Opinion

SAMUEL, Judge.

This is a suit on a building contract brought by the owners, husband and wife, against the contractor and his surety. The petition alleges that construction was not in accordance with the written contract, plans and specifications and was not done in a workmanlike manner. It seeks damages, reimbursement for alleged overcharges and deficiencies, liquidated damages under the demurrage clause of the contract, and attorney’s fees. The contractor reconvened for the balance due under the terms of the contract.

There was judgment in the trial court in favor of plaintiffs and against the defendants in solido in the sum of $10,749.61, less a credit of $4,961.00, the last figure representing the unpaid balance of the contract price as stipulated by counsel. Defendants have appealed from this judgment and plaintiffs have answered' the appeal asking that the judgment be amended in their favor to include demurrage for delay in completing the building, the claim for de-murrage having been disallowed by the trial judgment.

On July 26, 1957 plaintiffs entered into a written contract with the defendant, Le-moine, for the construction of a residence in the Parish of Jefferson at a cost of $17,-000.00. Fidelity Homestead Association, which financed the construction, was a party to the contract and the other defendant herein, U. S. Fidelity & Guaranty Company, was the contractor’s surety. The contract protected the interest of the homestead by providing that the work was to be done to the satisfaction and under the direction of the homestead’s building expert. It further provided that the work was to be done in strict accordance with the drawings and specifications identified with the contract. Completion was required within 120 days from the recordation of the contract, which in this instance took place on July 30, 1957, under penalty of $10.00 for each day’s delay in completion beyond the 120 day period. The contract also provided for attorney’s fees.

On October 18, 1957, the building expert was of the opinion that with six minor exceptions, the residence has been substantially completed and stated that it would be in order for the owners to sign the acceptance, provided the contractor and bonding company took cognizance of the exceptions which were to be completed before final payment. On the same date, October 18, 80 days after the contract was recorded and 40 days before the expiration of the allowed construction period, plaintiffs took possession and moved into the premises. They have lived there continuously since that date but they have never signed the acceptance.

Originally a serious complaint was the fact that the roof on one side of the house was located closer to the side property line than permitted by the pertinent building regulations of the Parish of Jefferson. This resulted in numerous negotiations between the parties and their attorneys, all of which failed. However, subsequent to the filing of this suit a waiver of the violation was obtained from the Jefferson Parish Board of Regulatory Inspection which rendered moot that matter, and the resulting claim for depreciation, orig[721]*721inally forming two of the items of damages claimed by plaintiffs.

Several other items claimed by plaintiffs, being credit for electric fixtures ($110.00), and attic fan and shutters ($125.00) and the cost of builders’ risk insurance ($49.61), were admitted by the defendants as being due and were correctly allowed by the judgment, which allowance is affirmed.

The remaining items allowed by the judgment and now involved in the case are: the cost of remedying 54 small items; the cost of correcting a sag in the roof over the rear porch; omission of heater, duct work and wiring for air conditioning as required under the plans and specifications; cost of correcting failure to put gravel under the house slab; cost of an air conditioning unit; attorney’s fees; and penalties under the contract demurrage clause as claimed in the answer to this appeal.

Plaintiff witnesses who offered testimony pertinent to the issues now involved were: plaintiffs themselves, an architect, a general contractor and Mrs. D’Antonio’s brother who had made his home with the plaintiffs. Pertinent testimony was offered on behalf of defendants by the contractor-defendant, his wife, his daughter, a sheet rock finisher, a painter, the owner of an air conditioning service, the manager of an electric company, a terrazzo contractor and the building expert for the homestead.

We are of the opinion that a detailed discussion of the testimony relative to the 54 items and the sag in the roof would serve no good purpose. Although some of that testimony is to the effect that the cost of remedying the 54 items was in excess of $1,500.00 as alleged and claimed in the petition, plaintiffs are limited by the maximum amount prayed for and they have offered sufficient proof to establish that they are entitled to the $1,500.00 as claimed. Nor can there be any real question about the sag in the roof which needed correction and the fact that the cost thereof would be $300.00. Therefore, we will affirm that portion of the judgment which allows these items in those amounts.

Plans and specifications called for a 4 inch layer of gravel under the slab. The testimony of the expert witnesses is that the purpose of this layer of gravel is to break the capillary action of the soil so that the under side of the slab will not be damp or, if dampness does occur, the same will be kept to a minimum. The contractor encountered a rainy spell from the time he began to excavate for the foundation until he poured the concrete for the slab and, with the approval of the' building expert of the homestead, used a proper amount of “sugar” or “spillway” sand as fill instead of the gravel. The homestead expert did not mention the subject of the substitution to the plaintiffs and we find as a fact that the substitution did not have the approval of either of the plaintiffs.

Three expert witnesses gave testimony on the subject with which we are now concerned. The homestead’s expert testified, for defendants, that he agreed to the substitution because he was and is of the opinion that in the area in which the property is located the gravel had no structural value; he felt that there would be a settlement of the soil and, the best water barrier being air space, the gravel would serve no useful purpose.

An architect called by plaintiffs testified that in some areas where the soil is granular gravel under the slab serves no useful purpose because it results in the gravel penetrating into the soil and the desired effect is lost; and to use gravel where the soil is granular and the capillary action is not a problem may not be desirable. He made three inspections, two in January and one in October and found no evidence of dampness. He did point out that this did not mean that under some extraordinary conditions during periods of extreme wet weather some evidence of dampness would not be found. He was of the opinion that to correct the absence of gravel under the slab after construction would be beyond the [722]*722realm of sensible operation but he estimated the cost of such correction would amount to $4,000.00 or $4,500.00.

Plaintiffs’ other expert witness, who was a general contractor, testified that he made two inspections of the premises during which he saw no evidence of dampness. In his opinion, based on his previous experience, dampness will occur when gravel is not placed under the slab. He estimated the cost of correcting the absence of gravel would be $4,000.00.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sullivan v. Carpenter
193 So. 2d 105 (Louisiana Court of Appeal, 1966)
Snow-White Roofs, Inc. v. Boucher
182 So. 2d 846 (Louisiana Court of Appeal, 1966)
Federico v. Kratzberg
163 So. 2d 843 (Louisiana Court of Appeal, 1964)
Southern Patio, Inc. v. Brown
153 So. 2d 924 (Louisiana Court of Appeal, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
144 So. 2d 719, 1962 La. App. LEXIS 2343, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lima-v-lemoine-lactapp-1962.