Du Bos v. Sanders

139 So. 651, 174 La. 27, 1932 La. LEXIS 1608
CourtSupreme Court of Louisiana
DecidedJanuary 4, 1932
DocketNo. 31291.
StatusPublished
Cited by12 cases

This text of 139 So. 651 (Du Bos v. Sanders) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Du Bos v. Sanders, 139 So. 651, 174 La. 27, 1932 La. LEXIS 1608 (La. 1932).

Opinions

LAND, J.

On May 14, 1930, Joseph Scorza, a building contractor, entered into a written contract with defendant to raise and set back a house owned by defendant, at municipal Nos. 1834-36 Annette street, city of New Orleans; to make certain improvements and repairs on the house, “in a perfect workmanlike manner,” for the sum of $4,162; and to deliver same, within four months from date of building permit, free from all liens and claims, “in perfect repair, broom-clean and complete.”

On June 25, 1930, a supplemental written agreement was entered into by the contracting parties for extra work amounting to $224.-40, or a total price of $4,386.40 for the entire building contract.

On November 4, 1930, the contractor assigned to James Du Bos, Jr., plaintiff, his claim against defendant, together with all of his rights under the lien filed by him on the same date, in the mortgage office for the parish of Orleans.

Plaintiff alleges that the contractor completed the work called for by his contracts in a good and workmanlike manner, but that defendant refused to accept same when tendered to her on September 22, 1930.

Plaintiff admits, in his petition, that $1,500 was received on the contract price, and prays for judgment against defendant for a balance of $2,8S6.40, with legal interest from judicial demand until paid, and full recognition of the lien filed against the property.

In her answer, defendant admits that she refused to accept the building when tendered to her, but alleges that it was on the grounds that the contractor had been formally put in default prior to the tender, and that the building had not been completed in accordance with the contract and the plans and specifications.

In her answer, defendant also admits that there is an unmatured balance on the contract of $2,S86.40, being the amount herein claimed by plaintiff; but specially pleads in compensation, against the balance, the following items:

(a) Cost of completion according to contract plans and specifications $1,830.00

(b) Demurrage to date, 60 days at $5.00 per day.................... 300.00

(c) Attorney’s fees incident to completion and enforcement of the contract ....................... 750.00

Total ........................$2,880.00

After deducting her claim in compensation from the amount sued for, defendant deposited in the lower court the balance of $6.40, as the full amount due plaintiff.

The trial judge dismissed, as of nonsuit, both the demand of plaintiff and the plea of compensation of defendant.

Prom this judgment all the plaintiffs have appealed, and defendant has filed an answer to the appeal; and has prayed that the judgment appealed from be amended, either by dismissing plaintiff’s suit, or by maintaining defendant’s plea of compensation, and, as thus aniended, that the judgment be affirmed.

It is alleged in the petition that, under the terms of the building contract, payment of the *31 amount due Joseph Seorza was to be made to tbe joint order of Seorza and tbe Globe Indemnity Company, surety for Seorza under tbe contract; that the Globe Indemnity Company appears herein for the purpose of waiving any of its rights, under the provision authorizing the payment of the amount due by defendant to plaintiff James E. Du Bos, Jr., in accordance with the assignment; and that Seorza appears herein for the purpose of confirming the assignment made by him to plaintiff, James.E. Du Bos, Jr., of his claim against defendant, together with all of his rights und'er the lien securing the payment of the amount due.

On September 15, 1030, defendant appeared before a notary public in the city of New Orleans, and, in an affidavit made by her, declared Joseph Seorza, contractor, to be in default, for failure to complete the contract within four months from May 14, 1930, the date of issuance of the building permit; for refusal and neglect to supply a sufficiency of material and workmen; for unreasonable neglect and suspension of work; and for failure and refusal to follow plans and specifications and to. comply with his contract.

On September 16, 1930, this formal notice of default was served on Joseph Seorza by registered mail, and on the same day was duly recorded in the mortgage office for the parish •of Orleans.

Andrew S. Montz, office architect for twelve years, and architect for the city of New Orleans for the last eight years, was employed by defendant to examine the building, after having received a copy of the plans and specifications and building contract.

On October 8,1930, after having made three or four inspections of the building, Mr. Montz made a report, showing a list of itemized defects and work which was poorly executed.

1. The first defect found by Mr. Montz was that there was no rat-proofing at all. The witness testified that: “They did not put any chain wall in,'which is required by law, to extend two feet below the grade.” This is the requirement for rat-proofing. Tr. 69, 78, 87.

It is provided under the head of “General Conditions,” in the “Specifications,” that: “The contractor is to be governed in all cases in the construction of this work by the building Daws of the City and such Ordinances pertaining to construction of such buildings are to be strictly adhered to in all cases.” Tr. 13.

As Mr. Montz, architect of the city of New Orleans, testified that rat-proofing was required by law, and as the city ordinances as to construction must be adhered to in all cases, as stated in the specifications, it was the duty of the contractor to have put in the rat-proofing.

Hyman Rabinovitz, a graduate of Tulane University, and an engineer and contractor of twenty years’ experience, was furnished with the report of Mr. Montz, architect, and examined defendant’s building and made an estimate as to the cost of completing same, according to plans and specifications.

This witness testified that he made a very careful examination of defendant’s premises and of the plans and specifications. The estimate made by him for rat-proofing, i. e., chain wall and other masonry in connection with the rat-proofing, is $300. Tr. 74.

*33 This item is allowed, as it is required by law.

2. Originally, the plans called for an eight-foot basement, hut the city of New Orleans would not issue a permit, as a basement of that height would be considered as an additional story. So the permit was issued „ with the understanding that the basement would not be over seven feet, sis inches high. On May 26, Í930, defendant wrote the contractor a letter authorizing him “to make the basement at 1834 and 1836 Annette Street 7'-6" in accordance with city laws.”

' The basement was intended to be built by the contractor only 7'-6" high. Mr. Montz, the architect, testified that it was “about seven feet four and a half to seven feet five to some of the joists wfyere the joists are not as deep as in other places.” Tr. 88.

As the contractor has substantially complied with his contract in this respect, nothing more can be required of him. The items of $300 for raising the house and of $300 for changing masonry, due to the proposed raising, are therefore rejected.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wallace C. Drennan, Inc. v. Haeuser
402 So. 2d 771 (Louisiana Court of Appeal, 1981)
Sullivan v. Carpenter
193 So. 2d 105 (Louisiana Court of Appeal, 1966)
Federico v. Kratzberg
163 So. 2d 843 (Louisiana Court of Appeal, 1964)
Lima v. Lemoine
144 So. 2d 719 (Louisiana Court of Appeal, 1962)
Bertrand v. Ducote
128 So. 2d 809 (Louisiana Court of Appeal, 1961)
Bank of Hawaii v. Char
43 Haw. 316 (Hawaii Supreme Court, 1959)
Standard Tile & Marble Co. v. Gray
85 So. 2d 356 (Louisiana Court of Appeal, 1956)
Norman v. Brown
83 So. 2d 488 (Louisiana Court of Appeal, 1955)
Leopold v. Leggio
79 So. 2d 925 (Louisiana Court of Appeal, 1955)
Michel v. U. S. Fidelity & Guaranty Co.
80 So. 2d 173 (Louisiana Court of Appeal, 1955)
Montague v. Milan
67 So. 2d 351 (Louisiana Court of Appeal, 1953)
Goldberg v. Banta Bros.
162 So. 786 (Supreme Court of Louisiana, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
139 So. 651, 174 La. 27, 1932 La. LEXIS 1608, Counsel Stack Legal Research, https://law.counselstack.com/opinion/du-bos-v-sanders-la-1932.