 2, 1955.
Rehearing Denied November 29, 1955.

*489 Bethard & Bethard, Coushatta, for appellant.

George T. Anderson, Jr., Coushatta, for appellee.

GLADNEY, Judge.

Grover C. Norman entered into a written agreement with Malone Brown to construct for the latter a house according to *490 certain plans and specifications. After completion of the house, this suit was instituted for the net sum of $845.80, of which $400 represented an unpaid balance on the contract, and the remainder for alleged extra work. Plaintiff's suit was defended by Brown, who, in turn, claimed by way of reconvention the sum of $3,501.50 for alleged defects of construction. After trial, judgment was rendered in favor of plaintiff for $845.80 and, in defendant's favor on the reconventional demand for $212. Aggrieved by the judgment so rendered, defendant has appealed to this court.

In our jurisprudence it is well settled that where a contractor sues on a building contract and it is shown that the work delivered is defective or unfinished, the contractor is nonetheless entitled to recover at the contract price if the owner fails to establish damages sustained by reason of the contractor's partial default. The remedy of the owner in such case is for a reduction in the price to an amount necessary to complete the work in accordance with the terms of the contract. Thus, it was said in Cairy v. Randolph, 1851, 6 La.Ann. 202:

"But under the uniform jurisprudence of this court, a suit may be maintained upon a building contract, although the work be defective or unfinished, and the remedy of the defendant in such a case is for a reduction of the price agreed upon to the extent of the damages sustained by reason of the defective performance."

See also: Lillis v. Anderson, La.App. 1945, 21 So.2d 389 and LSA-C.C. arts. 1930, 2769.

Damages for the breach of a building contract where the owner derives some benefit from the defective construction are usually measured by the cost of repairing the defective work. See: Du Bos v. Sanders, 1932, 174 La. 27, 139 So. 651; Merrill v. Harang, La.App.1940, 198 So. 386; Sarver v. Barksdale, La.App. 1946, 24 So.2d 649; Home Services v. Marvin, La.App.1948, 37 So.2d 413; Banks v. Reed, La.App.1951, 52 So.2d 554; Moore v. Usrey & Usrey, La.App.1951, 52 So.2d 551; Montague v. Milan, La.App.1953, 67 So.2d 351. The stated rulings are consistent with provisions in the Civil Code which expressly declare that if a contractor fails to do the work he has contracted to do, or if he does not execute it in the manner and at the time he has agreed to do it, he shall be liable in damages for the losses that result from his non-compliance. LSA-C.C. art. 2769. A substantial compliance with a building contract however, is all that is required. Merrill v. Harang, La.App.1940, 198 So. 386; Walter E. Canulette & Son v. Clesi, La. App.1949, 39 So.2d 853; Stabler v. Keaty, La.App.1949, 42 So.2d 909. With these legal principles in mind we move to consider the circumstances which gave rise to this controversy.

The defendant having decided to build a residence, obtained the plans and specifications of a building he wished to duplicate, and on or about March 1, 1953, he entered into a written contract with plaintiff for the construction of the house on the Ashland Road near Coushatta. The contract, as executed by the parties, reads:

"I agree to construct home for Malone Brown on Highway No. 9 as per plan attached and following specifications:—
"1. All materials to be furnished by owner. All brick-work to be done by another contractor.
"2. Interior Wall Finish—Sheetrock, one coat textone and one coat Super Kemtone, or equal.
"3. Sand floors and apply 3 coats of varnish on all inside woodwork. Owner is to have all hard tile, brick and concrete work done by other contractor.
"4. Owner is to have all electrical and plumbing work done.
"5. Doors and windows and door casings and window casings, all cabinets, book cases & screens for windows *491 are to be factory assembled and will be installed by contractor.
"6. All labor and material for gas to be furnished by owner.
"7. Exterior Finish:—Three coats of the desired kind of paint on all woodwork.
"8. Contractor to be paid $350.00 (Three Hundred Fifty Dollars) at the end of each week by owner until $3,000.00 (Three Thousand Dollars) has been paid. The balance of $400.00 (Four Hundred Dollars) will be paid on completion of building.
"Total contract $3,400.00 (Thirty Four Hundred Dollars).
"G. C. Norman --------------- "Contractor "Malone Brown --------------- "Accepted"

Reference to the agreement discloses that Norman was to become the labor contractor with certain noted exceptions, and Brown was to furnish all materials. Generally speaking, the exceptions relieved Norman of furnishing any materials whatsoever, any brick, tile or concrete work, and all electrical and plumbing work. It was also specified that doors, windows, cabinets, bookcases and screens were to be factory assembled.

Further inspection of the agreement shows that it was not expertly drawn and that many conventional provisions are omitted therefrom. We note especially the omission of services of an architect or other expert to supervise and coordinate the work of the several contractors to the end that defects in construction attributable to one contractor would not affect the work of another. In attempting to evaluate performance under the contract, some consideration also must be given to the illness of Brown at the very commencement of the construction work. At this time Brown underwent surgery for the removal of a kidney stone which required his confinement in a hospital for three weeks, and an additional two weeks at his home. During this interim in order for the work to continue, Brown called upon Norman to assume certain obligations which were not actually imposed in the written contract. We recognize as a proven fact the defendant delegated a certain amount of authority to Ernest May Brown, but the record does not indicate the latter was able to give such attention to the work as should have been expected. All of these conditions perhaps contributed to some extent to the ill feeling which existed between the parties when the contract was completed August 31, 1953.

The defendant before this court does not seriously contest the award by the trial court in favor of plaintiff. It is contended, however, that the court, except to item 6, erred in failing to sustain its reconventional demand for all of the items listed below. The claim evidenced by item 6 was allowed by the trial court. The several items claimed are:

"1. To level floors which necessitates
     correcting foundation,
     placing termite
     shields                           $ 500.00
 2. To get sag out of the roof
     it is necessary to correct
     the foundation, but after
     the foundation is corrected
     additional bracing is
     required and the cost of
     this bracing alone                $ 250.00
 3. 

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Florida Ice MacHine Corp. v. BRANTON INSULATION INC.
290 So. 2d 415 (Louisiana Court of Appeal, 1974)
Maloney v. Oak Builders, Inc.
224 So. 2d 161 (Louisiana Court of Appeal, 1969)
Jim Walter Corporation v. Laperouse
196 So. 2d 539 (Louisiana Court of Appeal, 1967)
Sullivan v. Carpenter
193 So. 2d 105 (Louisiana Court of Appeal, 1966)
U-Finish Homes, Inc. v. Michel
183 So. 2d 101 (Louisiana Court of Appeal, 1965)
Federico v. Kratzberg
163 So. 2d 843 (Louisiana Court of Appeal, 1964)
Southern Patio, Inc. v. Brown
153 So. 2d 924 (Louisiana Court of Appeal, 1963)
Kuhlman v. Talley
145 So. 2d 101 (Louisiana Court of Appeal, 1962)
Lima v. Lemoine
144 So. 2d 719 (Louisiana Court of Appeal, 1962)
Airco Refrigeration Service, Inc. v. Fink
134 So. 2d 880 (Supreme Court of Louisiana, 1961)
Loeb v. Neilson
128 So. 2d 447 (Louisiana Court of Appeal, 1961)
Standard Tile & Marble Co. v. Gray
85 So. 2d 356 (Louisiana Court of Appeal, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
83 So. 2d 488, Counsel Stack Legal Research, https://law.counselstack.com/opinion/norman-v-brown-lactapp-1955.